[2025] VCAT 978
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2025-10-31
Original judgment source is linked above.
DOMESTIC BUILDING: issue as to which party terminated the contract; consideration of the term 'repudiation'- Koompahtoo Local Aboriginal Land Council v Sanpine Pty Limited (2007) 233 CLR 115; [2007] HCA 61 referred to; applicant builder's director issued an End of Contract Notice but denied it operated as a notice of termination of the contract; issue to be viewed objectively- Laurinda Pty Ltd v Capalaba Park Shopping Centre Pty Ltd (1989) 166 CLR 623; [1989] HCA 23, [14].;held-the respondent owners lawfully terminated the contract when they accepted the builder's repudiation contained in the End of Contract Notice.
Previan Property Group Pty Ltd (ACN 634 838 609) v Saydam (Building and Property) [2025] VCAT 978
(a) the applicant is not entitled to any extension of time in relation to the suspension of the works of 67 days, or at all;
(b) the applicant is entitled to an extension of time by consent of 14 days in respect of the COVID lockdown for the period 20 September 2021-4 October 2021;
(c) the applicant is entitled to an extension of time by consent of 5 days in respect of a delay arising from the upgrade of the doors requested by the respondents;
(d) the applicant is not entitled to an extension of time in relation to delays in delivery of timber for the project of five-weeks, or at all;
(e) the applicant is entitled to an extension of time of 14 days in relation to the requirement to drill through rock and associated engineering issues;
(f) as the initial contract completion date of the contract was 10 April 2022, the date for completion is extended to 13 May 2022.
(a) the respondents terminated the contract on 4 June 2022; and
(b) the termination was lawful.
(a) the legality of the applicant's suspension of the works;
(b) the applicant's other claim for extension of time which were not accepted by the respondents; and
(c) the questions of who terminated the contract, and whether the termination was lawful.
THE LEGALITY OF THE APPLICANT'S SUSPENSION OF THE WORKS
As mentioned, if I don't receive an email by 4pm today stating the invoice will be paid, all work will be stopped immediately and the owners will be liable for late payment interest, delay damages and any other theft that may occur because us not being able to proceed with the work to complete the job.
THE CLAIMED 67 DAYS EXTENSION OF TIME BY REASON OF THE SUSPENSION OF THE WORK.
THE BUILDER'S OTHER CLAIMS FOR EXTENSIONS OF TIME
Claim for extension of time in respect of delivery of timber
The builder's contention that the owners are deemed to have accepted the 5 week timber delay.
(a) interest for late payment of the fixing stage invoice calculated at $2,792.24 on the basis of a 5.5 week delay;
(b) delay damages at $500/week from 23 March 2022 to 14 May 2022, a total of 9.5 weeks $4,318.23
(c) renewal of Public Liability Insurance due to project delays $1,727.26
(d) an administrative fee to put the trades on hold of $318.18; and
(e) an administrative fee to get the trades to renew of $318.18.
(a) clause 30 - failure to pay progress payments;
(b) clause 30.1 - failure by the owners to give the "Lending Body an authority
(c) clause 34.3 - the builder's right to an extension of time;
(d) clause 34.4 - failure to pay delay damages.
(a) the builder had repudiated the contract on the basis 'that it failed to proceed with the Building Works competently and diligently, suspended the Building Works unreasonably and finally has shown itself as unable or unwilling to complete the Building Works';
(b) the builder has failed to follow the procedure set out in clause 42 of the contract to end the contract, and this constituted a further repudiation of the contract;
(c) the builder is precluded under clause 42.3 of the contract from ending the contract while it is in substantial breach itself (noting that the builder has suspended works without basis and/or failed to proceed with the building works diligently and/or is unable or unwilling to complete the works);
(d) the fixing stage invoice has been paid;
(e) by serving the notice, the builder has itself repudiated the contract, and the owners accept that repudiation; and
(f) the owners otherwise reserve all rights to seek resultant loss and damage.
The term repudiation is used in different senses. First, it may refer to conduct which evinces an unwillingness or an inability to render substantial performance of the contract. This is sometimes described as conduct of a party which evinces an intention no longer to be bound by the contract or to fulfil it only in a manner substantially inconsistent with the party's obligations. It may be termed renunciation. The test is whether the conduct of one party is such as to convey to a reasonable person, in the situation of the other party, renunciation either of the contract as a whole or of a fundamental obligation under it. ... Secondly, it may refer to any breach of contract which justifies termination by the other party. (Citations omitted)
Repudiation is not ascertained by an inquiry into the subjective state of mind of the party in default; it is to be found in the conduct, whether verbal or other, of the party in default which conveys to the other party the defaulting party's inability to perform the contract or promise or his intention not to perform it or to fulfil it only in a manner substantially inconsistent with his obligations and not in any other way.
(a) has failed to complete the building works within the building period;
(b) it is unable or unwilling to complete the building works;
(c) alternatively, the builder is unable or unwilling to rectify and/or complete defective and incomplete works as asserted in the notice (and relies upon the report of Mr Romano);
(d) alternatively, the builder is in substantial breach of the contract because of service of the purported notice on 18 May 2022 in circumstances where the owners are not in default under the contract, there exists no basis upon which the builder can end the contract and has failed to follow the procedure set out at clause 42 of the contract; and
(e) the owners place the builder on notice that if the builder remains in breach for 10 days after the date of the notice, then it is the owners' intention to bring the contract to an end
IMPACT ON THE ASSESSMENT OF DAMAGES ARISING FROM THE FINDING THAT THE OWNERS LAWFULLY TERMINTED THE CONTRACT.
The rule of the common law is, that where a party sustains a loss by reason of a breach of contract, he is, so far as money can do it, to be placed in the same situation, with respect to damages, as if the contract had been performed.[3]
[2] (1989) 166 CLR 623; [1989] HCA 23, [14].
[3] [2009] HCA 8, [13].
[4] [1848] EngR 135; (1848) 1 Exch 850 at 855 [154 ER 363 at 365].
Previan Property Group Pty Ltd (ACN 634 838 609)
Saydam
(2007) 233 CLR 115
(1989) 166 CLR 623