[2000] VSC 311
Supreme Court of Victoria
2000-08-08
Balmford, J.
Original judgment source is linked above.
The Application for Review is disallowed and the decision of the Responsible Authority is affirmed. A permit is granted and directed to be issued.
The development and use of a patrol base and associated works for the Rosebud and District Lifesaving Club in accordance with the endorsed plans.
The permit must contain the conditions set out in the Responsible Authority's notice of decision to grant a permit issued on 27 July 1997 except that the following new condition must be added:
"Beach patrol flags must not be located within 150 metres of the eastern boundary of the McCrae Yacht Club."
The form of that order is considered at paragraphs 128 and following below_._
1. The Tribunal erred in law in failing to hold that by reason of the provisions of section 61(3) of the Planning and Environment Act 1987 ("the P & E Act") it had no power to grant a permit;
2. The Tribunal erred in law in that by reason of section 61(3) of the P & E Act it should have upheld the application for review and pursuant to section 61(3) directed that no permit be issued;
3. The Tribunal misdirected itself as to the content and extent of Mr Nixon's submissions, and in particular only considered his submissions with respect to section 61(2) of the P & E Act and failed to consider and decide upon his and the other Applicants' submissions with respect to section 61(3) of the P & E Act;
4. The Tribunal erred in law in holding that the refusal of the application for consent under the Coastal Management Act 1995 ("the Coastal Management Act") was a procedural deficiency;
5. The Tribunal erred in law in holding that section 62 of the Schedule of the VCAT Act applied to enable it to disregard the provisions of section 61(2) of the P & E Act;
6. If the Tribunal was entitled to apply section 62 of the Schedule of the VCAT Act to enable it to disregard the provisions of section 61(2) of the P & E Act (which it is contended it was not entitled to do), the Tribunal misdirected itself in the exercise of its discretion thereunder;
7. The Tribunal erred in law by having regard to and considering the submissions made by Mr Cicero and "the new consent" after the conclusion of the hearing;
8. The Tribunal erred in law and denied the Applicants procedural fairness by not re-listing the Application for Review for further hearing and providing the Applicants with a proper opportunity of dealing with the submissions made by Mr Cicero and "the new consent".
9. The Tribunal erred in law by failing to have regard to Mr Warfe's response to the submissions made by Mr Cicero and "the new consent" and in particular Mr Warfe's contention that "the new consent" was invalid and improperly given in the circumstances and that were the Tribunal to have regard to "the new consent" the Tribunal must first determine its validity;
10. The Tribunal erred in law by failing to have regard to Mr Rumpf's response to the submissions made by Mr Cicero and "the new consent" and in particular Mr Rumpf's contention that "the new consent" was ultra vires;
11. The Tribunal erred in law by failing, contrary to Clause 42.01-3 of the planning scheme, to have proper regard to the matters specified in Clause 4 of Schedule 25 of the Environment Significance Overlay ("the overlay") and in particular the combined use or reuse of existing buildings;
12. The Tribunal erred in law by failing, contrary to Clauses 36.02-5 and 42.01-3 of the planning scheme, to have proper regard to the matters specified in Clause 21.08 of the Municipal Strategic Statement ("the strategic statement") and in particular the requirements to "ensure preference is given to the reuse of existing structures" and to give effect to "the preferred option to investigate the reuse of existing buildings and the multi use of buildings . . . in preference to a proliferation of separate buildings and structures";
13. The Tribunal misdirected itself in holding that alternative or existing structures should only be considered if the merits of the proposed development could not be sustained because of the environmental impact of the development;
14. The Tribunal erred in law by failing to have regard to the availability and suitability of alternative sites and existing structures and the multi use of buildings;
15. The Tribunal erred in law by failing to have regard to the availability and suitability of the existing building used by the Rosebud Sea-Scouts as an alternative site;
16. The Tribunal erred in law by failing to give proper regard to the availability and suitability of the existing lighthouse dwellings as an alternative site;
17. The Tribunal, not being constituted by members who were judicial members or legal practitioners, erred in that it failed to act in accordance with the provisions of section 107 of the VCAT Act, with respect to questions of law that arose in the proceeding, namely:-
(i) What matters was it required to consider upon the failure of the Rosebud & District Lifesaving Club to produce the documents referred to in the summons issued by the Registrar upon the application of Mr Rumpf?
(ii) Can [Clause 62 of schedule 1] of the VCAT Act be applied by the Tribunal to enable it to disregard the provisions of section 61(2) of the P & E Act?
(iii) Can [Clause 62 of schedule 1] of the VCAT Act be applied by the Tribunal to enable it to disregard the provisions of section 61(3) of the P & E Act?
(iv) Was the refusal of the application for consent under the Coastal Management Act a procedural deficiency?
(v) Was the Tribunal entitled to have regard to and consider the submissions made by Mr Cicero and "the new consent" after the conclusion of the hearing?
(vi) Was the Tribunal obliged as a matter of procedural fairness to re-list the Application for Review for further hearing and provide the Applicants with a proper opportunity of dealing with the submissions made by Mr Cicero and "the new consent"?
* Grounds 1-6 The deemed refusal under the Coastal Management Act;
* Grounds 7-10 The correspondence after the hearing
. . .the appellant, in order to succeed in this case, has to demonstrate to the satisfaction of this Court that the Town Planning Appeals Tribunal went wrong in law in arriving at its decision. It would not be enough for the appellant to show that the Tribunal's reasons for its decision are so expressed as to suggest the possibility that the Tribunal proceeded upon a wrong view of the law. This Court is not entitled to interfere with the decision unless it is satisfied that there was, in fact, a vitiating error of law.
Not every consideration that a decision-maker is bound to take into account but fails to take into account will justify the court setting aside the impugned decision and ordering that the discretion be re-exercised according to law. A factor might be so insignificant that the failure to take it into account could not have materially affected the decision.
The limited role of a court reviewing the exercise of an administrative discretion must constantly be borne in mind. It is not the function of the court to substitute its own decision for that of the administrator by exercising a discretion which the legislature has vested in the administrator. Its role is to set limits on the exercise of that discretion and a decision made within those boundaries cannot be impugned.
Of course, if it is shown that a Tribunal such as the present, in making an order within its competence, has failed to take into account relevant matters, its determination can be reviewed, as in this case, upon an order to review. So much is a settled facet of the relevant jurisprudence. But that course cannot be taken unless it clearly appears that there has been a material error of that kind. Whether or not it has occurred is a matter of fact and not of surmise. Failure in expressing reasons for decision is a very unsure guide to the resolution of such a fact, though in some cases it may be indicative. But, in any case, such a failure to advert to some material circumstance, if it exists, must be weighed in the light of all the circumstances of the proceedings including the nature and extent of the charter of the Tribunal.
Further, it seems established that failure to consider relevant matters can constitute a vitiating error. As Gowans J observed in Wattle Glen Estates Pty Ltd v MMBW (1974) 40 LGRA 104 at 109:
In this connexion reliance was placed on the limited reasons stated by the tribunal at the time of giving its decision as indicating a failure to give consideration to relevant circumstances and considerations advanced in evidence adduced and in arguments submitted for the appellant. If it were established that there was a failure of this kind, there would be, in my opinion, a miscarriage of discretion vitiating the determination: see Harrison v Mansfield [1953] VicLawRp 60; [1953] VLR 399.
On the other hand some caution must be exercised in reaching such a conclusion. The proper test was stated by Sholl J in Yendall v Smith Mitchell & Co Ltd [1953] VicLawRp 53; [1953] VLR 369 at p 379 as adopted by Adam J in McConkey v McConkey [1960] VicRp 47; [1960] VR 295 at p 300 . . .
The true principle . . . must be, not that everything relevant which a magistrate does not refer to is to be taken to have been overlooked, or on the other hand, that it is to be taken to have been considered, but that, if something which should have been considered is not referred to, and the nature of the decision suggests some error, which may have been due to that matter not having been considered as it should have been, or if the magistrate's observations indicate, on a comparison of what he said with what he did not say, that the matter in question has not been considered as it should have been, the appellate tribunal may properly draw such an inference, and the magistrate will have no cause to complain if it does so.
