[2025] VSC 636
General information, not legal advice.
Supreme Court of Victoria
2025-10-08
Efthim AsJ
Original judgment source is linked above.
SPECIFIC PERFORMANCE - Building contract - Delay in completing the rectification work under the contract - Whether specific performance is an adequate remedy - Mayor, Aldermen and Burgesses of Wolverhampton v Emmons [1901] UKLawRpKQB 22; [1901] 1 QB 515 applied - Whether the scope of work is clearly defined - Whether damages are a more adequate remedy.
...
We put you on notice that the Property is fully alarmed and any unauthorised attendance at the Property by you (or any third parties at your direction), will be immediately reported to the Police.
Contract means the New Homes Contract entered into between the Owner and the Builder for the construction of a home at the Site dated 13 April 2022.
...
Defects Report means the report prepared by the Expert identifying any defective building works.
...
Execution Date means the date on which this Deed is executed and exchanged between the Parties.
Expert means an independent expert building consultant.
Expert Confirmation means that the Expert must inspect the Rectification Works and, if the Expert considers that the Rectification Works satisfactorily remedy the defects identified in the Defects Report (as amended following any Objection), the Expert must provide the Builder and the Owner with written confirmation of this.
5.1 In full and final settlement of the Dispute, the Parties agree that:
. . .
(b) the Completion Date is extended to 30 July 2024 and the Builder must bring the Works to Completion by this time (including causing an occupancy permit to be issued);
. . .
(d) once the Works reach Completion, the Builder and the Owner must jointly engage the Expert to inspect the Works and prepare the Defects Report;
. . .
(f) if the Builder and/or the Owner consider that any defects identified in the Defects Report are not defective building works or certain defects have been omitted from the Defects Report, the Builder and/or the Owner may write to the Expert with an Objection;
(g) if an Objection is received by the Expert, the Expert must consider the Objection and determine whether the Defects Report be revised to omit or include the subject matter of the Objection;
(h) the Builder must carry out and complete the Rectification Work within 60 days of receipt of the Defects Report (as amended following any Objection(s));
(i) if the Builder reasonably considers that it requires more time under cl 5.1(h) to promptly carry out and complete the Rectification Work, the Builder must provide the Owner with a written notice requesting a reasonable extension to the time to promptly carry out and complete the Rectification, such consent not to be unreasonably withheld by the Owner;
(j) the Expert must inspect the Rectification Works and, once the Expert considers that the Rectification Works have been satisfactorily completed, provide the Expert Confirmation;
(k) the Builder and the Owner must share in equal proportions all costs in relation to the engagement of the Expert;
(l) the Owner must pay to the Builder, by way of direct deposit to the Builder's Bank Account, the following:
(i) subject to clause 5.1(n), the First Payment within three business days of the Owner being provided with relevant plumbing certifications pursuant to Stage 13 of the Contract;
(ii) the Second Payment within three business days of the Builder providing to the Owner written confirmation that:
(a) an occupancy permit has been issued by the relevant building surveyor for the Project; and
(b) Completion under the Contract has been achieved; and
(iii) the Final Payment immediately upon the Owner being provided with the Expert Confirmation;
. . .
7.4 Subject to clause 7.2, if the Builder materially defaults in any of its obligations in clause 5 of this Deed and that default does not arise from or is not related to any failure by the Owner to comply with cl 5.1(c) of this Deed, the Owner may elect to either:
(a) terminate this Deed and the Contract; or
(b) commence proceedings in a court of competent jurisdiction against the Builder seeking specific performance of the terms of this Deed plus interest and costs.
The conduct of your client (both before and after the entering of the deed) provides no confidence that our client will not be in the same position come 15 August 2025. It is not unreasonable for our client to withhold its agreement to the extension, as currently proposed.
Our client's position is that your client is plainly in default. Clause 7.4(b) of the Deed provides our client with the right to elect, in the event of default, to apply to a Court for urgent orders that your client specifically perform the Deed (plus interest and costs).
Orders for specific performance would provide a level of accountability on your client to perform its obligations under the Deed. A breach of the orders likely being deemed a contempt of court by your client (and potentially Mr Carr).
