[2026] VSC 206
General information, not legal advice.
Supreme Court of Victoria
2026-04-13
Fary AsJ
Original judgment source is linked above.
CORPORATIONS - Winding up - Statutory demand - Application to set aside on ground of offsetting claim - Corporations Act 2001 (Cth), ss 459G, 459H - Demand seeks payment comprising GST on invoices issued to company - Whether offsetting claim genuine - Whether to vary demand pursuant to s 459H(4) - Demand varied in respect of legal costs and liquidated damages - Not satisfied claim otherwise established.
(a) Originating Process dated 27 January 2026;
(b) affidavits of Julian Minter affirmed 27 January 2026, 2 February 2026 and 17 February 2026;
(c) affidavit of Angus Angelatos sworn 2 February 2026;
(d) affidavit of Shaila Khan (Ms Khan) affirmed 17 February 2026 (Khan affidavit);
(e) bundle of authorities dated 17 February 2026;
(f) written submissions dated 17 February 2026; and
(g) paras [14] to [19] of the Khan affidavit.
(a) affidavit of Mackenzie Smyth affirmed 5 February 2026;
(b) affidavit of Yufeng Shi (Mr Shi) affirmed 10 February 2026 (Shi Affidavit);
(c) bundle of authorities dated 24 February 2026; and
(d) written submissions dated 24 February 2026.
... We will transfer the $1,355,770 GST refund to you once we have received the same from the ATO.
We are not aware of any outstanding issues or reasons for non-payment...
(a) liquidated damages of $257,950;
(b) legal costs in accordance with cl 8.4(e)(3) of the Development Agreement of $6,050; and
(c) indemnity costs pursuant to cl 13.5 of the Development Agreement of $422,075.40.
As the terms of s 459H of the Corporations Act and the authorities make clear, the company is required, in this context, only to establish a genuine dispute or off-setting claim. It is required to evidence the assertions relevant to the alleged dispute or off-setting claim only to the extent necessary for that primary task. The dispute or off-setting claim should have a sufficient objective existence and prima facie plausibility to distinguish it from a merely spurious claim, bluster or assertion, and sufficient factual particularity to exclude the merely fanciful or futile. As counsel for the appellant conceded however, it is not necessary for the company to advance, at this stage, a fully evidenced claim. Something 'between mere assertion and the proof that would be necessary in a court of law' may suffice. A selective focus on a part of the formulation in South Australia v Wall [(1980) 24 SASR 189], divorced from its overall context, may obscure the flexibility of judicial approach appropriate in the present context if it suggests that the company must formally or comprehensively evidence the basis of its dispute or off-setting claim. The legislation requires something less.
(a) first, a claim for legal costs and liquidated damages pursuant to cl 8.4(e) of the Development Agreement (as varied); and
(b) second, a claim pursuant to the indemnity provided by cl 13.5 of the Development Agreement.
(1) the Landowner agrees to enter into the Section 173 Agreement;
(2) the Landowner must execute (or authorise the Developer to execute on behalf of the Landowner pursuant to the Power of Attorney) the Section 173 Agreement immediately upon:
(i) receipt from the Developer of a copy of the deed of variation (Deed) under which this clause 8.4(e) was inserted into this agreement executed by the Developer; and
(ii) payment by the Developer of the costs referred to in clause 8.4(e)(3);
(3) the Developer must pay to the Landowner $5,500, plus GST, towards the Landowner's legal costs in connection with the Section 173 Agreement, the Deed and the dispute referred to in the recitals; and
(4) if the Intersection Works (as defined in the Section 173 Agreement) are not completed (in accordance with the terms of the Section 173 Agreement) by the date which is 12 months after the date of the Section 173 Agreement (Sunset Date), the Developer must pay to the Landowner a sum of $500 per day (exclusive of GST) from and including the date after the Sunset Date to and including the date on which the Intersection Works are completed (in accordance with the terms of the Section 173 Agreement or otherwise satisfied by Casey City Council). Any such amount must be paid weekly in arrears until completion of the Intersection Works by the Developer or Casey City Council (in accordance with the terms of the Section 173 Agreement). The parties acknowledge and agree that this amount represents the Landowner's genuine pre-estimate of the losses that it will suffer due to non-completion of the Intersection Works (in accordance with the terms of the Section 173 Agreement) by the Sunset Date, and its inability to sell the Medium Density Site as a result. ...
(a) The Developer indemnifies the Landowner against any Damage suffered or incurred by or brought against the Landowner to the extent arising out of or in respect of:
(1) the Landowner doing or not doing anything pursuant to this agreement or at the request of the Developer; and
(2) a negligent act or omission of the Developer or a breach by the Developer of its obligations under this agreement, except to the extent such Damage is caused or contributed to by the negligent act or omission of the Landowner, or any of its employees, agents, contractors or invitees.
(b) The Landowner, to the extent that it is within the Landowner's control and at the Developer's cost, agrees to use its reasonable endeavours to mitigate any Damage to the Landowner as contemplated in clause 13.5(a).
(a) The defendant dumped soil on the Land, which was owned by the Company.
(b) The defendant failed to remove soil from the Land.