(I should point out that the extract of that test as set out in the report of Stirling Properties is incorrect, in the omission of the word "not" before "been considered" where fourth appearing, and is also confusing in other ways.)
. . . the cases show, as one would expect, that decisions of [the Town Planning Appeals Tribunal] are not to be set aside by over-legalistic analyses of reasons stated or by over-zealous drawing of inferences from things not stated.
In approaching the decision of an expert tribunal I must, I think, not only refrain from making up my own mind on the evidence before it, must not only confine myself to inquiring whether on any reasonable view of the evidence the [Town Planning Appeals] Tribunal's decision on a question of fact can be supported, but must also bear in mind that I am concerned with areas in which members of the Tribunal have special expertise and experience which the legislation plainly intends them to employ. I must, therefore, be slow to conclude that on no reasonable view could this Tribunal decide a particular matter of fact as it has.
Grounds 1-6: The deemed refusal under the Coastal Management Act
(a) to establish the Victorian Coastal Council; and
(b) to provide for the establishment of Regional Coastal Boards; and
(c) to provide for co-ordinated strategic planning and management for the Victorian coast; and
(d) to provide for the preparation and implementation of management plans for coastal Crown land; and
(e) to provide a co-ordinated approach to approvals for the use and development of coastal Crown land.
(a) to plan for and manage the use of Victoria's coastal resources on a sustainable basis for recreation, conservation, tourism, commerce and similar uses in appropriate areas;
(b) to protect and maintain areas of environmental significance on the coast including its ecological, geomorphological, geological, cultural and landscape features;
(c) to facilitate the development of a range of facilities for improved recreation and tourism;
(e) to improve public awareness and understanding of the coast and to involve the public in coastal planning and management
A person must not use or develop coastal Crown land unless the written consent of the Minister has first been obtained.
(1) An application for consent to use or develop coastal Crown land must be made in a form and manner approved by the Minister.
(2) If the responsible authority under the Planning and Environment Act 1987 gives the Minister, the Secretary or the Department of Natural Resources and Environment, as a referral authority under that Act, a copy of an application under that Act for a permit for a use or development of coastal Crown land, that application is deemed also to be an application under this section for consent to that use or development unless consent has already been given under this Division for that use or development.
(1) Subject to sub-section (3), the Minister must make a decision within 28 days after receiving an application for consent to use or develop coastal Crown land.
(2) The Minister may ask for additional information in respect of an application.
(3) If additional information is requested, the Minister must decide the application within 28 days after receipt of that further information.
(1) After considering an application, the Minister may -
(b) consent to the use or development subject to conditions; or
(2) In deciding whether or not to consent to a use or development, the Minister must have regard to -
(b) any Coastal Action Plan applying to the land; and
(c) any recommendation of the Land Conservation Council for the land in respect of which notice has been given to the Department of Natural Resources and Environment under section 10(3) of the Land Conservation Act 1970; and
(d) the purposes for which land was reserved, in the case of land reserved or deemed to be reserved under the Crown Land (Reserves) Act 1978.
(3) If the Minister fails to make a decision within the time required under section 39, the Minister is deemed to have refused to consent to the use or development.
(1) A responsible authority must give a copy of an application [for a permit to use or develop land] to every person or body that the planning scheme specifies as a referral authority for applications of that kind without delay unless the applicant satisfies the responsible authority that the referral authority has --
(a) considered the proposal for which the application is made within the past three months; and
(b) stated in writing that it does not object to the granting of the permit for the proposal.
(c) to refuse to grant a permit on any ground it thinks fit.
(2) The responsible authority must decide to refuse to grant the permit if a relevant referral authority objects to the grant of the permit.
(a) must not decide to grant a permit to use or develop coastal Crown land within the meaning of the Coastal Management Act 1995 unless the Minister administering that Act has consented under that Act to the use or development; and
(b) must refuse to grant the permit if the Minister administering that Act has refused or is deemed to have refused under that Act to consent to that use or development.
