[2025] NSWCATCD 77
General information, not legal advice.
NCAT Consumer and Commercial
2025-08-28
Original judgment source is linked above.
Allianz v Waterbrook [2009] NSWCA 224; (2009) 15 ANZ Insurance Cases 224
Arian v Nguyen (2001) 33 MVR 37; [2001] NSWCA 5
Bostik Australia Pty Ltd v Liddiard (No 2) [2009] NSWCA 304
Douglass v Lawton Pty Ltd (No 2) [2007] NSWCA 90
Eko Investments Pty Ltd v Austruc Constructions Ltd [2009] NSWSC 371
Elite Protective Personnel Pty Ltd v Salmon (No 2) [2007] NSWCA 373
Harper v Harper (No 2) [2025] NSWSC 360
Hogan v Trustee of the Roman Catholic Church (No 2) [2006] NSWSC 74
Michael Hill Jeweller (Australia) Pty Ltd v Gispac Pty Ltd (No 2) [2024] NSWCA 274
Monie v Commonwealth of Australia (No 2) [2008] NSWCA 15
Oshlack v Richmond River Council (1998) 193 CLR 72; [1998] HCA 11
Puri v Medical Council Of New South Wales (No 2) [2024] NSWCATOD 122
Ritter v Godfrey [1920] 2 KB 47
State of New South Wales v Stanley [2007] NSWCA 330
Tomanovic v Global Mortgage Equity Corporation Pty Ltd (No 2) [2011] NSWCA 256
Vella v Mir (No 3) [2020] NSWCATAP 17
Waterman v Gerling (Costs) [2005] NSWSC 1111
Yazgi v Permanent Custodians Ltd (No 2) (2007) 13 BPR 24; [2007] NSWCA 306
St George Design & Construction Pty Ltd (Respondent)
(1) Rejected the builder's defence under the principles in Allianz v Waterbrook [2009] NSWCA 224; (2009) 15 ANZ Insurance Cases 224 that a pre-purchase building inspection report was sufficient to sever the casual nexus between any breach of statutory warranties and loss or damage of the owners.
(2) Found that a defect in respect of water ingress involving the balcony/front façade and front window involved a major defect under s 18E of the HB Act.
(3) Found that a defect in respect of water ingress involving the dining room window was a major defect under s 18E of the HB Act.
(4) Found that a defect in respect of water ingress into the living room corner was a major defect under s 18E of the HB Act.
(5) Rejected the owners claim that alleged failed waterproofing over the garage was a major defect under s 18E of the HB Act.
(6) Found that inadequate falls to tiling in the bathroom of the granny flat and absence of a water stop angle in the shower area was a major defect under s 18E of the HB Act.
(7) Found that a work order under s 48O of the HB Act for the builder to rectify defects was the appropriate remedy. Of the 4 defect items, the Tribunal accepted the method of rectification of the owners expert over the builder's expert on most of the items.
(8) Found that Rule 38 of the Civil and Administrative Tribunal Rules 2014 (NSW) (NCAT Rules) applied to the proceedings.
(9) Made an order that the builder pay the owners' costs as agreed or assessed, but imposed a condition that any party may apply to vary the costs order in the manner set out in the orders.
(1) Builder pay the owners' costs to 16 July 2023 on the ordinary basis; and owners pay the builders costs from 17 July 2023 on an indemnity basis. The builder relies upon a Calderbank offer; or
(2) Each party bear their own costs, except for and adjournment application granted on 9 February 2024 for which the owners should pay the builder's "costs thrown away".
(1) "Investigate" the major defects identified in the Jim's Building Inspection report dated 16 April 2021 (items 2.01 to 2.10) to "determine the cause and extent of any defective and non-complying work undertaken" by the builder;
(2) Undertake "all necessary" remedial work found in respect of major defects identified in the report of Jim's Building Inspections to "an acceptable industry standard;" and
(3) The owners proceedings are withdrawn under s 48I(2) of the HB Act, with no order as to costs, and the parties "are to enter into a formal deed of release which reflects the above terms and the completion of the investigation and remedial works" by the builder "within a reasonable period of time".
"7. The applicants are to pay the respondent's costs thrown away of and incidental to the granting of leave to rely on Mr Xue's report and the adjournment of the hearing on 5 March 2024, on the ordinary basis, as agreed or assessed."
(1) The builder's submissions make no reference to its failed Allianz v Waterbrook [2009] NSWCA 224; (2009) 15 ANZ Insurance Cases 224 (Allianz v Waterbrook) defence.
