The Application
1 This is an application by the first defendant to stay or strike out that part of the plaintiff's amended statement of claim in which it claims contribution from the first defendant under s.23B of the Wrongs Act 1958 (Vic).
The Factual Background
2 An affidavit in support of the application was sworn on 15 September 2005 by John James Boon Cooper, the solicitor for the first defendant. That affidavit referred in turn to the earlier affidavit of Mr Cooper, sworn on 21 April 2005. The following factual background, which for present purposes seemed to be common ground, is taken from statements in, and exhibits to, Mr Cooper's two affidavits and from the pleadings in the proceeding. Reference to the affidavits was permissible under r.23.04 of the Supreme Court Rules, because, as will be seen, essentially the application was for a stay, under r.23.04, because the alleged claim was said to be bad in law rather than for an order, under r.23.02, striking out the relevant part of the amended statement of claim with leave to replead the claim in the proper way.
3 By an agreement made on or about 20 June 1996 between the second defendant, Minara Resources Limited (then known as Anaconda Nickel Limited) ("Minara"), and the plaintiff, Fluor Australia Pty Ltd ("Fluor"), ("the EPCM Agreement"), Minara engaged Fluor to provide engineering, procurement, construction and management services for the design, construction and commissioning of a facility to treat nickel and cobalt bearing lateritic ores at Murrin Murrin in Western Australia ("the Facility").
4 By an agreement made on or about 21 February 1997 between Minara and the first defendant, ASC Engineering Pty Ltd ("ASC"), Minara engaged ASC to design, manufacture and supply four acid leach autoclaves to the Facility ("the ASC Contract"). Fluor was not a party to the ASC Contract, although it was named in that Agreement as the "Engineer".
5 In or prior to August 1997 Minara transferred the whole of its interest in the Facility, including the development of the Facility, to its wholly owned subsidiary Murrin Murrin Operations Pty Ltd (then known as Anaconda Operations Pty Ltd) ("MMO") as agent for the Murrin Murrin Joint Venture between Murrin Murrin Holdings Pty Ltd ("MMH"), a wholly owned subsidiary of Minara, as to 60% and Glenmurrin Pty Ltd ("Glenmurrin"), a wholly owned subsidiary of Glencore International AG, as to 40%, which interest it purchased from Minara. MMO was appointed the manager under the Joint Venture Agreement and each of MMH and Glenmurrin appointed MMO to act as its agent.
6 By an agreement dated 27 August 1997 but executed and operative from 21 August 1997 and made between Fluor and MMO, as agent for MMH and Glenmurrin ("the EPC Agreement"), Fluor agreed to assume responsibility for the design and construction of the Facility.
7 The autoclaves were designed and manufactured by ASC in South Australia and installed by ASC at the Facility in early 1998. Alleged defects were subsequently found in wear plates affixed to the inside of the autoclaves. ASC attempted unsuccessfully to repair the wear plates. In November 2000 MMO engaged ASC to remove all of the wear plates, which task was completed by April 2001.
8 MMO commenced arbitral proceedings against Fluor under the EPC Agreement in respect of, among many other things, the allegedly defective wear plates in the autoclaves. The Commercial Arbitration Act 1984 (Vic) was the Act under which the arbitration was conducted. Under the interim and final arbitral awards delivered in late 2002 Fluor was ordered to pay MMO $3,276,189 plus interest in respect of the defective wear plates.
9 Fluor appealed the arbitral award in MMO's favour to this Court. Judgment was delivered on 28 July 2003.[1] The appeal was largely unsuccessful and, relevantly, Fluor remained liable to pay MMO $3,276,189 plus interest in respect of the defective wear plates. A further appeal to the Court of Appeal was settled. On 5 May 2004 Minara, MMO, Fluor and three other parties entered into a Release by which, among other things, MMO and Minara purported to agree to assign or novate the ASC Contract to Fluor.
The Proceeding
10 Fluor commenced this proceeding by writ and indorsement of claim on 7 May 2003. It filed a statement of claim on 1 July 2004 and then an amended statement of claim on 23 August 2005. Three claims are pleaded by Fluor. First, Fluor seeks damages from ASC for breach of the ASC Contract, the benefit of which it alleges is held by Minara on trust for it ("the contract claim"). Secondly, Fluor seeks damages from ASC in negligence. Thirdly, and alternatively, Fluor claims contribution from ASC under s.23B of the Wrongs Act 1958 (Vic) ("the contribution claim"). It pleads that as it was Minara's intention that MMO would have the benefit of the contractual promises of ASC pursuant to the ASC Contract, ASC is therefore liable to MMO for the same damage for which Fluor has been held liable to MMO in the arbitration.
11 By a summons filed on 16 September 2005 ASC sought an order, pursuant to r.23.01 of the Supreme Court Rules, staying the contract claim and the contribution claim, alternatively an order, pursuant to r.23.02, striking out the contract claim and the contribution claim.
The Appropriate Test
12 The traditional statement of when a court can summarily determine a proceeding by, for example, staying the proceeding or a claim in the proceeding, under r.23.01, on the ground that it does not disclose a cause of action has been expressed in a variety of ways. In General Steel Industries Inc v Commissioner for Railways (NSW)[2], Barwick CJ summarised past approaches. His Honour said: