Source factsCourt
Supreme Court of Victoria
Decision date
2008-10-07
Before
HARPER J
Source
Original judgment source is linked above.
Judgment (30 paragraphs)
PRACTICE AND PROCEDURE - Appeal from a Master - Application for summary judgment - Personal guarantees given by directors of a company - Whether an issue to be tried - Terms of guarantee clear and unambiguous and arrived at following negotiation - Evidence adduced by the defendants inconsistent with claim that they were induced to enter the guarantee by representation - Appeal allowed.
1 Abigroup Contractors Pty Ltd is a construction contractor. In December 2004, it entered into a building contract with a company called 519 St Kilda Road Pty Ltd, ("519 P/L)", for "the design and construction of the development at 519 St Kilda Road, Melbourne". (That quotation is from the statement of claim paragraph 2 - an allegation which is admitted in the defence.)