...the exercise of the jurisdiction of equity as to enforcing specific performance of agreements, is not a matter of right in the party seeking relief, but of discretion in the Court - not an arbitrary or capricious discretion, but one to be governed as far as possible by fixed rules and principles.[8]
This remedy by specific performance was invented, and has been cautiously applied, in order to meet cases where the ordinary remedy by an action for damages is not an adequate compensation for breach of contract. The jurisdiction to compel specific performance has always been treated as discretionary, and confined within well-known rules.[10]
The contract between the appellants and the company was not a type which equity would specifically enforce. It was a contract for the construction of a house and erection. As Mellish LJ remarked in Wilkinson v Clements (1872) 8 Ch App, at p 112:
Now it is settled that, as a general rule, the court will not compel the building of houses.[13]
In relation to building contracts, it is not the case that specific performance will never be granted in respect of such contracts: Meagher RP, Heydon JD and Leeming MJ, Equity Doctrines and Remedies (4th ed 2002) at [20-080]. However, as the authors of that text observe (at 21-215), generally speaking, neither specific performance nor interlocutory injunctions having the effect of specific performance will be granted in respect of building contracts in other than exceptional circumstances.[16]
In my judgment all these cases illustrate the obvious. Specific performance is an equitable and thus fact specific and discretionary remedy. Its exercise is governed by well settled principles which are flexible and adaptable to achieve the ends of equity; that is, to 'do more perfect and complete justice' between the parties than leaving them to their common law remedies (Argyll Stores at 9F-G). Building contracts present special features "of a practical nature" (Argyll Stores at 11H) in the areas of sufficient particularity and superintendence of work. But provided the Court is satisfied they can be accommodated by the imposition of appropriate terms within the order, as the arbitrator was here, there is no principled reason why such contracts should not be the subject of awards for specific performance.[18]
The question, which is not free from difficulty, is whether, under the circumstances of this case, an order for specific performance should be made in favour of the plaintiffs. There is no doubt that as a general rule the Court will not enforce specific performance of a building contract, but an exception from the rule has been recognised. It has, I think, for some time been held that, in order to bring himself within that exception, a plaintiff must establish three things. The first is that the building work, of which he seeks to enforce the performance, is defined by the contract; that is to say, that the particulars of the work are so far definitely ascertained that the Court can sufficiently see what is the exact nature of the work of which it is asked to order the performance. The second is that the plaintiff has a substantial interest in having the contract performed, which is of such a nature that he cannot adequately be compensated for breach of the contract by damages. The third is that the defendant has by the contract obtained possession of land on which the work is contracted to be done.[20]
Any marks on the lower level of the external brickwork which is agreed was attributed to the owner's work is not the builder's responsibility.
However, other mortar smear marks or caulking smears will require spot cleaning by the builder as part of the completion of works.[21]
Item 67 in the builder's objection letter states that the owner requested that the holes be provided in the glass shower screen panels.
The scope of works does not mention the holes in the shower recess glass panels.
If the owner's instructions to the builder are proved or correct, then items 373, 384 & 385 should be deleted from the defects report.[22]
The issue of who supplied the first-floor balcony tiles is not the issue. The issue is that there are defective works with the installation of the tiles due to the lack of adequate design, stepdown height which has restricted the builder's ability to provide a compliant stepdown.
...
This cannot be rectified unless the balcony was stripped and possibly a hob installed under the sliding door frames.
The items should be discussed if compliance is required.[23]
The defendant has statutory obligations under the DBC Act.
These are not obligations, they are warranties which apply to every domestic building contract.
There is the possibility for dispute about scope if a new builder is engaged.
This applies to every building contract. And scope is in dispute now.
Engaging a replacement builder is notoriously difficult.
This applies to every building contract. There is no evidence that the regional location is an extraordinary impracticality.
Engaging a replacement builder is notoriously costly.
Engaging a replacement builder would expose the plaintiff to delay.
Engaging a replacement builder would expose the plaintiff to planning, building or insurance risk.
Biltar may not have the financial means to meet an award of damages.
This is pure speculation. Further, it ignores the builder's warranty insurance provided by the Defendant.
[1] Paragraph 26 of the affidavit of Benjamin Lindsay Carr, sworn 15 August 2025, which has not been contradicted by the plaintiff
[2] Paragraph 23 of the affidavit of Benjamin Lindsay Carr, sworn 15 August 2025, which has not been contradicted by the plaintiff.
[6] See Rossi Recycling Pty Ltd v Buckland Valley Pty Ltd [2022] 165 ACSR 332.
[11] See Primewest (Mandurah) Pty Ltd v Ryom Pty Ltd [2012] WASC 443 and Hawkesdale Asset Pty Ltd v Bennett [2023] VSC 409.
[14] [2012] HCA 39 at [105].
[21] Second report of Mr Ryan, at p 21.
[23] Second report of Mr Ryan, at p 25.
Grech
Biltar Pty Ltd [2025] VSC 636
(1983) 149 CLR 639