Rehman v F&F Smart Homes Pty Ltd
[2023] NSWCATCD 12
At a glance
Source factsCourt
NCAT Consumer and Commercial
Decision date
2022-12-21
Source
Original judgment source is linked above.
Judgment (15 paragraphs)
Contents Topic Paragraph Outline 1 Hearing 3 Jurisdiction 10 Relevant law 11 Lay evidence 16 Mr Rehman 16 Mr Khan 20 Expert evidence 31 Owner's submissions 32 Builder's submissions 43 Submissions in reply 48 Consideration 51 Assessment of witnesses 51 Work order or money order? 62 Contested items 70 Low e glass 72 Feature tiles 74 Insulation 79 Drainage 90 Scaffolding 99 Retaining wall 100 Concrete path 107 Defective work 112 Unit 1, internal 113 Unit 1, external 120 Unit 2, internal 125 Unit 2, external 134 Incomplete work 141 Period of delay 144 Claim for unit 2 152 Claim for unit 1 157 Summary 165 Costs 167 Orders 169
Outline
- These proceedings relate to the construction of duplex residential properties in Schofields. The owner alleged defective work, incomplete work, and delay.
- After considering the evidence, and having regard to the submissions, the Tribunal determined that a work order should be made in relation to the defective work, and that there should be a money order in relation to the remaining claims of the owner.