Despite anything to the contrary in section 77 or 79, an applicant for a permit for the use or development of coastal Crown land within the meaning of the Coastal Management Act 1995, has no right to apply to the Tribunal for review of -
(a) a decision by a responsible authority to refuse to grant the permit, if the Minister administering that Act has refused or is deemed to have refused to consent to that use or development under that Act; or
(b) the failure of the responsible authority to grant the permit within the prescribed time, if the Minister administering that Act has not consented to that use or development under that Act.
(1) After hearing an application for review, the Tribunal may -
(b) in the case of an application for review of a refusal or failure to grant or a decision to grant a permit -
(i) grant the permit and direct the responsible authority to issue it; or
(ii) grant the permit, direct that the permit must or must not contain any specified conditions and direct the responsible authority to issue the permit; or . . .
(2) In determining a proceeding for review of a decision the Tribunal may, by order -
(c) set aside the decision under review and make another decision in substitution for it; or
(d) set aside the decision under review and remit the matter for re-consideration by the decision-maker in accordance with any directions or recommendations of the Tribunal.
(b) is not bound by the rules of evidence or any practices or procedures applicable to courts of record, except to the extent that it adopts those rules, practices or procedures;
(c) may inform itself on any matter as it sees fit;
(d) must conduct each proceeding with as little formality and technicality, and determine each proceeding with as much speed, as the requirements of this Act and the enabling enactment and a proper consideration of the matters before it permit.
(3) Subject to this Act, the regulations and the rules, the Tribunal may regulate its own procedure.
(4) Sub-section (1)(a) does not apply to the extent that this Act or an enabling enactment authorises, whether expressly or by implication, a departure from the rules of natural justice.
The purpose of this Schedule is to set out variations from Parts 3 and 4 for certain proceedings under certain enabling enactments.
(f) Planning and Environment Act 1987 (except sections 94(5) and 105);
Part 16 - Planning Enactments
The Tribunal has jurisdiction to determine a proceeding under a planning enactment despite any failure to comply with the planning enactment or any other enactment and, in doing so, may determine to disregard that failure if the Tribunal considers it in the interests of justice to do so.
As delegated under Section 40 of the [Coastal Management Act], I consent to the use and development of a patrol base for life saving activities subject to the conditions listed on the attached copy of Consent for Use and Development of Coastal Crown land.
Accordingly, the Department does not object to a permit being granted subject to the conditions of the consent being complied with, and subject to the following conditions being included in the planning permit. . . .
There followed a number of conditions not presently relevant. The attached document ("the delegate's second letter") was headed:
Consent for Use and Development of Coastal Crown land
Consent for: Rosebud and District Life Saving Club Patrol Base
The operative part of the delegate's second letter read:
As delegated pursuant to Section 40 of the Coastal Management Act, I consent to the proposed use and development subject to the following conditions. . . .
There were set out the conditions appearing in the delegate's first letter and some additional conditions.
I have considered the issues raised in your letter and accept that your letter is a fresh application for consent to use and develop coastal Crown land under the Coastal Management Act 1995.
I support the intent of the Coastal Management Act consent issued on 2 March 1999 and, to remove any uncertainties surrounding the earlier consent, my delegate will issue a new Coastal Management Act consent.
A document ("the delegate's third letter") was issued to Mr Cicero and was effectively in the same terms as the delegate's second letter (with some minor changes to the conditions), but dated 2 December 1999. That is the document which is referred to in the Reasons and in the grounds of appeal as "the new consent" and which is considered further below, in a different context, at paragraphs 61 and following. It is sufficient at this stage to say that it was forwarded to the Tribunal by Mr Cicero.
The issue of the new consent does however confirm in the Tribunal's mind that a consent under the Coastal Management Act was always intended to be issued and that subject to the conditions contained within the consent, the proposal enjoys the support of the Minister acting as both a Referral Authority under the Planning and Environment Act and under the provisions of the Coastal Management Act. It is significant that no party submitted that the proposal did not enjoy the Minister's support. Rather the submissions revolved around a technical failure which in the Tribunal's mind constitutes a minor administrative oversight which has no bearing on the consideration on the merits of the proposal.
