The Peninsula Aero Club has existing use rights for the continued use of the 'authorised landing ground' and aircraft landing ground' at the subject land (Tyabb airfield) between the hours of 9:30am and 10:30am on Sundays for the purposes of aircraft departures and landings.
Mr M Townsend, Barrister instructed by Mornington Legal
Declaration that the Peninsula Aero Club has existing use rights for the continued use of Tyabb airfield for take-offs and landings by aircraft between the hours of 9:30am and 10:30am on Sundays; and alternatively, to exercise discretion to remove the reference to the use of the airfield for take-offs and landings by aircraft between the hours of 9:30am and 10:30am on Sundays in condition 2 in Permit No P65/0002.09, condition 2 in Permit No P2/0268.09, and condition 6 in Permit No P91/7308.1.
Application under section 149A(1)(b) of the Planning and Environment Act 1987 - declaration
Application under section 149(1)(a) of the Planning and Environment Act 1987 - secondary consent
The subject land is irregularly shaped. It accommodates a sealed north-south runway and an unsealed east-west runway. The subject land has a frontage to Mornington-Tyabb Road of approximately 100 metres, a frontage to Stuart Road of approximately 200 metres, and an overall site area of 27.794 hectares.
The subject site is developed with infrastructure relating to use as an 'authorised landing area'.
... has existing use rights pursuant to section 6 of the Planning and Environment Act 1987 (Vic) and the Mornington Peninsula Planning Scheme to use the authorised landing ground at the Subject Land between 9:30am and 10:30am on Sundays for the purposes of aircraft departures and landings.
Tyabb airfield was originally constructed in conjunction with the subdivision of 4 ha lots fronting Mornington-Tyabb Road as an air park by D Thompson in early 1962 and use of the land as an airfield commenced in April 1963 (using the East-West runway).
PAC was formed in March 1964. In May of that year, Mr Thompson obtained approval from the Department of Civil Aviation (DCA) to use Tyabb airfield for flying training using the north-south runway only.
As certain minimum requirements could not be met, the DCA considered that Tyabb airfield could not be approved as a "licensed aerodrome" but accepted that it met the requirements for an "authorised landing area" (ALA).
The 'first aviation activity on what is now part of the land occurred in 1962 when land at the rear of a number of lots fronting the Mornington-Tyabb Road was acquired and combined to provide the east-west runway. Subsequently in around 1963 or 1964 Mr Thompson acquired more of what is now the land to the south and then established the north-south runway (in its original form). This the council says was completed and inspected by representatives of the then Department of Civil Aviation in February 1964.
For present purposes, PAC simply notes the incongruity of the remarkable suggestion that use for the purpose of an "airfield", "authorised landing ground", "flying school" or other constituent/ancillary component of use for the purpose of an "airport" is prohibited within the SUZ3 (Airfield development).
(3) Subject to subsections (4) and (4A), nothing in any planning scheme or amendment shall -
(a) prevent the continuance of the use of any land upon which no buildings or works are erected for the purposes for which it was being lawfully used before the coming into operation of the scheme or amendment (as the case may be); or
(b) prevent the use of any building which was erected before that coming into operation for any purpose for which it was lawfully being used immediately before that coming into operation; or
(c) prevent the use of any works constructed before that coming into operation for any purpose for which they were being lawfully used immediately before that coming into operation; or
(d) prevent the use of any building or work for any purpose for which it was being lawfully erected or carried out immediately before that coming into operation; or
(e) require the removal or alteration of any lawfully constructed building or works.
An existing use right is established in relation to use of land under this scheme if any of the following apply:
- The use was lawfully carried out immediately before the approval date.
- A permit for the use had been granted immediately before the approval date and the use commences before the permit expires.
- A permit for the use has been granted under Clause 63.08 and the use commences before the permit expires.
- Proof of continuous use for 15 years is established under Clause 63.11.
A use in Section 2 or 3 of a zone for which an existing use right is established may continue provided:
If, in relation to an application or proceeding under the Act or this scheme, including an application for a certificate of compliance under Section 97N of the Act, the extent of any existing use right for a period in excess of 15 years is in question, it is sufficient proof of the establishment of the existing use right if the use has been carried out continuously for 15 years prior to the date of the application or proceeding.
An existing use right may be established under this clause even if the use did not comply with the scheme immediately prior to or during the 15 year period, unless either:
... the use of the appeal land (in addition to the existing permitted use) for the purpose of the use of the existing aircraft landing ground facilities for the landing and take off of aircraft having an all up weight of between 4,500 and 12,500 pounds but not exceeding a maximum all up weight of 12,500 pounds.
Fundamentally, the concept of existing use rights is one of fairness. It would be unfair if a use which was operating lawfully one day either under a planning scheme or permit could be rendered unlawful the next day because of an amendment to a planning scheme, which made the use prohibited or subject to conditions. For this reason, section 6(3) of the Planning and Environment Act 1987 provides that nothing in any planning scheme shall prevent: ... the continuous use of the land.
Clause 63 also goes beyond the ambit of protection directed by section 6(3) in terms that whilst section 6(3)(b) and (c) protect use of any building or works erected or constructed before an amendment for any purpose for which they were lawfully being used immediately before the amendment came into operation, clause 63 talks about existing use rights being established in respect of land, not just the use of buildings and works. It avoids the complications that might arise if the exact words used in section 6(3) were used in the planning scheme relating to use of buildings and works, rather than use of land, although it provides that a permit for any new buildings or works is required.
