austlii:qld/QBCCMCmr/2025/265
General information, not legal advice.
QBCCMCmr
2025-07-30
Original judgment source is linked above.
Paragon on Arthur [2025] QBCCMCmr 265
The Body Corporate for Paragon on Arthur (respondent)
Body Corporate and Community Management Act 1997 (Qld) (Act), sections 227(1)(b) and 229(3)(a)
Body Corporate and Community Management (Accommodation Module) Regulation 2020 (Accommodation Module)
MAINTENANCE; PROPERTY DAMAGE; - where body corporate wishes to undertake repairs to common property and the owner's property damaged by water ingress but the lot owner refuses to provide access.
The Applicant says they nominated SDX Engineers to supervise necessary remedial works. They believe that Pursuant to by-law 7.6, the Body Corporate was required to respond or object within a prescribed timeframe. No formal objection, alternative nomination, or valid reason for delay has been provided. Accordingly, he says the nomination must be taken to have been accepted, and the Body Corporate's refusal to cooperate constitutes a breach of the By-Laws.
The Applicant says the SDX synopsis provided significant insights into Non Compliant Defects of completed and failed works of RPS in July 2020. The critique of method for the new proposed works alluded to likely failure of the new works. The revised quote input into the EGM April 2025 showed no alterations to the original, thereafter receiving a formal Report in March 2025. He says there is a clear need to seek alternative contractors regarding the non compliant works.
Motion 2 of the EGM purports to rely on funds from a previous 2020 resolution. However, invoices from that period show that the entirety of the $33,593.11 allocation was spent. The applicant says "the 2025 motion misleads owners by suggesting that $44,131.27 remains available, when this is demonstrably false". The motion also proposes new works with materially changed specifications (including membrane type and drainage), triggering the requirement for fresh approval and accurate disclosure.
Invoice Number: 354 Invoice Date: 22/06/20 $14,087.98
Invoice Number: 355 Invoice Date: 22/06/20 $ 7,867.20
Invoice Number: 356 Invoice Date: 29/06/20 $ 2,271.06
Invoice Number: 357 Invoice Date: 07/07/20 $ 9,391.99
The applicant says only one quote was provided for works exceeding $20,000, in breach of the applicable Regulation Module requiring multiple quotations. The Body Corporate has failed to disclose or assess alternate quotes despite being aware of an existing recommendation by SDX Engineers. The continued attempt to proceed with works using only a single contractor, previously subject to complaints and legal orders, is procedurally flawed and raises risks of legal, structural, and financial liability.
Next, the applicant says there are no inclusions for building works removed required to be rebuilt, privacy screens, lights, damaged stairwell housing or flashings included in the Quote by RPS.
The applicant says he has raised concerns regarding the work undertaken by RPS and says he is concerned about compliance with building standards.
Finally the applicant says that an Interim Order is therefore necessary to preserve the current position and allow the Adjudicator to determine the final dispute. He says that
should the proposed works proceed while this dispute remains unresolved, the applicant may suffer irreparable harm, including:
6.2 An order that the Body Corporate must accept that the remedial works on Lot 38 are to be carried out by RMS (as recommended by Structural Diagnostics), under the supervision and direction of Structural Diagnostics (SDX), in accordance with the final Scope of Works established through the Engagement Notice issued pursuant to clause 7.5 of the By-laws on 14 March 2025, and the Engagement Nomination made pursuant to clause 7.8 of the By-laws on 4 April 2025.
6.3 An order that the Body Corporate pay for and ensure all rooftop works comply with:
a) the Queensland Building and Construction Commission Act 1991 (QBCC Act),
b) the National Construction Code (Building Code of Australia), and
c) that all such works be:
- certified by a qualified hydraulic engineer,
- executed by a licensed plumbing contractor (noting RPS lacks the required QBCC licence), and
- accompanied by all relevant Form 16s or compliance certificates on completion.
d) the Engagement Notice dated 14 March 2025, and Engagement Nomination dated April 4th 2025, submitted by the Applicant, and fund the associated expert investigation, design and supervision process, as outlined in SDX's report, with estimated costs of $8,500-$11,000 to be paid from the Sinking Fund within 14 days.
7.1 the source of all water ingress into the Applicants lot be repaired;
7.2 the water damaged gyprock and any other water damaged elements in the Applicants lot is removed and replaced to mitigate any risk of exposure to mould spores;
7.3 all areas of the lot that have been water damaged be inspected and certified free of any mould by appropriately qualified mould experts.
7.4 that the costs of the Gyprock requiring replacement beyond the Timmers Quote 879502 August 15 2022 be measured and invoiced by the Contractor to the Body Corporate and be paid, by the Body Corporate
7.5 that the costs of Electrical cabling be checked when the plaster is removed, and replaced if affected and damaged from water ingress, and electronic items affected and damaged from water ingress from 2022, per quotes from Allscope Communications, be paid for by the Body Corporate, for product and installation.