The Tribunal referred to two provisions of the VCAT Act, section 98(1)(d) and clause 62 of Schedule 1 (see paragraph 24 above), and continued at paragraph 26:
Having regard to the fact that it was clearly the intent of the Minister to issue a consent for the proposed use and development of the land, an intent reinforced by the issue of a new consent, the Tribunal considers that it is appropriate in the circumstances to apply the above provisions [ie section 98(1)(d) and clause 62] and to proceed with the consideration of the merits of the proposal.
The Issues: The Essential Submission of the Plaintiff
Although the Minister is the repository of the power conferred by s 11(1) of the [Aboriginal Land Rights (Northern Territory) Act 1976] and although he may not delegate that power to his departmental officers, the Minister cannot be regarded in his exercise of the power as unaware of information possessed by his Department. As Lord Diplock said in Bushell v Environment Secretary [1980] UKHL 1; [1981] AC 75 at p 95:
To treat the minister in his decision-making capacity as someone separate and distinct from the department of government of which he is the political head and for whose actions he alone in constitutional theory is accountable to Parliament is to ignore not only practical realities but also Parliament's intention. Ministers come and go; departments, though their names may change from time to time, remain. Discretion in making administrative decisions is conferred upon a minister not as an individual but as the holder of an office in which he will have available to him in arriving at his decision the collective knowledge, experience and expertise of all those who serve the Crown in the department of which, for the time being, he is the political head. The collective knowledge, technical as well as factual, of the civil servants in the department and their collective expertise is to be treated as the minister's own knowledge, his own expertise.
Clause 62 of Schedule 1 of the VCAT Act
The Tribunal has jurisdiction to determine a proceeding under a planning enactment despite any failure to comply with the planning enactment or any other enactment and, in doing so, may determine to disregard that failure if the Tribunal considers it in the interests of justice to do so.
The Tribunal has jurisdiction to determine a proceeding under a planning enactment despite any failure of that proceeding to comply with the planning enactment or any other enactment.
If there had been a failure to comply with an enactment (which he did not concede), the failure had not been in the proceeding before the Tribunal, and accordingly, he submitted, clause 62 had no application.
(1) If in any proceeding before the Tribunal it appears to the Tribunal or it is submitted that there has been a failure to comply with this or any other Act or the regulations made under an Act, the Tribunal has jurisdiction to determine the appeal and, if it appears to it just to do so, may determine to disregard that failure.
Thus between 1980 and the enactment of the VCAT Act in 1998, Parliament had several opportunities to consider the provision and to amend it by the addition of the words "of that proceeding" (or perhaps better, "in that proceeding") had it wished to do so. It did not do so, and must be taken to have intended to retain the wide operation apparent on the face of clause 62 as it stands.
The Planning Appeals Act provides that where there has been a failure to comply with certain statutory requirements, the [Administrative Appeals Tribunal] may disregard the failure and amend the document or deal with it as it sees fit. However, the Supreme Court has held in one decision that where a responsible authority has not complied with a mandatory requirement of the Planning and Environment Act the authority's decision to grant or refuse a permit is invalid the permit is void and the tribunal has no jurisdiction to hear the matter. This conflicts with another Supreme Court decision on this question.
The Bill addresses this problem by giving the tribunal clear jurisdiction to hear a matter notwithstanding a failure to comply with any Act or regulation.
The Determination to Disregard the Failure to Comply
The issue of the new consent does however confirm in the Tribunal's mind that a consent under the Coastal Management Act was always intended to be issued and that subject to the conditions contained within the consent, the proposal enjoys the support of the Minister acting as both a Referral Authority under the Planning and Environment Act and under the provisions of the Coastal Management Act. It is significant that no party submitted that the proposal did not enjoy the Minister's support. (Emphasis added).
Use and development control will be implemented via planning schemes established pursuant to the Planning and Environment Act 1987 while ensuring that the landowner - the Crown - retains a veto role.
He submitted that it would be contrary to the legislative intention if that veto were to be circumvented by the operation of clause 62.