Having regard to the fundamental reason why existing use rights should be protected and the scheme for doing so that is established under the Act and the planning scheme, I therefore return to the question previously posed as to why it is necessary in this particular case to rely upon clause 63.01 at all in establishing the Seers' right to continue to use the land for the purpose set out in the permit.
Clause 63.11 is a very useful provision when it cannot be established that the use was lawfully carried out immediately before the approval date. This may be because the use commenced unlawfully without a permit or, through the effluxion of time, it may not be possible to establish when or in what circumstances the use commenced. Sometimes, though, there is a tendency on the part of practitioners to assume that once a use has been established for 15 years, even though it commenced lawfully pursuant to a permit or the provisions of the (then) planning scheme, the establishment of an existing use right under clause 63.11 supersedes an existing use right established under the first dot point of clause 63.01 (use lawfully carried out immediately before the approval date) or a right under an ongoing permit. One implication of this assumption is that this renders the provisions of clause 63.05 inapplicable. In other words, the implication is that even though a use commenced lawfully under a permit, once it has been going for 15 years, the conditions of the permit can be ignored because an existing use right is established under the alternative provision of clause 63.11.
This cannot be right. It would make a mockery of the whole scheme of the Planning and Environment Act 1987 which provides that planning permits granted under a planning scheme and in accordance with the Act are a key means of regulating the use and development of land in Victoria.
Clearly, there will be circumstances where a use has commenced lawfully under a permit but, over time, the use has expanded beyond what is allowed under the permit or has transformed into a different use. In those cases, the establishment of existing use rights may depend on either or both the first and fourth dot points of clause 63.01, depending on the characterisation of the use or uses. However, unless there is a reason for needing to rely upon clause 63.11 (15 years continuous use) in preference to the first dot point (the use was lawfully carried out immediately before the approval date), I do not consider reliance should necessarily be placed on clause 63.11 and the fourth dot point rather than the first dot point of clause 63.01 or, as in this case, on an existing valid permit.
It is important to recognise that the local planning context was significantly different when the airfield was originally established in 1965. When Tyabb Airfield was initially approved in the mid 1960's it was considered a small, local facility and the limited range of conditions imposed demonstrate that only a very basic level of planning control was considered necessary. Today, Tyabb Airfield functions more broadly as a General Aviation facility, supporting primarily recreational use but catering for a diverse mix of aviation uses including a flight school, charters, engineering services for aircraft, the restoration and maintenance of historic aircraft, and support for emergency-services. It also hosts the biennial Tyabb air show.
It is clear that today the use of the airfield has since evolved and is very different to what is[t] was in 1965. Given the evident increase in intensity and diversity of activity occurring on the land, and the lack of additional regulation, Council officers argue that any future development must be considered cohesively and in conjunction with the use and future development of the site as a whole. This argument is supported by the very purpose of the Special Use Zone Schedule 3 (SUZ3); to provide for the coordinated use and development of land in the vicinity of the Tyabb Airfield. Clause 65.01 of the Planning Scheme (Approval of an Application or Plan) also requires that before deciding on an application the Responsible Authority must consider as appropriate and amongst other things, the orderly planning of the area and the effect on the amenity of the area from both a use and development perspective.
...has existing use rights pursuant to section 6 of the Planning and Environment Act 1987 (Vic) and the Mornington Peninsula Planning Scheme to use the authorised landing ground at the subject land between 9.30am and 10.30an on Sundays for the purposes of aircraft departures and landings.
The Peninsula Aero Club has existing use rights for the continued use of the 'authorised landing ground' and 'aircraft landing ground' at the subject land (Tyabb airfield) between the hours of 9:30am and 10:30am on Sundays for the purposes of aircraft departures and landings.
SHOULD THE RELEVANT CONDITION IN EACH PERMIT BE DELETED?
The primary permission given by each of these permits is to use the land as an airfield, or as is put, an authorised landing ground. The conditions work to control how that use will then operate, i.e. they set boundaries or limits on the use. The amendments do not change these boundaries. In fact, the amendments do not change the operation of these conditions at all. What the amendments do is to afford the PAC an opportunity to apply for variations to those limits from time to time, for whatever reason that it might feel is justified.
[1] The submissions and evidence of the parties, any supporting exhibits given at the hearing, and the statements of grounds filed; have all been considered in the determination of the proceeding. In accordance with the practice of the Tribunal, not all of this material will be cited or referred to in these reasons.
[2] P65/0002.09 - condition 2; P72/0268.09 - condition 2; P91/7308.1 - condition 6
[3] Turbulence over Tyabb - A History of airports and aviation in the Shire of Hastings, DM Thompson, 1985; Letter to Thompson - 3 Aug 1964; Letter Department of Civil Aviation Aug 1964; Minister for Local Governments decision - 1967; DCA letter to Honourable P Lynch, May 1971; PAC's submission to Minister for Planning - Nov 1982; Department of Aviation Letter to PAC - 20 Sep 1982; Shire's submission to Panel - 1983; Vowell Air Services Brochure; Panel Report Amendment Co 8 1983; AAT Decision 1991
[5] Tyabb & District Ratepayer's Business & Environment Group Inc v Mornington Peninsula SC [2012] VCAT 1475
[6] (Red Dot) [2016] VCAT 1198