Separate Question 1On 14 February 2012, I heard oral argument on a separate question in these two proceedings, which are travelling together. The parties were directed to file supplementary written submissions, and they did so. the decision remains reserved, but the urgency of it is accepted by the Court. 2The respondent sought to re-list the matter before me on 29 February to clarify that it wanted to be heard before any consequential orders are made, following publication of my decision answering the separate question. The applicant agreed on 29 February to that course.
Notice(s) to Produce 3For convenience, as I had some recent knowledge of the matter, the Registrar also referred to me two notices of motion ('NOM') regarding production of documents in the proceedings. Those documents would not have any relevance to the separate question so I dealt with the motions as the rostered Duty Judge. Both were filed in the Allandale proceedings (30853 of 2011) alone, as consideration is being given to possible discontinuance of the Quarry Products proceedings (30851 of 2011). 4The respondent's NOM filed 2 February seeks an order that the applicant(s) produce for inspection within 2 days " the documents requested in the respondent's letter dated 3 November 2011 ". 5The applicant's Amended NOM filed in court on 29 February seeks to set aside that letter of 3 November 2011, to the extent that the Court finds it to be a Notice to Produce ('NTP'), as defined in Uniform Civil Procedure Rules 2005 ('UCPR') 21.9 & 21.10. It also seeks to set aside the respondent's NTP dated 16 February 2012 (copy tendered on the motion as Exhibit R2 ). 6These Notices or purported NsTP concern the dispute between the parties as to the Market Value of resumed land on which there is a quarry.