7.5a For the Body Corporate to authorize and fund the initial evaluation the condition of wiring Quote Number QU-BSEQ-0005 Bright sparky Electrical TOTAL AUD 3,795.00
7.5b That should the report determine wiring is damaged and require replacement, an order should be made for the Body Corporate to authorize and fund the quote from Bright Sparky Electrical.
7.5c That the Quote from Allscope Communications be funded and paid for by the Body Corporate within 14 days following the outcome for Quote# 8034 16th April 2025 TOTAL: $11,533.50
[22] Consequently, there is no need to order the body corporate to carry out this work. The body corporate will do it when Mr Ehrlich allows it. While Mr Ehrlich may disagree with the body corporate's approach to the work, it is nevertheless work the body corporate is obliged to carry out in some form, and the specific approach the body corporate has taken was properly authorised at a general meeting. In these circumstances, Mr Ehrlich must allow the body corporate access to his lot pursuant to section 163 of the Act notwithstanding that he might prefer the body corporate met its maintenance obligations in some other way.
[23] If the work is ultimately unsuccessful as Mr Ehrlich apparently fears it will be, the body corporate will be required to correct it. That is surely preferable to leaving the rooftop in its present condition and allowing the water ingress to lot 38 to continue indefinitely.
[24] To the extent that Mr Ehrlich's opposition to the work is due to his preference for a different tile, he has already had his arguments on that point dismissed by Adjudicator Miskinis.
[25] If Mr Ehrlich continues to oppose the body corporate's entry to his lot for the purpose of carrying out the work to his terrace, I suggest the body corporate might be more assertive with its rights under section 163 of the Act. Buildcheck described the rectification works as "urgent" due to the risk that continued water ingress may cause concrete spalling, which could put the body corporate in contravention of its obligation to maintain roofing structures and essential supporting framework in structurally sound condition.
Where repair work has to be done at the expense of A whereas B obtains the practical benefit, or is subjected to the outcome of the work, I think the adjudicator was perfectly right to decline to stipulate that work ought to be planned and done to the satisfaction of (the lot owner). Whoever pays the piper ought to be able to call the tune. In my opinion, the body corporate ought to have a reasonably wide discretion in determining how it carries out its obligation. It may well be objectionable that the lot owners as a body corporate should have to pay beyond the minimum necessary to provide a building that does not leak.
in the absence of your unequivocal confirmation, particularly confirmation that you will give the body corporate and its contractors all reasonable and necessary access to undertake the necessary maintenance work, it is unreasonable to either expect that the body corporate will attempt to gain access to your lot to undertake the maintenance works or engage RPS for that purpose, without the benefit of a formal notice of entry, alternately and preferably an order requiring you to give access; and, in the circumstances, the body corporate will not do so; and
The body corporate repeats its reservation of rights identified in the penultimate paragraph of the letter dated 14 April 2025. In short, until you co-operate, these maintenance works will likely remain incomplete and at your risk.[21]
[23 ] If the work is ultimately unsuccessful as Mr Ehrlich apparently fears it will be, the body corporate will be required to correct it. That is surely preferable to leaving the rooftop in its present condition and allowing the water ingress to lot 38 to continue indefinitely.
[1] Paragon on Arthur [2024] QBCCMCmr 166
[2] Paragon on Arthur [2023] QBCCMCmr 114 at [48]- [49].
[5] Emails from Chris Hampson, Remedial Property Solutions, to Preston Hoad, Queensland Building and Construction Commission, 25 May 2021 & from Laurence Vecchio, committee chairperson, to Stacey O'Flynn, body corporate manager, 8 April 2022.
[6] Emails from Mr Ehrlich to Stacey O'Flynn, 8 & 26 April 2022.
[7] Email from Adam Williams, Managing Director of Platinum Hydraulics, to Mr Ehrlich, 19 May 2022.
[8] Email from Rose Jocumsen, body corporate manager, to "Sean" of Abstract Plumbing, 16 June 2020.
[9] Email from Chris Hampson to Preston Hoad, 25 May 2021.
[10] Email from Laurence Vecchio to Stacey O'Flynn, 8 April 2022.
[11] Paragon on Arthur [2024] QBCCMCmr 166
[14] Sections 226, 228 and 276 of the Act
[16] Paragon on Arthur [2024] QBCCMCmr 166
[17] Paragon on Arthur [2024] QBCCMCmr 167
[19] Although an applicant must identify a genuine legal issue to be decided, the granting of an interim order by itself does not indicate whether or not an applicant will ultimately be successful on their application for final orders.
[20] Paragon on Arthur [2024] QBCCMCmr 166
[22] Paragon on Arthur [2024] QBCCMCmr 166
[23] Attachments F, G & H to submission