[2005] VCAT 857
respondent. 1 Application P84/2005 is dismissed. 2 Costs reserved. 3 Any party that wishes to make an application for costs must file and serve such application and supporting submissions by no later than 27...
Revson objected to a planning permit but did not receive the Council's decision notice in time to apply to VCAT. The Council had sent the notice to the Body Corporate Manager because Revson had not provided a postal address. VCAT held that sending the notice to the agent satisfied the statutory requirement to give notice to each objector. The agent's failure to inform Revson was a private communication breakdown and did not amount to a 'material mistake' by the Council. The application to cancel the permit was dismissed for lack of standing.
AI-generated legal information, not legal advice. Zoe can make mistakes. Check the cited source, and for advice about your situation consult a qualified Australian lawyer.
1,848 words · generated 01/07/2026
Revson Pty Ltd owned or occupied nearly all apartments at 622 St Kilda Road, Melbourne, and objected to a planning permit application for Unit 1 to be used as a convenience restaurant. Two identical objections were lodged on behalf of Revson: one by email from Robin Caras (which did not include a postal address) and one through the Body Corporate Manager, Macfarlane & Co Pty Ltd (which listed Revson Pty Ltd as the objector) (Reasons [7]–[9]). The Port Phillip City Council granted the permit and, in compliance with s64(1) of the Planning and Environment Act 1987, sent its notice of decision to the Body Corporate, c/- Macfarlane & Co Pty Ltd on 10 November 2004 (Reason [13]). The Tribunal (VCAT) was told that Revson representatives did not learn of the permit until 17 December 2004, after the 21-day review period had expired; Revson applied under s87 (and s89) to have the permit cancelled on the ground of a "material mistake" in the grant (Reasons [1], [5], [14]). In a directions hearing on 29 April 2005, Deputy President Helen Gibson determined the preliminary issue of standing: whether Revson could rely on s89(1)(b)(iii) because it had not received notice and there had been a material mistake. The Tribunal held that s64(1) required notice to each objector, not each objection, and that sending notice to the Body Corporate Manager, the agent who had lodged an objection on behalf of Revson, fulfilled the notice obligation; the subsequent failure by that agent to pass on the notice did not amount to a material mistake in relation to the grant of the permit (Reasons [10]–[16]). Accordingly, Revson lacked standing under s89(1)(b), and the application was dismissed (Reason [17]).
1 cited instrument linked from this judgment.
The decision turned on statutory construction and the allocation of responsibility for communication between an objector and any agent who lodged objections on their behalf. Two statutory provisions were central:
Deputy President Gibson's first critical interpretive finding was that s64(1) imposes an obligation to give notice to each objector as such, not to every formal lodging of an objection. Where an objector's correspondence does not give a postal address, and where another agent (the Body Corporate Manager) had lodged an objection on the objector's behalf and provided contact details, it was reasonable and lawful for the responsible authority to send the statutorily required notice to that agent (Reasons [11]–[12]). The responsible authority had no direct postal address for Revson at the time it prepared the notice; hence sending notice to Revson via the agent who had lodged the objection met the legislative obligation (Reason [12]).
The Tribunal then distinguished between a failure of the responsible authority to comply with the statutory notice obligation (which could produce a material mistake) and a private communication failure between an objector and its agent (which does not make the responsible authority's conduct a "material mistake" under s89). The agent's apparent failure to pass on the notice to Revson led to the applicant missing the review deadline, but that breakdown was characterised as a private matter for resolution between Revson and the agent; it did not alter the fact that the Council had properly discharged its statutory duty by sending the notice to the agent who had lodged the objection (Reason [14]). The closeness of the relationship between Revson and the Body Corporate Manager was immaterial because the responsible authority could not be presumed to know about that relationship (Reason [15]).
On these grounds Deputy President Gibson concluded there had been no material mistake in the grant of the permit attributable to the responsible authority; accordingly Revson lacked standing to pursue cancellation under s89(1)(b) and the s87 request was unsustainable (Reason [17]).
This decision applies established principles of statutory construction and administrative responsibility in the context of planning notice requirements:
Before this decision, the statutory framework under the Planning and Environment Act required notice to objectors under s64(1), and s89 offered relief where a person was adversely affected by certain errors including "any material mistake in relation to the grant of the permit." Revson foregrounded the precise interaction of those provisions: whether an objector who missed the review deadline because notice was not received could show a material mistake where the notice had been sent to an agent.
After the decision, the clear practical takeaway is that where an objector has engaged an agent or another party to lodge an objection and the responsible authority does not have the objector's own postal address, sending the statutory notice to the agent can satisfy s64(1). The Tribunal's reasoning reinforces a boundary: a later communication failure between agent and principal will not, by itself, render the responsible authority's conduct a material mistake for the purpose of s89(1)(b)(iii), provided the authority properly gave notice as required (Reasons [11]–[16]). In short, this decision tightens the connection between the responsible authority's statutory act (sending notice) and the statutory relief (cancellation for material mistake): the focus is on whether the authority itself erred in giving notice, not on private failures in subsequent communication.
