DISPUTE - Dispute referred under s 155 of the Building Act 1993 (the Act) between an owner and an adjoining owner in relation to a matter arising under Part 7 of the Act, where the BAB does not have jurisdiction to deal with the matter under any other provision of Part 10 of the Act, concerning costs for assessing proposed protection work.
APPLICANTS Andre Reich and Veronica Angelidis-Reich (Adjoining Property owners)
RESPONDENT Patrick Volpe and Maria Volpe (Subject Land owners)
BEFORE Members H Hodges (panel chair) and P Paras
CITATION Reich & Anor v Volpe & Anor [2025] VBAB 99
Having considered all the submissions and information placed before it, the Building Appeals Board (BAB) determines pursuant to s 161 of the Building Act 1993 (the Act), that:
_____________________ ________________________
footings and bored piers (location as per drawings attached along with this documentation) will be dug with supervision at all times close to the western boundary of property 62 with a 200mm distance away from the boundary, to ensure the safety and structural integrity of current fence and your assets. the current fence will not need to be removed and will be structurally enforced during and throughout the construction to ensure safety to all, we will not need to access your property for this purpose of construction, and security will also be supervised daily to ensure access to construction site are controlled and logged again enhancing the safety of adjoining properties. After piers and footings been completed, a 110mm AFS wall with concrete core fill will be constructed following, and exposed section above the existing boundary fence will be rendered. All construction work will be conducted or supervised by a registered builder as approved and shown on the building permit. Again not require access into your property and proper dust control with water spray will be in place.
(1) The owner must pay to the adjoining owner all costs and expenses necessarily incurred by the adjoining owner in assessing proposed protection work and in supervising the carrying out of protection work in respect of the adjoining property and -
(a) agreed between the adjoining owner and the owner; or
(b) in the absence of an agreement, determined by the Building Appeals Board under Part 10.
(2) The costs and expenses of an adjoining owner which are agreed or determined may be recovered in a court of competent jurisdiction as a debt due to the adjoining owner.
(a) On 12 October 2024 the Applicants provided a copy of the quotation for the work and sought payment from the Respondents.
(b) On 14 October 2024 the Respondents provided an email response but did not agree to make payment for the invoice.
(c) On 17 November 2024 the Adjoining Owners served the first report of the Engineer together with the Form 8 requesting more information for the proposed protection work. A second and third report were later generated and shared with the Respondents on 19 November 2024.
(d) On 19 November 2024 the Respondents indicated a disagreement with the Engineer's costs. The Adjoining Owners responded to the Respondents confirming the requirements of s 97 of the Building Act 1993 (Act).
(e) On 9 December 2024 the relevant building surveyor made a Form 9 Determination pursuant to s 87 of the Act.
(f) On 20 December 2024 the Applicants sent a Fourth report from the engineer to the Respondents. The Applicants further requested $2,100 and a further amount of $4,725 which had not been paid.
(g) On 13 January 2025 the Applicants requested the engineer distinguish costs of assessing protection work from other fees and costs for other matters. The engineer provided a response on the same date confirming all work was related to assessing proposed protection work.
(h) On 29 January 2025 the Respondents offered $2,100 to settle the costs claimed by the Applicants.
(i) On 30 January 2025 the Respondents paid $2,100 to the Adjoining Owners. Accordingly, the Applicants now seek the remaining amount of $4,725.
(a) The reimbursement of protection work notice only becomes due and payable once a registered building surveyor has made a Form 9 Determination.[2] The Respondents rely on the VBA Protection Work Statement 2018.
(b) The Form 9 Determination was made on 9 December 2024.
(c) The Respondents note the Invoice dated 20 December 2024 seeks payment of 19.5 hours at $350 per hour. The Respondents say only 4.3 hours properly relate to assessing protection work and 15.2 hours relate to other work (site visits not undertaken 3 hrs, Report 1 & 2, for 4.3 hours non-protection work, Report 3 - boundary/legal title matters not protection work matters for 1.25 hours and Report 4: post-Determination reporting 6.6 hours not eligible to claim from owner).
(d) The Respondents paid 6 hours which they say is in excess of the 4.3 hours they consider necessary and reasonable. The balance of $4,750 is disputed.
(e) The following table is what the Respondent's consider necessary and reasonable. Further, the Respondents' engineer confirmed the hours dedicated to assessing protection work and which were not:

(f) In the email dated 13 January 2025 the engineer confirmed that all work as noted in the invoices related to assessing the proposed protection work. However, he noted that comments relating to overlooking did not include nay research.
