[2023] VCAT 942
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2023-08-14
Mr J
Original judgment source is linked above.
Builder undertakes renovation and extension of home under contract with owners; owners' claim for defective works in bathroom and new roof; what weight should be given to expert's opinion; builder's right to rectify; owners' obligation to mitigate loss; builder's claim for set off for delay damages under contract.
Robinson v Marcus Property Group Pty Ltd (Building and Property) [2023] VCAT 942
... for builders and building owners to use as a convenient reference to the minimum technical standards and quality of work. The Guide provides references to relevant areas of legislation and gives guidance on areas of building standards that are not covered by legislation. Building work that does not meet the standards outlined in the Guide could be considered defective.
... to help resolve disputes about the quality and standards of work. However, it should be understood that this document is intended as a guide only, all other documents stating statutory and contractual requirements take precedence over the VBA Guide.
... to inform parties as to what is an acceptable standard of workmanship in domestic building work.[4]
WHETHER MR LOVE'S EXPERT OPINION SHOULD BE EXCLUDED
Whether Mr Love has sufficient expertise to provide an opinion?
Why Mr Love referred to a different version of his report than the one filed?
My engagement is confined to that of a Building Consultant ... and therefore have not check or make no comment on: - 1/. The structural integrity of the building; 4/. The site and roof drainage systems...
4. Non Destructive Inspection
My inspection is carried out on a non-destructive basis and excludes anything that would require the removal of any fixture, fitting, cladding, insulation, sisalation, membrane, roof covering, lining material or the excavation of any soil.
12. Exclusions
b) Defects not evident by visual inspection;
d) Defects only apparent in different weather or environmental conditions as to those prevailing at the time of my inspection.
Whether Mr Love's report sufficiently particularised a failure to comply with a requirement of the NCC or an Australian Standard?
Is the builder responsible for the leak through the floor of the bathroom?
Shower recesses and components are defective if they crack, leak or don't perform as intended.
Is the cavity wall of the bathroom suitable for tiling?
What rectification works are required in the bathroom?
Is it necessary to strip, replace, waterproof and retile the walls?
IMPORTANT: Before using over existing paints, membranes, coatings or other surface finishes contact technical department of Gripset Industries for correct advice on surface preparation and suitability.
Is it necessary to remove and replace the floor or the joists below the floor?
I am not a mould specialist; however, it was clearly apparent that what a reasonable person could consider as being mould and a mould smell was clearly present.
What is the cost of rectification works required in the bathroom?
Plumber to remove all plumbing fixtures and store. 5 Hours @ $100.
Carpenter to strip all of room back to frame except for ceiling. 16 Hours @$75.
Carpenter to install new wall to east side of shower enclosure. 8 Hours @ $75.
Mould to be treated by mould expert. One off cost $480. Service Call. Note below.
Plasterer to install new water-resistant plaster to walls. 32 Hours @ $75.
Water proofer to waterproof wet area plaster to AS 3740. One off cost $560. Noted below
Shower screen to be installed. One off cost $590.Noted below in materials.
Electrician to reinstall power fittings. 5 Hours @ $500.[11]
Painter to repaint ceiling and door. 12 Hours @ $75.
Was it unreasonable to rectify the defects in the bathroom?
where [the owner's] refusal to give the builder that opportunity is reasonable or where the builder has repudiated the contract by refusing to conduct any repairs.[15]
42.0 The Builder must fix any additional defects in the Building Works that the Owner notifies in writing within 3 months from the earlier of:
• the date that the Owner takes Possession of the Land or any part of the Land; or
• the date the Builder hands over Possession of the Land.
Was it unreasonable for the owners to reject the builder's offer to rectify the bathroom?
Re Loose Shower Tiles
Further to our previous discussions I can advise the following-
Floor movement has caused the grout to dislodge and allow water to access beneath the tiles and onto the subfloor below.
Course of action-
Remove floor tiles,
Examine and assess substrates inc. waterproofing, cement sheet and timber floor
Replace as necessary
Apply new waterproofing and sealant
Re-tile floor
Apply flexible mastic/silicone grouting
Complete and check for proper operation
Please advise re floor tiles
After removing the tiles in the bathroom examination of the floor top and bottom revealed no mould or structural defect. It is proposed to install new AC sheet, seal , water proof and re tile the area.
Was the leak near the kitchen window caused by defects in the northern roof?
... I would suggest that it is tracking from the flashings around the chimney.
The new metal roof has been installed in such a manner that it is not complaint (sic) with the plumbing code.
The roof flashings to the chimney are not over flashed. The current pressure flashing is not secured at 100 mm centres. I refer the builder to the Plumbing Commissions Web Site, Technical Bulletin 0.03. This bulletin clearly mandates that the flashings cannot be installed as per the installation on site, but rather must be fastened at 100 mm centres.
Further, the Stucco should have been removed where the flashings come in contact with the chimney via a grinder cut into the Stucco and brick wall. An over flashing would then be installed and sealed in place to minimise the potential of water leakage behind the existing Stucco to brick installation.
Is the discharge of water from the northern roof mainly into only one downpipe due to defects in the northern roof?
What is the cost of rectification works required to the roof?
Was it unreasonable to rectify the defects in the roof?
Was it unreasonable for the owner to not give the builder an opportunity to rectify the roof?
IS THE BUILDER ENTITLED TO A SET OFF FOR DELAY DAMAGES UNDER THE CONTRACT OR OTHER COSTS?
37.3 If there is an extension of time due to anything done or not done by the Owner or by an agent, contractor or employee of the Owner, the Builder is, in addition to any other rights or remedies, entitled to delay damages worked out by reference to the period of time that the Building Period is extended and the greater of $250 per week or that amount set out in Item 12 of Schedule 1. Delay damages will accrue on a daily basis.
[1] AG Advanced Construction Pty Ltd v Shao [2018] VSC 116, [66], which also refers to comments made by Sifris J in Christ Church Grammar School v Bosnich & Sehr [2010] VSC 476, [40].
[2] Victorian Civil and Administrative Tribunal Act 1998 (Vic) ('VCAT Act') s 97.
[5] Grilli v Downing [2020] VCAT 704, [142], which references The Gombac Group Pty Ltd v Vero Insurance Ltd [2004] VCAT 2540; The Gombac Group Pty Ltd v Vero Insurance Ltd [2005] VSC 442; Ashjam Pty Ltd v Carroll [2006] VCAT 2612.
[6] The regulations made under the Building Act 1993 (Vic) incorporate the National Construction Code ('NCC'), previously referred to as the Building Code of Australia and the Plumbing Code of Australia. The NCC incorporates a number of relevant Australian Standards ('AS'). Where I refer to the NCC it is also a reference to the Building Code of Australia, the Plumbing Code of Australia and/ or the relevant Australian Standards.
[9] Email from builder to owner dated 5 October 2018.
[10] Reifek v McElroy [1965] HCA 46; (1965) 112 CLR 517, 521-2 as referred to in Olivera v Google Homes Pty Ltd [2015] VCAT 835, [33].
Robinson
Marcus Property Group Pty Ltd
(1965) 112 CLR 517