[2023] VCAT 168
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2023-02-23
Mr J, Ms J
Original judgment source is linked above.
REQUIREMENTS
R5 - Residential subdivisions must deliver a broad range of lot sizes capable of accommodating a variety of housing types.
R6 - Residential subdivision applications must demonstrate how they will contribute to the satisfaction of minimum housing yields in broad town centre catchments as described on Plan 3 and Table 2.
R7 - Development must appropriately respond to the existing railway station, potential future railway station sites, and future Principle [sic] Public Transport Network (PPTN) through the creation of opportunities for high density residential development.
R8 - Lots must front or side:
R9 - Subdivision applications must include indicative concept layouts for any lots identified for the future development of medium density, high-density, or integrated housing that suitably demonstrate:
GUIDELINES
G8 - Residential subdivisions should provide across each neighbourhood a broad range of lot sizes capable of accommodating a variety of housing types as described in Table 1.
G9 - Subdivision of land within a walkable distance of town centres, train stations, potential future station sites, and designated public transport routes should create a range of lot sizes suitable for the delivery of medium and higher density housing types.
...no further changes can be made to the plans due to the lack of market for apartment/stacked housing outcomes in growth areas currently and that the application meets the requirements of the Tarneit North Precinct Structure Plan concerning residential outcomes in this location.
A subdivision should implement any relevant housing strategy, plan or policy for the area set out in this scheme.
Lot sizes and mix should achieve the average net residential density specified in any zone or overlay that applies to the land or in any relevant policy for the area set out in this scheme.
...
Street tree planting associated with lots with a frontage of less than 8.5 metres
REQUIREMENTS
Street trees must be provided on both sides of all roads and streets (excluding laneways) at regular intervals appropriate to tree size at maturity and not exceeding the average intervals below unless otherwise agreed by the responsible authority:
R1 -
R3 - Street tree planting must use locally appropriate species and be consistent with the Wyndham City Street Tree Policy, Subdivision Landscape Works Standards and Specifications Manual and any guidance provided on the relevant cross section within this Precinct Structure Plan.
R40 - Configuration of vehicle access to lots from a public street must ensure that there is sufficient separation between crossovers to allow for a minimum of one on-street car park for every two residential lots.
R41 - Where a lot that is six metres or less in width, vehicle access must be via rear laneway, unless otherwise approved by the responsible authority.
GUIDELINES
G1 - Street networks within subdivisions should be designed to maximise the number of connections and direct views to waterways, open space and town centres.
G5 - Street trees should be used consistently across neighbourhoods to reinforce movement hierarchy and individual neighbourhood character.
G7 - Trees in streets and parks should be larger species wherever space allows (to facilitate continuous canopy cover).
For front loaded lots with a frontage less than 8.5 metres, functional layout plans must sufficiently show the provision of crossovers, canopy trees and service connections to the satisfaction of the Responsible Authority. Where this cannot be shown, the lot frontage will need to be increased to 8.5 metres.
R48 - Design of all streets and arterial roads must give priority to the requirements of pedestrians and cyclists by providing:
All to the satisfaction of the coordinating roads authority and the responsible authority.
R68 - Open space delivery
All public open space (where not otherwise provided via the DCP) must be finished to a standard that satisfies the requirements of the responsible authority prior to the transfer of the public open space to council, including but not limited to:
The road abutting the local park is 14.5 metres wide which results in the street footpath encumbering the open space and reducing the usable area by 1.5 metres for the entire length of the park. This is not consistent with Council position as parks must be unencumbered land as they are credited as part of the public open space contribution payments. This should be amended on the plans.
Dimensioned constructed waterway outside of Railway Corridor to be 50m wide and include a maximum 3m wide shared pathway to each side. Demonstrate canopy tree planting to both sides within the waterway with 1.5m offset from the shared pathway and outside the hydraulic width.
REQUIREMENTS
R26 - Design and layout of waterway corridors and other encumbered open space must maximise the potential for the integration of recreation uses, utility infrastructure and stormwater quality treatment assets, where this does not conflict with the primary function of the land.
R54 - Development must meet or exceed best practice stormwater quality treatment standards prior to discharge to receiving waterways as outlined on Plan 8, unless otherwise approved by Melbourne Water and the responsible authority.
R55 - Where a waterway is shown as 'natural' on Plan 8, development works must:
All to the satisfaction of Melbourne Water and the responsible authority.
R56 - Final design and boundary of constructed waterways, waterway corridors, retarding basins, stormwater quality treatment infrastructure and associated paths, boardwalks, bridges, and planting must be to the satisfaction of Melbourne Water and the responsible authority.
GUIDELINE
G36 - Streets should be the primary interface between development and waterways. Public open space and lots with a direct frontage may be provided as a minor component of the waterway interface. Where lots with direct frontage are provided, they should be set back up to 5.0 metres from the waterway corridor to provide pedestrian and service vehicle access to the satisfaction of Melbourne Water and the responsible authority
Prior to the Certification of any stage of the estate, the Plan of Subdivision must show sufficiently sized easements and/or reserves to be created over any proposed Melbourne Water asset to our satisfaction. This may require submission of an appropriate functional design to the satisfaction of the traditional landowner(s), Melbourne Water and Council.
