[2010] VSC 607
General information, not legal advice.
Supreme Court of Victoria
2010-12-17
EMERTON J
Original judgment source is linked above.
The parties signed a Joint Memorandum on Proposed Orders dated 19 November 2010, in accordance with Practice Note No. 4 of 2009 in the Judicial Review and Appeals List.
1 The parties to this appeal have agreed that the orders of the Victorian Civil and Administrative Tribunal made on 27 April 2010 are based on an error of law and should be set aside with the matter remitted to the Tribunal, differently constituted, for a further hearing of additional evidence limited to the issue of the noise impacts of the proposal on existing dwellings, including the cumulative acoustic effect of The Sisters Wind Farm and Mortlake Wind Farm.
2 The parties have provided to the Court, in accordance with Practice Note No. 4 of 2009 in the Judicial Review and Appeals List, a Joint Memorandum on Proposed Orders (the 'Joint Memorandum'), which sets out the following:
(a) The plaintiff applied for a planning permit to develop a wind energy facility on a 680 hectare parcel of land within the area known as The Sisters, approximately 230 kilometres west of Melbourne. On 7 August 2009, the Moyne Shire Council refused the plaintiff's permit application, and on 12 August 2009, the plaintiff applied to the Tribunal for a review of that refusal.
(b) On 20 November 2009, the Tribunal ordered that the Council's grounds of refusal be amended to include the following additional ground:
There is inadequate information to assess the cumulative effects of the proposal, including the cumulative visual effects and cumulative acoustic effects of the proposal, particularly with respect to the proposed Mortlake Wind Farm.
(c) The Moyne Planning Scheme and the Policy and Planning Guidelines for Development of Wind Energy Facilities in Victoria, 2009 (the '2009 Guidelines') make reference to assessing noise impact in accordance with New Zealand Standard NZ6808:1998 Acoustics - The Assessment and Measurement of Sound from Wind Turbine Generators (the '1998 Standard'). That standard was superseded by NZS6808:2010 Acoustics: Wind Farm Noise (the '2010 Standard').
(d) The 2010 Standard differs from the 1998 Standard in a number of respects. In particular, the 2010 Standard provides that a high amenity noise limit should be considered where a plan promotes a high degree of protection of amenity related to the sound environment of a particular area.
(e) The hearing of the plaintiff's application for review before the Tribunal took place on 11, 12, 15 and 16 February 2010. After a short adjournment as a result of the Tribunal expressing concerns about "shortfalls" in the plaintiff's application concerning noise impact assessment arising from turbines associated with both the plaintiff's proposal and the Mortlake Wind Farm, and the provision by the plaintiff of noise impact assessments and a report by an acoustic engineer, the hearing reconvened on 12 April 2010.
(f) By an order dated 27 April 2010, the Tribunal affirmed the decision of the Council and confirmed that no permit would be granted in respect of the plaintiff's proposal.
3 The error of law made by the Tribunal is submitted by the parties to be contained in the following statement:
under the Interpretation of Legislation Act 1984 the reference to the 1998 New Zealand Standard in the Policy Guideline and the Planning Scheme should be read as a reference to the 2010 New Zealand Standard.
4 The parties agree that the Tribunal was wrong to read references in the Planning Scheme and in the 2009 Guidelines to the 1998 Standard as references to the 2010 Standard.
5 It is submitted by the parties that there is nothing in the Interpretation of Legislation Act 1984 that authorised the Tribunal to read references in the Planning Scheme and in the 2009 Guidelines to the 1998 Standard as references to the 2010 Standard. In the absence of an amendment to the Planning Scheme, the Tribunal was required to apply the 1998 Standard when assessing the noise impact of the plaintiff's proposal.
6 I accept the submissions made by the parties in the Joint Memorandum, which I attach to this judgment. The Tribunal erred in reading the references in the Planning Scheme and the 2009 Guidelines to the 1998 Standard as a reference to the 2010 Standard. That error was a vitiating error.
7 The matter will be remitted to the Tribunal in accordance with the Minute of Joint Proposed Orders.
I certify that this and the 108 preceding page are a true copy of the reasons for Judgment of Emerton J of the Supreme Court of Victoria delivered on 17 December2010.
under the Interpretation of Legislation Act 1984, the reference to the 1998 New Zealand Standard in the Policy Guideline and the Planning Scheme should be read as a reference to the 2010 New Zealand Standard.
The Tribunal was wrong to read references in the Policy Guidelines and in the Planning Scheme to the 1998 New Zealand Standard as references to the 2010 Standard.
There is inadequate information to assess the cumulative effects of the proposal, including the cumulative visual effects and cumulative acoustic effects of the proposal, particularly with respect to the proposed Mortlake Wind Farm.
The VCAT also set down a date for a further hearing on 12 April 2010.[9]
"5.3.1 The wind farm noise limit of 40 dB LA90(10 min) ... is appropriate for protection of sleep, health, and amenity of residents at most noise sensitive locations. In special circumstances at some noise sensitive locations a more stringent noise limit may be justified to afford a greater degree of protection of amenity during evening and night-time. A high amenity noise limit should be considered where a plan promotes a higher degree of protection of amenity related to the sound environment of a particular area, for example where evening and night-time noise limits in the plan for general sound sources are more stringent than 40 dB LAeq(15 min) or 40 dBA L10. ...
5.3.3 Where a high amenity noise limit is shown to be justified in accordance with 5.3.1, under wind conditions determined in accordance with 5.3.2, wind farm sound levels ... during evening and night-time should not exceed the background sound level by more than 5 dB or a level of 35 dB LA90(10 min), whichever is the greater." (emphasis added)
This more stringent noise limit did not exist under the 1998 Standard.[14]
[1] This joint memorandum has been signed by the solicitors for the plaintiff and the first defendant. The first defendant has obtained the written consent of each other defendant to this proceeding to the proposed orders.
[4] [2009] FCAFC 33; (2009) 174 FCR 574 at 577 [12]- [16].
[5] Exhibit JTGL-1 to the Affidavit of Justin Lethlean is a copy of the executive summary of that permit application.
[6] Exhibit JTGL-2. See also Exhibit JTGL-11 at page 7.
[14] Clause 4.4.2 of the 1998 Standard simply said this: "As a guide to the limits of acceptability, the sound level from the WTG (or windfarm) should not exceed, at any residential site, and at any of the nominated windspeeds, the background sound level (L95) by more than 5 dBA, or a level of 40 dBA (L95), whichever is the greater".
[15] The VCAT's order and its reasons are exhibit JTGL-11.
[16] Exhibit JTGL-11 at [17], [18], [24], [27]
The Sisters Wind Farm Pty Ltd
Moyne Shire Council & Ors [2010] VSC 607
(2009) 174 FCR 574