s.185 - Application for approval of a single-enterprise agreement
Application for approval of the PHI International Australia Broome and Truscott Helicopter Pilots Enterprise Agreement 2024 - dispute settlement procedure in proposed agreement - whether Commission satisfied proposed agreement includes a term described in s.186(6)
39.1 Preamble and principles of the Disputes Resolution Process (DRP)
39.1.1 In the event of a disagreement about any matter arising under the Agreement or the NES, including a dispute regarding the interpretation or application of this Agreement, the NES, a matter pertaining to the employer-employee relationship, or any other work-related matter, the parties to the dispute will attempt to resolve the dispute in accordance with the following DRP.
39.1.2 The parties agree to participate in the DRP in good faith and in recognition that the satisfactory resolution of any dispute is in the interests of all parties to, or covered by, this Agreement.
39.1.3 A Pilot or a Pilot's representative acting on their behalf, subject to this Agreement, may initiate a dispute at any time.
39.1.4 A party to a dispute covered under the Scope and Application of this Agreement, as set out in clause 2 of this Agreement, may appoint and be accompanied and represented at any stage by another person, organisation or association, including a Union representative or PHI or non-PHI association in relation to the dispute. Ready access to the Pilot shall be provided to the Pilot's nominated representative so that relevant information and instructions can be provided. However not at a time such that it will impact with PHI's normal contracted operations.
39.2.1 Once a dispute has been initiated, the Pilot shall notify the Human Resources Department who shall refer the dispute to the appropriate person with the management structure who shall, unless otherwise agreed, meet and confer with the Pilot within a reasonable period at a mutually agreeable location, by a mutual agreeable method of communication, in an attempt to resolve the dispute.
39.2.2 The Pilot must not unreasonably fail to comply with any direction given by PHI about performing work. If the dispute is not resolved under Clause 39.2.1, the dispute may be referred to the Fair Work Commission (FWC) for resolution by mediation and/or conciliation and arbitration. If arbitration is necessary the FWC may exercise its procedural powers in relation to hearings, witnesses, evidence, and submissions which are necessary to make the arbitration effective.
39.2.3 While the dispute resolution procedure is being conducted work shall continue normally, unless a Pilot or PHI has a reasonable concern about an imminent risk to their health or safety, and pending the resolution of the dispute the subject matter of the dispute shall be preserved and the status quo retained.
39.3.1 The decision of the FWC will bind the parties, subject to either party exercising a right of appeal against the decision to a Full Bench of FWC. For clarity it is a term of this Agreement that the parties do have a right of appeal.
39.4.1 All Parties agree that the FWC can deal with this matter as per the provisions of the Fair Work Act.
39.4.2 FWC shall be provided access to the workplace to inspect or view any work, material, machinery, appliance, article, document, or other thing or interview any Pilot who is usually engaged in work at the workplace.
39.4.3 The parties agree that FWC may give all such directions and do all such things as are necessary for the just resolution and determination of the dispute. This includes but is not limited to mediation or conciliation or arbitration.
39.5.1 The parties agree that to the extent that any decision of the FWC alters the rights and responsibilities of any of the parties to the Agreement that those rights are so altered and are enforceable in a court of competent jurisdiction.
(6) The FWC must be satisfied that the agreement includes a term:
(a) that provides a procedure that requires or allows the FWC, or another person who is independent of the employers, employees or employee organisations covered by the agreement, to settle disputes:
(i) about any matters arising under the agreement; and
(ii) in relation to the National Employment Standards; and
(b) that allows for the representation of employees covered by the agreement for the purposes of that procedure.
63. Since each of the five unions had a right to initiate proceedings in the Court, s 186(6) required cl 28 to provide a procedure to resolve a dispute that would be litigated in such a matter, because that dispute would arise under the Yallourn agreement, even if no individual employee had initiated a complaint, provided that Energy Australia had contravened its obligations under cl 5.3 in respect of one or more casual employees (see s 540(2)).
64. Here, cll 28.2(e) and 28.3(b) provided that "the Parties" (being the persons defined as such in cl 2) would be bound by the decision of the Commission in an arbitration under that dispute resolution clause. Although the Yallourn agreement appears to have switched freely between referring to all persons who were in a legal sense parties to it (employees, Energy Australia and the five unions) as "parties" and the defined term "the Parties", cl 28.2(e) could not operate to cause a decision of the Commission to bind "the Parties" if the five unions had no right to raise, or be a legal party to, the dispute. That consequence bespoke the importance of providing a dispute resolution process in which disputes involving any one of the five unions, including in disputes between them, could be resolved, as well as disputes involving employees who were members of or eligible to be members of the relevant unions.
65. As s 172(1) of the Act provides, an enterprise agreement can be "about" matters pertaining to the relationship "between the employer ... and the employee organisation or employee organisations, that will be covered by the agreement". A dispute about, or involving, that relationship is a subject-matter for which s 186(6) requires a dispute resolution process to be included in an enterprise agreement. However, neither cl 28.1(a) nor par (3) of the model term, in Sch 6.1 to the Regulations, expressly addresses whether a dispute that any of the five unions may have with Energy Australia, arising under the Yallourn agreement as to its interpretation or Energy Australia's compliance with its terms, can be addressed only by discussions between the employer and one or more employees, without the involvement of the union(s) concerned.
66. Clearly enough, the literal phrasing of each of par (3) of the model term and steps 1 and 2 in cl 28.1(a) is apposite to cover a dispute that involves only the employer and one or more employees. However, both the model term and cl 28 are intended to provide, as s 186(6)(a)(i) requires, "a procedure that requires or allows [the Commission] ... to settle disputes ... about any matters arising under the agreement" (emphasis added). Therefore, a literal construction of cl 28 that precluded any of the five unions that are parties to the Yallourn agreement from initiating a dispute about a matter arising under it for which it has a workplace right, would defeat the purpose which the first three paragraphs of cl 28 (preceding cl 28.1) and ss 186(6) and 341(1) required the dispute resolution process in the clause to serve.
67. Energy Australia's argument that the Yallourn agreement did not provide any basis for any of the five unions to raise a dispute under cl 28 must be rejected. That is because, if the five unions themselves could never raise or pursue a dispute about their workplace rights, as employee organisations, covered by the Yallourn agreement within the meaning of ss 53(2), 172(1)(b) and 186(6)(a)(i), then cl 28 would not provide a procedure to settle a class of category 1 matters that could arise under the enterprise agreement. Accordingly, cl 28 would not comply with s 186(6).
Though on one view of clause 31 the procedure is designed to resolve disputes between one or more aggrieved employees and their employer, a construction of the provision which has the result that the Appellant is unable to initiate a dispute under the procedure is untenable in light of what is said by the Full Court in Energy Australia Yallourn.[5]