Grounds 7-10: The Correspondence after the Hearing
We ask that you advise the Tribunal within the next seven days whether you agree or disagree with the Permit Applicant's contention that the fresh consent has removed the bar that might otherwise have existed under Section 61(3) of the Planning & Environment Act for the Tribunal to now consider the planning merits of our client's application.
The law in Australia now is . . . that there is a strong presumption that an administrative or executive decision-maker, the repository of a statutory power, owes a duty to accord procedural fairness, and in particular a "hearing" in some form or other, to any person affected or likely to be affected by the decision, and not merely in respect of a legal or proprietary interest, even though that person is not directly involved in the decision-maker's proceedings; and a clear contrary legislative intent is required to rebut the presumption: Commissioner of Police v Tanos [1958] HCA 6; (1958) 98 CLR 383 at 395-6; FAI Insurances Ltd v Winneke [1982] HCA 26; (1982) 151 CLR 342 at 360; R v Ludeke; Ex parte Customs Officers' Association of Australia [1985] HCA 31; (1985) 155 CLR 513 at 528_; Kioa v West_ [1985] HCA 81; (1985) 159 CLR 550 at 584, 609-12 and 618-19; Haoucher v Minister for Immigration & Ethnic Affairs [1990] HCA 22; (1990) 169 CLR 648 at 651-3 . . . ; and Annetts v McCann [1990] HCA 57; (1990) 170 CLR 596 at 598.
This is not to say that the Commission is obliged to adhere to the rules of evidence or conduct formal hearings or to be satisfied according to any stated onus of proof. It is clear that the Commission has an "absolute discretion", in the sense that they may devise their own criteria and no appeal is available against their decision, whether it be mistaken or not. . . . Fairness requires that the person affected should, save in an emergency, be given notice by the Commission of its intention to issue a warning-off notice and of the grounds for that proposed action and should be afforded an opportunity to make representations to the Commission on his own behalf, which it must consider before taking action. . . . I do not think that fairness requires in this context an oral hearing though in some circumstances the Commission may well find that it cannot resolve inconsistencies between its information and written submissions from the person concerned without such a hearing. It is however for the Commission itself to devise its own procedures in the light of its obligation to act fairly.
(2) If the parties to a proceeding agree, the Tribunal may conduct all or part of a proceeding entirely on the basis of documents, without any physical appearance by the parties or their representatives or witnesses.
That sub-section is not, in my view, intended to allow the Tribunal to proceed without giving all parties the opportunity to make submissions; the key to its meaning is in the phrase "without any physical appearance".
In what seems to me to have been a well-reasoned response, the Council, by letter dated 8 April 1982 under the hand of Mr LR Boyd, City Engineer, complained that the applicants had "simply felt that they did not get their point across well enough on the day so decided to reopen the matter. This behaviour is considered, at best, totally contrary to the spirit of the appeal system". I feel bound to interpolate the comment that, while it is true that s.25 of the Act gives the Board wide powers to determine its own procedures, e.g. it is not bound to have regard to technicalities or legal forms, and it is not required to conduct proceedings in a formal manner, it does seem to me that, in general, where parties have had ample opportunity to consider the issues involved and to prepare and present their cases on appeal, and the Board has reserved its decision (as it did in this case), the Board should not entertain further submissions. In this case, the City Engineer complained at some length as to the procedure adopted, and in my view, the reasons advanced in support of that complaint were sound.
To protect and enhance the natural ecosystems and landscapes of the coast for the benefit and enjoyment of present and future generations.
* Limit the development of new structures on the foreshore to designated activity nodes where possible.
* Ensure that preference is given to the re-use of existing structures where feasible and the removal of degraded foreshore structures wherever possible.
* Applying a precautionary approach to decision making, . . .
* Avoiding the construction of additional structures on the foreshore except where substantial net benefits to the community and/or coastal environment are clearly demonstrated.
To achieve coordinated development of public and private facilities that increases the sustainable social, economic and recreational value of the coast and foreshore to the community.
