[2025] QCAT 208
General information, not legal advice.
Queensland Civil and Administrative Tribunal
2025-05-30
Original judgment source is linked above.
CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - THE CONTRACT - CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS - OTHER MATTERS - where the contractor engaged a sub-contractor to re-roof the owners' home - where the contractor issued progress claims for the final two stages of the contract including practical completion - where the owners complained about the standard of work and refused to pay - where new sub-contractors were engaged to perform rectification work - where the certifier issued a Form 21 - where the owners engaged a roofing contractor who reported defective work - where the contractor instituted proceedings claiming payment of the stages of work and in the alternative a claim in quantum meruit - where the work as rectified was sufficient to entitle the contractor to claim the stage payments - where the contractor had not utilised the contractual procedures entitling payment pursuant to contract - where the contractor was entitled to claim in quantum meruit for the value of work done - where a claimed variation was not allowed because the contractor failed to establish that the work was not already within the scope of work of the contract - where there was minor defective work with battens and evidence of swarf left on roofing sheets but no evidence of cost of rectification for that - where the claim for interest was not under the contract but under general law and therefore to be calculated pursuant to s 54(1)(c) Queensland Building and Construction Commission Regulation 2018 (Qld)
Cochrane v Lees [2021] QCATA 74
Harrison v Meehan [2017] QCA 315
Mann v Paterson Constructions Pty Ltd [2019] HCA 32 Miller v Lida Build Pty Ltd [2015] QCATA 137
Mondel v Steel [1841] EngR 61; (1841) 8 M & W 858; 151 ER 1288
Waterways Authority of New South Wales v Coal & Allied (Operations) Pty Ltd [2007] NSWCA 276
Worthington v Ryan; Ryan v Worthington [2021] QCATA 138
... that stage when:
a) The works are complete in accordance with the contract and all relevant statutory requirements, apart from minor omissions or minor defects, the rectification or completion of which do not prevent the works from being used for the intended purpose; and
b) If the owner claims there are minor defects or minor omissions, the contractor gives the owner a defects document.
Some of the battens off the northern valley have been re-used. However, given the valley is a low load-width area and the spacing between the existing holes appears acceptable, in my opinion, these battens are sufficiently securing the sheeting and will not require replacement.
... there's a few deciding factors about whether you need a doubler batten, and that's the spacing of the hole. Now, the issues with yours was the ridge cap. So given that the ridge cap and the spacing - it hasn't - it - it's not as overly loaded as a normal batten ....
...
Ms Tummon: ... So there must've been an area in ‑ ‑ ‑?‑‑‑Yep.
‑ ‑ ‑ the roof you said to do double battens - one you could definitely see - one or two?‑‑‑Yeah, and it was pretty well straight above your manhole, from what I remember, was the - the ‑ ‑ ‑
Yeah?‑‑‑The batten I asked to be done. Yes.[3]
...replace the solar panels with current approved panels and install the system compliant with the current standards. Due to government renewable energy discounts for new systems it is more cost effective to replace the inverter at the same time and install a complete new system.
(3) Without limiting the tribunal's powers to resolve the dispute, the tribunal may exercise 1 or more of the following powers -
(c) award damages, and interest on the damages at the rate, and calculated in the way, prescribed under a regulation;
(1) For section 77(3)(c) of the Act, interest is payable on the amount of damages awarded -
(a) if the parties have entered into a contract - at the rate provided under the contract; or
(b) at the rate agreed between the parties; or
(c) otherwise - at the rate of 10%.
(2) The interest is payable on and from the day after the day the amount became payable until and including the day the amount is paid.
Did the learned Member err in allowing interest from the date of the decision?
[35] The Millers contended that the learned Member erred in law in allowing interest on the awards of damages in their favour from the date of the decision rather than the date of the 'alleged date of practical completion' because Lida Build was awarded interest on amounts awarded to it from that date.
[36] We are not satisfied that this is a demonstrated error.
[37] The Tribunal has power to award interest on damages at the rate and calculated in the way, prescribed under regulation 34B of the Queensland Building and Construction Commission Regulations 2003 (Qld). Regulation 34B(2) provides that interest is payable on and from the day after the day the amount became payable. Until a decision to award damages is made no amount is payable.
[55] This being a claim for unliquidated damages, an amount became "payable" only when there was an amount which had been fixed by an assessment of damages. Regulation 34B is in different terms from s 58(3) of the Civil Proceedings Act 2011 (Qld), which provides that the court may order that there be included, in the amount for which judgment is given, interest at the rate the court considers appropriate for all or part of the period between the date when the cause of action arose and the date of judgment.
[1] The builder objected to the owners' statement of evidence attaching without prejudice correspondence dated 7 July 2022 from the builder to the owners. A statement of evidence of Mr Enriquez, the builder's operations manager, attached the same without prejudice correspondence objected to however. The statement of evidence has been admitted into evidence in full. The builder's objection cannot be sustained. Privilege has been waived by implication. The correspondence is available for consideration. The correspondence proposes a settlement of the dispute and return of the builder to install doubler battens and also refers to the builder having issued invoice 598 claiming $2,962.46 for practical completion stage on 30 May 2022. The invoice itself, 598, is also attached to Mr Enriquez' statement of evidence. The invoice bears date 5 May 2022, not 30 May 2022, which latter date postdates the issue of the Form 21, but not the former.
[2] Not put in evidence through the statement of evidence of Mr Enriquez but included as part of the without prejudice material attached to the owner's statement of evidence the subject of objection at hearing.
[4] Cochrane v Lees [2021] QCATA 74, [45].
[5] And see Waterways Authority of New South Wales v Coal & Allied (Operations) Pty Ltd [2007] NSWCA 276, [220] (McColl JA).
RA Coastal Builders Pty Ltd
Tummon & Anor [2025] QCAT 208