[2025] WASC 174
General information, not legal advice.
Supreme Court of WA
2025-05-14
Cobby J
Original judgment source is linked above.
To assist in the funding, Mr Hutson and I will likely draw on the USD 7.0 million facility from Taurus to ensure there is sufficient funds to cover all costs. The Administrators have not previously drawn down such account.
Richard and Rob
Please find the updated cash flow forecast attached.
The headline is that we will need to draw down the VA facility to cover November month end payments unless we want to seek to defer Byrnecut (and pay them interest under the contract). However, given the road is closed and we are already behind on haulage, I suggest we draw down the full USD 7.0 million as I suspect we will drop $5.8 million in receipts due to haulage/weather.
Cash flow comments
Abra reported negative EBITDA in October of $3.2 million. Capex costs are also up with the TSF extension and raise bore works underway.
Cash receipts MTD are behind prior estimates. We should have three invoices issued by now ($12.6 million) - but the HC-2 was only issued to MRI yesterday, and even that was below what we would hope for due to only barely getting 2,500 WMT within proximity of Port.
Lead prices are off which is hurting revenue. LME pricing is currently USD1,940 /tonne. Forward pricing is also flat at USD1,983 for three month contracts.
Byrnecut's costs for October include a back charge for roof support that was missed in its September claim, a $732k excl GST impact not previously accounted for. The cheque this month is $8.7 million ex GST.
Lambton Construction is well ahead of forecast on the TSF works. Its claim was $400k higher than forecast based on last progress claim estimates provided. We had expected more work occur in December/ January, but at this rate, the costs will be largely incurred this year.
Ciro has also flagged potential delay claims by Raisebore Australia - in the order of $150k. He will work through this as he thought much of the downtime was caused by Raisebore Australia.
Administration funding facility
The VA facility was initially sized off high-level pre-appointment cash flow forecast which was rolled out to August and included no capex other than Byrnecut mine development.
The VA facility has a utilisation period of six months; which expires on 11 December 2024. Clutz is drafting and amending deed to address this - but I think we need to draw down the facility in full which will negate the requirement to amend the facility.
Regardless whether or not we are to trade-on or place the mine into care and maintenance, we need more funding. We have less cash and less concentrate today than we did at the start of the job - and the mine is now loss making having previously tread water.
Subject to where matters get to tomorrow with Byrnecut, we need to start thinking about pressing Taurus for an appropriate facility to operate through the wet season/ place the mine into C&M and to ensure you are off risk.
As foreshadowed, we will need to draw down the administration facility shortly owing to challenging weather conditions which have compounded the operating loss recorded in October and the build of concentrate at site (effectively locking out cash and inventory). The cost of extending the TSF [that is, tailings storage facility] and completing the raised bore work (both essentially to operating beyond December) is also depleting our cash position. Back-charged September roof bolt costs of $730,000 has also impacted the position compared to prior forecasts.
In view of the urgency of the funding requirements, the requirement for the administrators to seek s 447A relief from personal liability in relation to the increase of US$10 million was a condition subsequent rather than a condition precedent.
The parties acknowledge that the Administrators may, after the Effective Time, apply for any court order (including pursuant to section 447A of the Corporations Act), which they consider necessary in respect of the increase to the Commitment (including to ensure that any limitation of liability set out in the Facility Agreement remains effective) effected by clause 8 of this document and that they may disclose this document and any other Finance Document to the court to the extent necessary to do so.
The Administrators undertake to promptly advise the Lender in writing whether or not they will apply for a court order under paragraph 9 and, if such application is made, to provide the relevant court orders to the Lender promptly after such orders are made, and in any event, within two Business Days of the relevant orders being made.
(1) the first plaintiffs have entered into a funding agreement in their capacity as joint and several administrators of the company, which is also party to the funding agreement;
(2) Taurus will make available for drawdown a further US $10 million to the first plaintiffs, for which interest will be charged in the same manner as funding provided by the lender to the company under the original funding agreement, with no additional security being provided for the loan;
(3) the varied funding agreement sets out how the loan can be accessed, what the funds may be used for, and provisions for its repayment.
I certify that the preceding paragraph(s) comprise the reasons for decision of the Supreme Court of Western Australia.
[1] References to statutory provisions are to the provisions of the Act unless otherwise stated.
[2] Although Mr Tucker refers to the email as having been dated 20 November 2024, the date of the email does not appear on the attachment (other than it follows an email which was sent at 7.40 am on 20 November 2024) and the cash flow to which it refers appears to have been dated 15 November 2024.
[3] Secatore, Re Fletcher Jones & Staff Pty Ltd (administrators appointed) [2011] FCA 493, 23.
[4] Mentha Re Griffin Coal Mining Company Pty Ltd (administrators appointed) [2010] FCA 1469; (2010) 82 ACSR 142, 30.