(g) The Gencon report deals with non-protection work related matters including:
(i) Overlooking/privacy screens
(ii) Boundary encroachment
(iii) Drainage systems
(iv) Structural design assessments
(v) Other planning and building works matter outside the Form 7.
(h) The Respondents believe that the costs are outside of market benchmarking and that the hourly charge out rate should be $250.
(i) The Respondents have also included a more detailed table of works that they consider to be non-protection work related matters and reasons for same.
(j) The Applicants made payment without agreement permitted by s 97 of the Building Act 1993 (Act).
(k) The Respondents state the site visit did not occur and it should not have taken 3 hours. Further, no permission was provided to enter their property.
(l) The submissions of the Applicants do not reconcile with Report 1 from the engineer Mr Genitsaris.
(m) The document size referred to by Mr Genitsaris was for overlooking rather than protection work assessment.
(n) The Respondents' engineer provided a report in which he provided examples regarding the work items performed or material sought by the Applicants' engineer which was not required for assessing protection work. This included the following:
(i) a complete set of architectural drawings is not required.
(ii) the engineering drawing notes on drawing no 10 were unrelated to protection work. However, a typographical error was rectified.
(iii) a site inspection was undertaken and updated structural drawings were provided to show the detail of the existing brick wall and proposed structural footing. Piers were introduced to accommodate the angle of repose. Further, a site inspection was conducted and footing probe completed on the boundary steel fence. Piers were introduced to accommodate the angle of repose. The engineer was of the view no underpinning was required for the steel fence footing.
(iv) The engineer formed the view that some of the request of levels of the land and information on the fence footing depth was not reasonably practical. The existing steel fence footing depth is provided on the updated structural drawing, and the existing brick retaining wall footing is much lower than proposed structure footing.
(v) The north (front) of the structure has had additional piers with shallow strip footing adopted into the updated design to accommodate the engineer's concerns. The proposed design is sufficient to control and mitigate the risk of damage to the boundary brick fence footing.
(vi) Current stormwater drainage design complies with the BCA performance requirements.
(vii) Overlooking and setback are not part of protection work.
(viii) Dilapidation and insurance are not part of the Form 7 an 8 process.
(ix) The retaining wall beside retaining wall/fence has had a site inspection and footing probe completed at the boundary of the colour bond steel fence. Updated structural drawings show detail between the existing brick wall and the proposed structure footing. Piers have bene introduce to accommodate the angle of repose.
(x) Update structural drawings show the details between the existing fence and the proposed structure footing. Piers have been introduced to accommodate the angle of repose.
(a) The market guide of $250 per hour at 4 hours should have been sufficient for reasonably incurred fees.
(b) The reasonable hours incurred by Mr Genitsaris would be 4.35 hours.
(c) The owners have paid 6 hours at $350 per hour.
(d) The hours calculated by the Respondents deducted the following:
(i) Report 4 had 6.6 hours billed after the Form 9 Determination which were not for assessing protection work.
(ii) Report 3 had 1.25 hours billed outside protection work definition
(iii) Reports 1 & 2 had client consultations, 50% of which were attributed to non-protection work allowed by owner. Accordingly, 4.3 hours should be removed.
(iv) Invoiced site visit not performed on owner's property.
(v) The owners have deducted procedural administration matters such as comments on Form 6 and 7 service, demand for full architectural drawings, request for full structural set, comment on general note in drawings, request for land levels and re-establishment survey/boundary, drainage items, overlooking or setback issues, debris and concrete spill protection, dilapidation report, insurance, reviewing land survey, Report 4 includes 6.6 hours after Form 9 Determination was not challenged.
APPLICANTS' SUBMISSIONS IN RESPONSE (in summary form)
(a) The protection work costs were necessarily incurred.
(b) The Applicants deny the Form 9 limited the ability to challenge the scope of the protection work.
(c) The reports were all necessary to assess the protection work
(d) The Applicants do not accept the market benchmarking put forward by the Respondents.
(e) The Applicants required a professional opinion of a qualified engineer. There is nothing in the engineer's invoice which suggests it is not necessarily incurred in assessing the adequacy of proposed protection work. The engineer had to spend more time due to the inadequate material and need to revise protection work.
(a) Whether the Applicants were required under s 97 of the Act to attempt to obtain the Respondents' agreement on costs or seek several quotations for assessing protection work.