Several practical fact patterns will bring this decision into play:
This judgment does not cite subsequent appellate treatment or indicate it was applied, distinguished or overruled by later decisions within the written reasons. The decision itself is an administrative tribunal determination by Deputy President Gibson and focuses on statutory interpretation of s64(1) and s89(1) in the facts before it (Reasons [10]–[17]). Practitioners should check later authorities and appellate decisions for any refinement or contrary authority when relying on this decision as precedent.
The decision is clear on the specific fact pattern where an agent lodged an objection and the authority sent notice to that agent. However a number of practical and legal questions remain open or only implicitly addressed by this decision:
Practitioners should therefore treat Revson Pty Ltd v Port Phillip CC [2005] VCAT 857 as a clear authority for the proposition that sending notice to an objector's agent satisfies s64(1) where the authority lacks a direct address for the objector, and that private communication failures thereafter do not automatically create a material mistake. However, the decision does not exhaustively cover edge cases about the authority's constructive knowledge, the reliability of agent contact details, or competing reasonable steps the authority might take to notify an objector. In those situations, further authority or careful factual argument will be required.
Section 87 Planning and Environment Act 1987 - Request to cancel or amend person on the basis of a material mistake in relation to the grant of a permit - Section 64(1) Planning and Environment Act 1987 - Notice sent to agent of objector does not constitute material mistake
Pacific Rim Marketing Group Pty Ltd, Davis Prepared Foods Pty Ltd & Subway Developments (East Vic & Tas)
Minister for Planning - Department of Sustainability & Environment, Westpac Banking Corporation
1 Application P84/2005 is dismissed.
2 Costs reserved.
3 Any party that wishes to make an application for costs must file and serve such application and supporting submissions by no later than 27 May 2005. Any response must be filed and served by no later than 10 June 2005. Any party may request a hearing to consider any application for costs or the Tribunal may convene a hearing at its discretion.
4 Liberty to apply.
For Davis Prepared Foods Pty ltd & Subway Developments (East Vic & Tas)
Mr Peter Soding, Town Planner, of Tixxis Consulting
(given orally at the hearing and subsequently revised)
1 This is an application pursuant to section 87 of the Planning and Environment Act 1987 to cancel permit 1265/2004 issued by the responsible authority on 10 December 2004 for use of the subject land as a convenience restaurant with four car spaces in accordance with the endorsed plans.
2 The subject land at 622 St Kilda Road, Melbourne consists primarily of residential apartments, all of which are either owned or leased by the applicant, Revson Pty Ltd, and are operated as serviced apartments by Revson trading under the name of The Punt Hill Group. The exception is Unit 1, which is owned by Pacific Rim Marketing Group Pty Ltd and which was the subject of the permit application by Davis Prepared Foods Pty Ltd for use as a Subway convenience restaurant. Previously Unit 1 had been used as a chiropractic clinic.
3 The purpose of the directions hearing was to consider a number of preliminary issues raised by the respondent/permit holder, the main issue being whether the applicant for review has standing to make this request for cancellation of the planning permit.
4 Section 87(3) of the Planning and Environment Act 1987 sets out the categories of people who may make a request to cancel or amend a permit. The applicant in this case would come within the category of a person under section 87(3)(b) namely any person under section 89. Section 89(1) of the Act provides as follows:
(1) Any person who objected or would have been entitled to object to the issue of a permit may ask the Tribunal to cancel or amend the permit if -
(a) the person believes that the person should have been given notice of the application for the permit and was not given that notice; or
(b) the person believes that the person has been adversely affected by -
(i) a material mis-statement or concealment of fact in relation to the application for the permit; or
(ii) any substantial failure to comply with the conditions of the permit; or
(iii)
any material mistake in relation to the grant of the permit.
5 In the present case the applicant, Revson Pty Ltd, was a person who objected to the grant of the permit and it believes that it has been adversely affected by a material mistake in relation to the grant of the permit, hence coming within the ambit of section 89(1)(b)(iii). The question that must be determined is whether there has, in fact, been any material mistake in relation to the grant of a permit. This is also the ground relied upon by the applicant for requesting cancellation under section 87(1). The material mistake alleged by the applicant is that the responsible authority failed to give Revson Pty Ltd, as an objector, a notice of its decision to grant a permit.
6 The application was made by Arno Caras, Director of Revson Pty Ltd. For the purpose of this application I have treated the applicant as being Revson Pty Ltd, which gives as its address for service in the request as 267 Flinders Lane, Melbourne.