* Limit the number of structures within foreshore areas to that necessary to meet demonstrated community needs. The preferred option is to investigate the re-use of existing buildings and the multi use of buildings and structures and the upgrading of existing facilities in preference to a proliferation of separate buildings and structures.
Before deciding on an application to use or subdivide land, construct a building or construct or carry out works, in addition to the decision guidelines in Clause 65, the responsible authority must consider, as appropriate:
* The State Planning Policy Framework and the Local Planning Policy Framework, including the Municipal Strategic Statement and local planning policies.
Before deciding on an application, in addition to the decision guidelines in Clause 65, the responsible authority must consider, as appropriate:
* The State Planning Policy Framework and the Local Planning Policy Framework, including the Municipal Strategic Statement and local planning policies.
* The statement of environmental significance and the environmental objective contained in a schedule to this overlay.
* Any other matters specified in a schedule to this overlay.
Schedule 25 to the Environmental Significance Overlay
Before deciding on an application, the responsible authority must consider, as appropriate:
* The ability to reduce the number of buildings and other structures by combined use or re-use of existing buildings.
* The Victorian Coastal Strategy, Siting and Design Guidelines for Structures on the Victorian Coast (May 1998) and Landscape Setting Types for the Victorian Coast (May 1998).
These extracts constitute only some of the matters which the Tribunal was required to take into account in its consideration of the merits of the Club's proposal.
In the Tribunal's view, in the event that the merits of the proposed development could not be sustained because of the environmental impact of the development, then consideration could appropriately be given to the use of an alternative or existing structure. As will be discussed subsequently the Tribunal does not believe that this is the case. The Tribunal makes two further comments with respect to the proposal for the club to locate within the existing dwellings. Firstly the Tribunal was provided with no evidence as to the availability of these dwellings. Secondly, having inspected the site, the Tribunal considers that the amenity of the Lighthouse precinct could be substantially improved if the Lighthouse dwellings were in fact removed.
He submitted that in the first part of this passage the Tribunal had reversed what was required by the planning scheme. The planning scheme required other sites to be investigated, and their feasibility assessed, before consideration was given to the merits of the proposed new structure. The Tribunal's approach was not consistent with the "precautionary approach to decision-making" required by clause 21.08 of the planning scheme, or with the reference in that clause to "avoiding the construction of additional structures on the foreshore except where substantial net benefits to the community and/or coastal environment are clearly demonstrated".
(1) A question of law arising in a proceeding must be decided by a judicial member or a member who is a legal practitioner.
(3) If a question of law arises in a proceeding where the Tribunal is constituted by a member or members who are not judicial members or legal practitioners -
(a) the question must be decided by another member who is a judicial member or legal practitioner; and
(b) for that purpose only, the Tribunal in the proceeding is to be reconstituted to include that other member.
(4) In this section "question of law" includes a question of mixed law and fact.
(1) Despite section 107(1), if the Tribunal is constituted for the purposes of a proceeding under a planning enactment without a judicial member or a member who is a legal practitioner, a question of law arising in the proceeding may be decided -
(a) by the presiding member if the parties agree; or
(b) in accordance with the opinion of a judicial member or a member who is a legal practitioner nominated by the President.
(2) Section 107(3)(b) does not apply to a proceeding under a planning enactment.
s by another member who is a judicial member or legal practitioner; or
s by the Tribunal as constituted for the purposes of the proceeding, but in accordance with the opinion of a judicial member or a member who is a legal practitioner nominated by the President.
Further, if the question is decided by another member who is a judicial member or legal practitioner, the Tribunal is not required to be reconstituted to include that other member. However, if the question is decided by the Tribunal as constituted for the purposes of the proceeding, but in accordance with the opinion of a member who is a legal practitioner but not a judicial member, that member must be formally nominated by the President.
Notwithstanding the latter fact [the Shire's awareness of the Chief Chairman's view], I am of opinion that the procedure here adopted was so divergent from that which was appropriate that the order nisi ought to be made absolute. . . .