(b) Whether the costs incurred by the expert were necessarily incurred in accordance with the requirements of s 97 of the Act.
Whether the Applicants were required to attempt to obtain agreement on costs or seek several quotations prior to arranging an expert opinion
...to allow for the expenses of an adjoining owner incurred in assessing proposed protection work to be re-imbursed.
Whether the costs incurred by the expert were necessarily incurred in accordance with the requirements of s 97 of the Act
(a) permanent or temporary work of -
(i) underpinning, including the provision of vertical support, lateral support, protection against variation in earth pressures, provision of ground anchors and other support for adjoining property; or
(ii) shoring up of adjoining property; or
(iii) overhead protection for adjoining property; or
(iv) other work designed to maintain the stability of adjoining property or to protect adjoining property from damage from building work; or
(b) any work or use of equipment necessary for the provision, maintenance and removal of work referred to in paragraph (a) -
30. ......The Macquarie Concise Dictionary defines the word necessarily as:
1. by or of necessity; 2. as a necessary result.
1. that cannot be dispensed with; 2. happening or existing by necessity; 3. acting or proceeding from compulsion or necessity; not free; involuntary...
... to establish a successful claim for costs of assessing protection work, the Board must be satisfied of the following:
(a) The claim must be for assessing the protection work and not extraneous matters.
(b) The costs must be necessarily incurred not relate to speculative future costs.
(c) The costs were required to achieve the function of assessing the protection works.
Lines 1 to 3 are considered to have been time spent for engineering services provided for the review of proposed PW, initially proposed as part of the Form 7 and documents which accompanied the Form 7; We note that Invoice B241001 dated 11/11/24 states "initial fee as quoted 6hrs @$350/hr" and $2,100 was charged. We therefore consider that the time spent for these 3 lines, being 6.5hrs, is for the services quoted for the amount of $2,100, noting however that Invoice B241001a, dated 20/12/24, indicates 6.5hrs;
We further note that Engineering Report 1 included advice in relation to non-protection work items and that we consider that 3 hours for travel and time on the adjoining property site would be at an upper limit. Based on the above, we accept the amount of $2,100 that was quoted based on 6.0hrs (but 6.5 hrs were spent) to be reasonable. We also note that this amount has been paid by the Respondent.
We accept that services by Mr Genitsaris would have been required to review the response from the Respondent's Architect and Engineer, and that 0.75 hours is reasonable.
In general, we accept that additional assessment of proposed Protection Work following the issue of ER1, and therefore costs incurred, would have been required, additional to the initial assessment, covered by Engineering Report 1.
A total of 1.4 hours has been charged for consultation with the client at this stage, presumably to discuss the response received to Engineering Report 1 and for the preparation of Engineering Report 2. Based on the response and the content of Engineering Report 2, we do not consider it reasonable that 1.4 hours is required for discussions with the client (Applicants) in relation to the assessment of proposed protection work. Instead, we consider that 0.75hrs is a reasonable amount of time to discuss matters in relation to the assessment of proposed PW.
We accept that a second report (ER2) was required to be prepared, based on the response to ER1, and we accept that 3.0hrs is reasonable for the preparation of Engineering Report 2. This would have required time to review the response to ER1 and further updated documents and a new Form 7.
19 November 2024 report 3 (ER3) & consult with client
We consider it reasonable that 1.25 was taken for review of the further response, preparation of Engineering Report 3, and consultation with client. We note that structural drawings were amended and issued at this stage, to include the piers at the boundary between the two sites.
As the Form 9 was issued on 9/12/24, we consider that the period for assessing proposed protection work has, in principle, ceased and assessment or review of proposed Protection Work is fundamentally for the purpose of any appeal which may be actioned. Therefore, we do not consider that the preparation of Engineering Report 4 is part of the assessing proposed protection work.
18 December 2024 View determination and documents
11.75@ $350 = $4,112.50, less $2,100 already paid, balance owed = $2,012.50
[1] Clause 17 of Schedule 3 to the Building Act 1993 provides: 'Unless the Building Appeals Board otherwise determines, a party to a proceeding before the Board must bear his, her or its own costs'.
[2] See paragraph 12.5 of the Respondents' Statement of Defense
[4] See for example; Maniatis & Anor v Mitchell [2022] VBAB 94
[5] Yu & Anor v Pantazopoulos & Anor [2023] BAB 71.
[8] See for example Maniatis & Anor v Mitchell [2022] VBAB 94.
�Reich & Anor
Volpe & Anor [2025] VBAB 99;