7 The responsible authority received two objections to the permit application which were on behalf of Revson Pty Ltd:
i
Robin Caras Director Punt Hill Apartment Hotels and Serviced Apartments
ii
Ian Macfarlane, Body Corporate Manager of Macfarlane and Co Pty Ltd.
8 Both objections were identical and neither included Revson's Flinders Lane address. Each objection was sent with a covering letter. The first was an email from Robin Caras which stated:
Please find enclosed objection to Grant a Planning Permit to the above Application. Please acknowledge receipt.
9 The second came by fax and then by post from Macfarlane & Co Pty Ltd, signed by Ian Macfarlane, Body Corporate Manager, which stated:
The Body Corporate has been requested by Owners to record concerns regarding this application.
Please refer to the attached S.57 Form listing objections.
These objections are considered important and urgent issues that need to be addressed.
The objector stated on the objection form was Revson Pty Ltd.
10 Section 64(1) of the Planning and Environment Act 1987 provides as follows:
(1) The responsible authority must give the applicant and each objector a notice in the prescribed form of its decision to grant a permit.
11 This provision requires notice be given to each objector, not to each objection. When faced with two identical objections from Revson Pty Ltd, one sent by an individual (Robin Caras) but without indicating that person's relationship to the company, and one from the Body Corporate Manager for the Body Corporate of the whole premises, I find it was reasonable that the responsible authority, should chose the Body Corporate Manager as the address to which to send communications.
12 I also find that the responsible authority could not have given notice direct to Revson Pty Ltd at its Flinders Lane address because it did not have this information. It was therefore obliged to give notice under section 64(1) to Revson Pty Ltd to one of its agents who had lodged the objection on its behalf. It could not have sent the notice to Robin Caras because her email does not include a postal address. It chose to send the notice to the Body Corporate Manager.
13 The notice of decision was sent to the Body Corporate, C/- Macfarlane & Co Pty Ltd on 10 November 2004. On 7 December 2004 the Victorian Civil and Administrative Tribunal advised the Council that no applications for review had been lodged and a planning permit was issued on 10 December 2004.
14 The problem was that the Body Corporate Manager, Ian Macfarlane, apparently did not pass on the information about the notice of decision to Mr or Mrs Caras as representatives of Revson Pty Ltd in time for Revson to lodge an application for review with the Tribunal. Mr and Mrs Caras say that they did not become aware of the Council's decision to grant a permit until 17 December 2004, by which stage the 21 day period for lodging an application for review by objectors had expired. Clearly there has been a breakdown in communication between the Body Corporate Manager and the Body Corporate owners and/or occupier, however this is an issue that must be sorted out between themselves. It is not a circumstance that necessarily means there has been any material mistake in relation to the grant of the permit. The Council's obligation under section 64(1) is to give notice to each objector. It may give notice directly to the objector or to the objector's agent. In the present case, the Council was unable to give notice directly to the objector so it gave it to the objector's agent, namely Macfarlane & Co.
Revson Pty Ltd
Port Phillip CC [2005] VCAT 857
1 Application P84/2005 is dismissed. 2 Costs reserved. 3 Any party that wishes to make an application for costs must file and serve such application and supporting submissions by no later than 27 May 2005. Any response must be filed and served by no later than 10 June 2005. Any party may request a hearing to consider any application for costs or the Tribunal may convene a hearing at its discretion. 4 Liberty to apply.
15 Mr Bock, on behalf of the owner of Unit 1, drew attention to the fact that Mr Arno Caras is the chairman of the Body Corporate and, as director of Revson Pty Ltd, which is the sole occupier of the entire premises at 622 St Kilda Road apart from Unit 1, has a close relationship with Mr Macfarlane as Body Corporate Manager. Given that Revson is the owner and/or occupier of all the apartments except Unit 1, this breakdown in communication is difficult to comprehend. He claimed that it was therefore inexplicable why Mr Macfarlane had not passed on the notice from the Council to Mr Revson.
16 However the closeness or otherwise of the relationship between Revson Pty Ltd and Macfarlane is not relevant to my finding because the responsible authority cannot be presumed to have known this. The Body Corporate Manager was acting as an agent for Revson Pty Ltd. The responsible authority sent the notice required by section 64(1) to the Body Corporate Manager. It had no other postal address for Revson Pty Ltd and the objection by Revson Pty Ltd had been lodged by the Body Corporate Manager on behalf of Revson Pty Ltd. I find that this does not constitute a material mistake in relation to the grant of the permit. Notice of the decision was properly given under section 64(1).
17 Based on my finding that there has been no material mistake in relation to the grant of the permit, the applicant does not have standing to make this application under section 89(1)(b). This also means that the ground relied upon for making the request under section 87(1) is not substantiated either. For these reasons the application should be dismissed.
18 This therefore disposes of the matter and the hearing listed for 24 May 2005 will be cancelled.