It should go without saying that the reference, and the opinion given in response, must be in writing; the parties are entitled to know precisely what passed. It would be desirable if, as with most cases stated, the terms of the reference were the product of agreement between the parties; in the absence of agreement, there should be submissions as to those terms. The opinion of the Chief Chairman should be given only after the parties have been given the opportunity of making submissions, a course which I am informed is normally followed by the Chief Chairman.
It may well be that the terms of the [AAT] Act in this regard are significantly different from the terms of the statute considered by Southwell J in Shire of Sherbrooke v FL Byrne Pty Ltd [1987] VicRp 29; [1987] VR 353 (to which counsel referred me): but what was said there about procedure may still have some application at least so far as concerns the need (which is always present) to see that the parties do not lose the opportunity of being heard on the question on which the opinion of another is being sought. Perhaps it was unfortunate that no attention appears to have been paid in this case to what was said in Shire of Sherbrooke. For instance, the opinion of Mr Webb appears to have been sought somewhat informally and before at least the responsible authority had made its submissions on the question. Yet once the opinion had been obtained, it would seem that under s.47(1)(c) Mr Buckley was required to decide in accordance with that opinion. Certainly at first glance it appears to be unsatisfactory that only then did Mr Traficante make his submissions on the point and, after that, make application for an adjournment to take legal advice - after the event, as it were. But I have heard no argument on this aspect of the case and only one party is now represented. Moreover, counsel for the responsible authority expressly disclaimed any separate complaint on this score and so I pass it by.
Our reading of the material provided shows two main points of conflict of evidence:
1. Whether consent was sought and obtained by the Tribunal from the parties for the Tribunal to determine the preliminary point of law with respect to the subpoena requiring [the Club] to produce a list of members and any subsequent points of law that might arise in the course of the hearing,
The recollection of both Tribunal Members with respect to the first point is that the matter was stood down to enable us to consult with respect to the subpoena for the list of club members, and that our decision not to take the list was predicated by a clear indication that if in the course of the hearing it became apparent that the list of members was relevant, we would revisit the matter. We are certain that we informed the parties that neither of us were legal members. We are equally certain that we did not seek or obtain leave from the parties with respect to determining questions of law. We discussed the issue of the subpoena during the stand down period with a legal member.
All of the parties consented to the Tribunal hearing and determining [the point referred to in ground 17(i)] and any other questions of law that might arise during the proceedings.
Had that been so (which the response of the Members indicates it was not), such a consent of the parties would have been ineffectual. To repeat, the power conferred by clause 66(1)(a) is for a question of law arising in the proceeding to be decided "by the presiding member if the parties agree". Thus that power is conferred on the presiding member, not on the Tribunal. The parties cannot by agreement confer on the Tribunal as constituted for the purposes of the proceeding the power to decide questions of law. (Although it can in effect do so when there is only one member of the Tribunal as so constituted, so that the Tribunal and the presiding member are one and the same, that was not the case here.)
If the Tribunal is constituted without a legal practitioner and any party withholds consent to the question being determined by the Presiding Member, the parties shall notify the Presiding Member accordingly.
The decision of the responsible authority is varied as set out below.
Rumpf
Mornington Peninsula Shire Council [2000] VSC 311
Body Corporate Strata Plan No 4166 & Ors v Stirling Properties (No 2) [1984] VicRp 73; [1984] VR 903
Harrison v Mansfield [1953] VicLawRp 60; [1953] VLR 399
Heatley v Tasmanian Racing and Gaming Commission [1977] HCA 39; (1977) 137 CLR 487
Kentucky Fried Chicken Pty Ltd v Gantidis [1979] HCA 20; (1979) 140 CLR 675
Minister for Aboriginal Affairs v Peko-Wallsend Ltd [1986] HCA 40; (1986) 162 CLR 24
Shire of Sherbrooke v FL Byrne Pty Ltd [1987] VicRp 29; [1987] VR 353
(1977) 137 CLR 487
(1979) 140 CLR 675
(1986) 162 CLR 24
(1958) 98 CLR 383
(1982) 151 CLR 342
(1985) 155 CLR 513
(1985) 159 CLR 550
(1990) 169 CLR 648
(1990) 170 CLR 596