Plaintiff v Defendant
[2007] VSC 213
At a glance
Source factsCourt
Supreme Court of Victoria
Decision date
2007-07-06
Before
BYRNE J
Source
Original judgment source is linked above.
Judgment (37 paragraphs)
PRACTICE AND PROCEDURE - amendment of pleading after trial - deliberate forensic decision - prejudice to other parties - amendment refused.
1 At this, the final round of judgments, other than those for costs, JJP Geotechnical Engineering Pty Ltd (formerly known as Barrett Fuller Partners), known in this proceeding as Barrett Fuller, seeks a final order dismissing the claim of Wynton Stone Australia Pty Ltd (in liquidation), known in this proceeding as Wynton Stone, against it for apportionment. Counsel for Wynton Stone resisted this, seeking judgment for $4,138,696 plus interest for breach of contract and, if this be necessary, leave to amend its claim to include a contract claim to support this judgment.