Prior to the endorsement of the Development Plan, any lot or design changes as recommended or required by the final Stormwater Management Strategy must be made to the proposed Development Plan to the written satisfaction of the Responsible Authority and Melbourne Water. While Melbourne Water offers in principal [sic] support for the Development Plan, it is expected that alterations will be required to be made to the proposed Development Plan to accommodate for the findings of the Stormwater Melbourne Water Management Strategy. Melbourne Water reserves the right to enforce these amendments as part of this condition of permit.
To provide for the safe, efficient operation of public transport and the comfort and convenience of public transport users.
To provide public transport stops that are accessible to people with disabilities.
Road alignment and geometry along bus routes should provide for the efficient, unimpeded movement of buses and the safety and comfort of passengers.
While this arrangement of lots backing onto this VicTrack reserve is acceptable, it will ultimately result in an awkward and unfortunate legacy resulting from the delivery of the future Train Station.
I understand that once the station has been developed, that VicTrack will dispose of the reserve, enabling the two 14.5m wide (east-west) aligned local streets to connect through to the neighbouring development and the rest of the reserve repurposed.
... I consider the provision of both Style Way and Friend Way to be sufficient to facilitate connection between these neighbourhoods.
...
In general, I find the provision of the 20m wide VicTrack reserve, to facilitate construction of future Train stations within growth areas (in a timely fashion) a necessary precaution, but one that has interim and legacy spatial imposts on the development of adjacent land, should the surrounding neighbourhood develop prior to the delivery of the Train station. In instances (such as this) where if the adjacent land seeks to develop in advance of the public transport infrastructure, I would advocate that the access to and construction of the station should occur via the established street network. This would enable the more seamless absorption of the VicTrack reserve into the layout of the new neighbourhood and a more efficient and integrated outcome. Avoiding any potential obvious legacies within the ultimate subdivision layout and street network.
I believe there are opportunities for both the applicant and the Department of Transport and Planning to collaborate and potentially enter into a land swap arrangement (in respect of the VicTrack reserve) and revise the layout of the eastern portion of the subdivision to a mutually beneficial outcome, now that there is a State Government commitment to deliver the new Train station in the near future.
[1] Section 4(2)(d) of the Victorian Civil and Administrative Tribunal Act 1998 states a failure to make a decision is deemed to be a decision to refuse to make the decision.
[2] The submissions and evidence of the parties, supporting exhibits given at the hearing, and statements of grounds filed have all been considered in the determination of the proceeding. In accordance with the Tribunal's practice, not all of this material will be cited or referred to in these reasons. This includes submissions about a limited number of conditions filed with my leave after the hearing by the Council and applicant.
[3] Tribunal Book page reference (TB) TB565. The subject land is outlined in a red dashed line. The northern portion of the land is outlined in blue.
[4] The Tarneit North Precinct Structure Plan September 2014, amended May 2022.
[6] Extract from the plan at TB342. The red line is the boundary of DDO10 (not DPO10 as cited in the legend to the plan). The orange line depicts a sewer line.
[8] Victorian Civil and Administrative Tribunal Act 1987.
[9] Letter dated 16 November 2022, TB786.
[11] The election was on 26 November 2022.
[12] Section (98)(1)(c) of the Victorian Civil and Administrative Tribunal Act 1998.
[13] Relevant scheme clauses are listed in the 'Information' section of these reasons.
[20] TB137, with additional aspects of the vision in section 2.1 of the TNPSP.
[21] Proposed Amendment C265 seeks to change this, as I refer to in these reasons.
[22] There are also new Precinct Structure Planning Guidelines, VPA, dating from October 2021.
[23] Such as the Town Centres & Employment Figure 1, TN144.
[24] TB584-585, Wyndham North Precinct Structure Plans Background Report June 2013.
[25] Wyndham North Precinct Structure Plans Background Report June 2013, section 3.3.2, page 12.
[26] Extract, Future Urban Structure Plan 2, TB136. The subject land is notionally outlined in red.
[28] Extract from Plan 7, with my arrow identifying the potential future station.
[30] I note that this is not shown or specified in the application plans.
[31] My highlight added to the extract from Table 2.
[32] Applicant's submission, paragraph 44, footnotes excluded.
[35] TB348. As the Council notes, some concepts show apartments straddling proposed lot boundaries.
[36] Such as through clauses 02.03-6, 11.01-1L, 11.03-1S, 16.01-1S, 16.01-1L and 18.02-3S.
[38] Such as using the appendix to Mr Negri's evidence, TB599. Mr Campbell's evidence is that this material should be relied on rather than other estimates by his firm - TB663-664.
[39] Although the three storey option includes a large expanse of surface parking, as Mr Rantino observes.
[40] I note Urbis is the author of a planning report that accompanied the permit application (4 March 2022) but this material does not appear to have formed part of the permit application. It is unclear to me whether R9 was met with respect to relevant information. I further note the planning report, in addressing R7, does not refer to the railway station.
[42] The Wyndham North Development Contributions Plan adopts the same metrics for medium and high density housing, at page 51. These are higher than 'conventional' housing which is defined as 'Housing with an average density of 10 to 15 dwellings per net developable hectare'.
[46] This dimension is not stated in the application plans. I note that cross-sections included in Mr Holmes' evidence (Appendix 3, TB751) are not drawn on a perpendicular alignment as discussed at the hearing, so that they variously depict different corridor widths.
[48] TB639 with respect to the width of the rear access to one group of lots. The Council and Melbourne Water do not appear to have taken any issue with the proposed 4.0 metre setback. This is, however, another dimension which is not marked on the plans.
Peet No. 1895 Pty Ltd
Wyndham CC [2023] VCAT 168