[2021] NSWSC 331
Supreme Court of NSW
2021-03-10
Stevenson J, Mr J
Original judgment source is linked above.
Solicitors: Vincent Young Lawyers (Plaintiff) Marsdens Law Group (Defendant) File Number(s): 2019/133490
The issues The contractual context The Project Delivery Agreement The Voluntary Planning Agreement The Umbrella Agreement The Fit Out Agreement The 2012 Design The determination of the FOA Contract Price at $2.171 million The events leading to 24 February 2017 The pleading point The 24 February 2017 Agreement Directions to vary the work Payce's damages case The Superintendent point The Independent Certifier point Council's misleading or deceptive conduct case The final payment claim point The wrong entity submission The "BCA" point Quantum Mr Daubney's references to Mr Rigby's affidavit The integers in Payce's damages calculation Actual costs as best evidence of reasonable costs The amount to be attributed to the FOA Contract Price The Base Build Costs The Builder's margin Escalation of the 2012 Design prices The claims where the parties have agreed to a "split the difference" Variation 1 - internal walls - $12,078 Variation 3 - modification to operable wall track in function room - $6,086.02 Variation 5 - CO2 monitoring - $15,290 Variation 7 - skylight - $7,194.15 Variation 8 - security door - $6,147 Variation 9 - walls and windows - $28,719.64 Variation 12 - boxing out of column to concierge - $10,459 Variation 14 - library - comms room wall - $7,500 Variation 15 - library - comms room air conditioning - $1,170 Variation 16 - library - young adults glazed balustrade - $37,094 Variation 17 - automatic fire detection and warning system Variation 18 - mechanical system - $192,010.51 Variation 19 - supply of lighting - $276,070.33 Variation 20 - power and data point Variation 21 - electrical - miscellaneous - $30,226 Variation 22 - wifi Variation 23 - ceiling finishes - $372,598.48 Variation 24 - hearing loop - $142,279.50 Variation 25 - security system - $40,233.38 Variation 26 - internal glazing - $30,071.60 Variation 27 - blinds - $11,860 Variation 29 - acoustic screen - $23,430 Variation 30 - acoustic insulation - $77,754.60 Variation 31 - picture rail and hangers - $10,128 Variations 33 and 33A - other consultant fees $88,250 - CKD's fees $38,700 Variation 41 - plasterboard and painting to staff room - $7,098.42 Variation 42 - section 96 application fees - $10,480 Variation 43 - section 96 planner fees - $6,500 Variation 52 - additional works - $86,020 Conclusion
Judgment
The issues
The Project Delivery Agreement
The Voluntary Planning Agreement
The Umbrella Agreement
The Fit Out Agreement
The 2012 Design
The determination of the FOA Contract Price at $2.171 million
The events leading to 24 February 2017
The pleading point
The 24 February 2017 Agreement
Directions to vary the work
Payce's damages case
The Superintendent point
The Independent Certifier point
Council's misleading or deceptive conduct case
The final payment claim point
The wrong entity submission
The "BCA" point
Quantum
Mr Daubney's references to Mr Rigby's affidavit
The integers in Payce's damages calculation
Actual costs as best evidence of reasonable costs
The amount to be attributed to the FOA Contract Price
The Base Build Costs
The Builder's margin
The claims where the parties have agreed to a "split the difference"
Variation 1 - internal walls - $12,078
Variation 3 - modification to operable wall track in function room - $6,086.02
Variation 5 - CO2 monitoring - $15,290
Variation 7 - skylight - $7,194.15
Variation 8 - security door - $6,147
Variation 9 - walls and windows - $28,719.64
Variation 12 - boxing out of column to concierge - $10,459
Variation 14 - library - comms room wall - $7,500
Variation 15 - library - comms room air conditioning - $1,170
Variation 16 - library - young adults glazed balustrade - $37,094
Variation 17 - automatic fire detection and warning system
Variation 18 - mechanical system - $192,010.51
Variation 19 - supply of lighting - $276,070.33
Variation 20 - power and data point
Variation 21 - electrical - miscellaneous - $30,226
Variation 22 - wifi
Variation 23 - ceiling finishes - $372,598.48
Variation 24 - hearing loop - $142,279.50
Variation 25 - security system - $40,233.38
Variation 26 - internal glazing - $30,071.60
Variation 27 - blinds - $11,860
Variation 29 - acoustic screen - $23,430
Variation 30 - acoustic insulation - $77,754.60
Variation 31 - picture rail and hangers - $10,128
Variations 33 and 33A - other consultant fees $88,250 - CKD's fees $38,700
Variation 41 - plasterboard and painting to staff room - $7,098.42
Variation 42 - section 96 application fees - $10,480
Variation 43 - section 96 planner fees - $6,500
Variation 52 - additional works - $86,020
Conclusion
Endnotes
Payce Communities Pty Ltd
Canterbury-Bankstown Council
(2011) 243 CLR 588
(1985) 157 CLR 215
[2011] HCA 21