[2025] VSC 436
General information, not legal advice.
Supreme Court of Victoria
2025-07-22
Stynes J
Original judgment source is linked above.
(a) The work the subject of the Value Management Adjustment ('VMA Work') forms part of the agreed scope of work under the Contract.
(b) Unsurprisingly, therefore, on the proper construction of the Contract, there are no provisions that govern the valuation of, or the adjustment to the contract sum to account for, such works.
(c) The provisions relied on by Little Hardiman Street are inapplicable to the VMA Work.
(d) Therefore, the Adjudicator did not err.
D.3.1 The VMA Work forms part of the agreed scope of work under the Contract
(a) item 1 of the Brandtman Report concerns a change to the brick tile finish from "Brick snaps, case‑in on Precast panel" to "Brick + rail system". That item relates to item 46 of Part F which provides: "Alternative brick and brick snaps have been allowed for. Samples to be supplied to Architect for review and approval before ordering."; and
(b) item 2 of the Brandtman Report concerns a change to the metal cladding from "standing Seam metal Cladding - 28mm rib height, pan width 180mm, 15mm construction grade substructure" to "Archlad Cliptray - 48mm rib, pan width 275mm". That item relates to item 81 of Part F which provides: "Alternative Nailstrip metal cladding profile in lieu of Standing Seam metal cladding profile".
(a) clause 1.2 of the Formal Instrument of Agreement requires Henny to carry out and complete the work under the Contract in accordance with the Contract;
(b) as described above, each item of the VMA Work is a specific clarification or exclusion to the scope of work as set out in Part F. Part F forms part of the Contract. Indeed, clause 2.1 of the Formal Instrument of Agreement lists Part F as second in the order of precedence of contract documents; and
(c) no item of the VMA Work, as articulated in Part F, is expressed to be subject to any further agreement between Little Hardiman Street and Henny.
D.3.2 There are no provisions in the Contract that govern how the Superintendent is to value or account for the Value Management Adjustment - The provisions relied on by Little Hardiman Street are inapplicable to the VMA Work
(a) the Superintendent is to issue a progress certificate evidencing his opinion of the moneys due from Little Hardiman Street to Henny pursuant to the progress claim ('Progress Certificate');
(b) the Superintendent is to issue a certificate evidencing his assessment of retention moneys and "moneys due from [Henny] to [Little Hardiman Street] pursuant to the Contract"; and
(c) Little Hardiman Street must then pay to Henny the balance of the Progress Certificate after setting off such of the Superintendent's Certificate as Little Hardiman Street elects to set off. If that setting off produces a negative balance, then Henny must pay that balance to Little Hardiman Street.
(a) in the case of liquidated damages, cl 34.7 authorises the Superintendent to certify an amount in liquidated damages "as due and payable to [Little Hardiman Street]";
(b) in the case of early practical completion, cl 34.8 empowers the Superintendent to certify a bonus amount as due and payable to Henny; and
(c) in the case of defects rectified by others, cl 29.3 empowers the Superintendent to certify the cost incurred as "moneys due from [Henny] to [Little Hardiman Street]".
E Issue 2 - Did the Adjudicator fall into error by failing to assess the Value Management Adjustment as a second‑class claimable variation pursuant to s 10A(3) of the SOP Act?
(a) If it is incorrect in relation to Issue 1, then the Value Management Adjustment ought to have been valued as a claimable second‑class variation under s 10A(3) of the SOP Act.
(b) Clause 36.1 of the General Conditions defines a variation as including any direction to "change the character or quality" of the work under the Contract, which is perfectly apt to describe the work the subject of the Value Management Adjustment.
(c) Each item of work satisfies the requirements of a second‑class variation under s 10A(3).
[2] JG King Project Management Pty Ltd v Hunters Green Retirement Living Pty Ltd [2024] VSCA 310, [243] (Kennedy JA).
[3] Mount Bruce Mining Pty Ltd v Wright Prospecting Pty Ltd [2015] HCA 37; (2015) 256 CLR 104 ('Mount Bruce Mining'), [46] (French CJ, Nettle and Gordon JJ).
[4] Mount Bruce Mining, [47] (French CJ, Nettle and Gordon JJ).
[5] Wilkie v Gordian Runoff Ltd [2005] HCA 17; (2005) 221 CLR 522, [16] (Gleeson CJ, McHugh, Gummow and Kirby JJ).
[6] That table was referred to and relied upon by Little Hardiman Street's counsel during the hearing in support of the proposition that Little Hardiman Street had directed the works to be done, without contradicting its content.
Little Hardiman Street Pty Ltd
Henny Pty Ltd [2025] VSC 436