(c) At some point, possibly 16 November 2022,[3] the Company requested that the soil be removed from the Land.
(d) In December 2022 and January 2023, the Company removed the soil from the Land at a cost of $200,000.
(e) The failure to remove soil caused the Company loss and damage in that:
(i) the Company was 'unable to proceed with its development application in a timely manner' with the consequence that:
- (A) it missed the Sunset Date for the purposes of the Section 173 Agreement (11 August 2021);
- (B) it was required to expend $427,245.37[4] to remove the Section 173 Agreement.
(f) The Company has a right to recover that loss and damage from the defendant pursuant to cl 13.5 of the Development Agreement.
(a) On 31 May 2018, planning permit 'PLnA00536/17.A' issued in respect of lot 2 on PS332227T authorised the development of lot 2 for a multi-lot subdivision in three stages. Condition 25A provided that prior to the issue of a statement of compliance for stage 3, the Cameron Street/Elmslie Drive intersection must be constructed to the satisfaction of the Responsible Authority.
(b) On 2 August 2018, the parties entered into the Development Agreement.
(c) On 11 August 2020, the Company and the Council entered into the Section 173 Agreement. The agreement was expressed to end on the latter of the completion of the Intersection Works to the satisfaction of the Council and the repayment of any remaining bond to the payee.
(d) Mr Shi has deposed that during the development of the Site, the defendant had a stockpile of soil on the Company's medium density site adjacent to the Site. He deposed that 'I believe that the Stockpile was removed by May 2021'. He annexed an invoice dated 26 May 2021 issued by Rokon.
(e) On 26 May 2021, Rokon issued a tax invoice to the defendant in the amount of $66,000 (incl GST) for '0316 Cameron St (Eastwood intersection works)-Disposal of Material - REVISED'.
(f) On 11 August 2021, the Sunset Date was reached.
(g) Between 30 June 2022 and 30 November 2022, Spot Planning issued a series of tax invoices to the Company in respect of work done removing the Section 173 Agreement.
(h) On 16 November 2022, Mr Lai, director of Kaleida, sent an email to Mr Buckland, Senior Development Manager of Risland, stating:
...
Following our discussions regarding the fill remaining on the MD site, we require both mounds to be removed from site by the end of November 2022.
It was previously advised to us in June 2021 that the larger stockpile was removed, but it clearly has not been.
We allowed CG/Risland to use the MD site in good faith during construction and expect that the site be returned to us without this burden.
If the mounds are not removed by the end of November 2022, we will have to remove the mounds at Risland/CGs expense.
(i) Mr Shi has deposed that the Intersection Works were completed at the latest by 24 November 2022, being the date the Section 173 Agreement was removed.
(j) On 24 November 2022, the Section 173 Agreement was removed.
(k) On 28 November 20222, Mr Lai sent an email to Mr Buckland stating:
...
Further to my email and discussions, we have obtained quotes to clear the site.
The expense will be in the range of $160,000 to $200,000 depending on what the makeup of the fill is. Note that this could be more if further contamination or waste is discovered in the fill during removal.
Given we haven't received a quote and commitment from your team to remove the fill we will proceed to do so ourselves at your cost.
(l) On 29 November 2022, Mr Buckland sent an email to Mr Lai, which provided:
The stockpile generated by Risland during civil construction was removed in May 2021 with only a small quantity of third party dumping by builders/others remaining on the site. Are you able to share a copy of the quote including the estimated quantity of what is currently on site, as it seems far in excess of what we have already removed and would suggest this is new dumping occurring more recently? I have attached a photo of the site from when the original stockpile was removed showing the work was completed.
Risland's position is that the stockpiles generated from civil construction were removed and we should not be liable for third party dumping. I also question the reasoning behind seeking additional damages for dumping removal when there are already liquidated damages in place to compensate for the delays.
Happy to discuss further when we close this out. Has there been any further progress on the S173 removal?
(m) The photograph attached (which purports to show the Land after the removal of soil in May 2021) showed a site that is mostly cleared, but with two moderate sized piles of soil on it (Photo).
(n) On 21 December 2022, GRN Built issued a tax invoice to the plaintiff in the amount of $183,864.92 (incl GST) in respect of 'agreed works for 40 Cameron St, Cranbourne East'.
(o) On 30 January 2023, GRN Built issued a tax invoice to the plaintiff in the amount of $18,210.48 (incl GST) in respect of 'agreed works for 40 Cameron St, Cranbourne East'.
The First Offsetting Claim relates to a claim the plaintiff has against the defendant for damages suffered as a result of the defendant's dumping of soil on the [Land].
[1] The plaintiff referred to as the 'Landowner' and the defendant as the 'Developer'.
[2] [2008] VSCA 70; (2008) 66 ACSR 67, 79 (Neave and Kellam JJA agreeing at [1] and [2]) (emphasis added).
[3] Email dated 16 November 2022 from Daoren Lai, director of Kaleida, and sent to Jason Buckland, Senior Development Manager of Risland (16 November Email).
[4] Comprising fees payable for Town planning, Lawyer, Council application, Civil Works and Project Management.
Plaintiff
EASTWOOD CRANBOURNE PTY LTD