(2) The hearing was adjourned on 19 September 2023 because the builder raised the Allianz v Waterbrook defence for the first time.
38 Costs in Consumer and Commercial Division of the Tribunal
(1) This rule applies to proceedings for the exercise of functions of the Tribunal that are allocated to the Consumer and Commercial Division of the Tribunal.
(2) Despite section 60 of the Act, the Tribunal may award costs in proceedings to which this rule applies even in the absence of special circumstances warranting such an award if -
(a) the amount claimed or in dispute in the proceedings is more than $10,000 but not more than $30,000 and the Tribunal has made an order under clause 10(2) of Schedule 4 to the Act in relation to the proceedings, or
(b) the amount claimed or in dispute in the proceedings is more than $30,000.
" [28] Clause 38 gives the Tribunal a wide discretion to make an order for costs. It does not specify the factors the Tribunal must take into account in exercising the discretion, although the discretion to make such an order must be exercised judicially: see, for example, Ruddock v Vadarlis [2001] FCA 1865 at [9].
[29] Where an application has been heard and determined on the merits and Clause 38 applies, the appropriate starting point for the exercise of the discretion is not that the parties are to pay their own costs. Rather, it is the well-established position at common law; that is, that the purpose of making a costs order is to provide compensation to the party in whose favour the order is made for the expense the party has been put to in prosecuting or defending legal proceedings. In general terms, this means that a party who is successful is entitled to an order for costs in its favour, subject to exceptions generally involving misconduct on the part of that party: Latoudis v Casey [1990] HCA 59; [1990] 170 CLR 534 ; Oshlak v Richmond River Council [1998] HCA 11 .
[30] In BNT Constructions Pty Ltd v Allen [2017] NSWCATAP 186 the Appeal Panel, having set aside a costs order made in the Consumer and Commercial Division, decided to re-exercise the costs discretion. Clause 38 was the applicable costs provision in that case. At [67] the Appeal Panel noted the following principles relevant to the exercise of the discretion:
(1) the starting point is that a successful party should be entitled to an order for costs in his favour;
(2) an award of costs is by way of an indemnity and not as punishment;
(3) there is no absolute rule that, absent disentitling conduct, a successful party is to be compensated by the unsuccessful party;
(4) the factors to be considered are not to be confined as to do so would constrain the general discretion;
(5) the relative success of the parties on different issues and the time taken to determine them may be relevant;
(6) the nature of the proceedings is relevant;
(7) the proper exercise of the discretion requires a decision maker to do justice between the parties and to exercise the discretion having regard to relevant considerations and in a manner which is not arbitrary and capricious."
(1) Unreasonable rejection of a Calderbank offer by the successful party.
(2) Mixed success on different issues by both parties such that a proportionate costs order should be made (Bostik Australia Pty Ltd v Liddiard (No 2) [2009] NSWCA 304 at [38]; Monie v Commonwealth of Australia (No 2) [2008] NSWCA 15 at [63]-[66]; Michael Hill Jeweller (Australia) Pty Ltd v Gispac Pty Ltd (No 2) [2024] NSWCA 274 at [20]); or an order that each party bear its own costs (Hogan v Trustee of the Roman Catholic Church (No 2) [2006] NSWSC 74 at [40]).
(3) Disentitling conduct by the successful party (Tomanovic v Global Mortgage Equity Corporation Pty Ltd (No 2) [2011] NSWCA 256 at [97] -[98]; Ritter v Godfrey [1920] 2 KB 47). An example of disentitling conduct is where the successful party's conduct caused unnecessary expense or delay (Douglass v Lawton Pty Ltd (No 2) [2007] NSWCA 90).
(4) The party achieves only very minor, or nominal, success in comparison to the extent of claims made (Eko Investments Pty Ltd v Austruc Constructions Ltd [2009] NSWSC 371 at [18]- [23]; Yazgi v Permanent Custodians Ltd (No 2) (2007) 13 BPR 24; [2007] NSWCA 306 at [24]).
(5) An earlier interlocutory costs order against the successful party.
"The failure by a party to accept an offer of compromise which is a Calderbank offer where that party does not achieve a judgment more favourable than the offer is one of the circumstances in which the court may exercise its discretion under r 42.1 of the UCPR to make some order other than costs following the event on the ordinary basis. However, merely because the party to whom the offer was made does not ultimately obtain a more favourable judgment does not automatically lead to a favourable costs order, or raise a presumption that such an order should be made: E Group Security at [57].
The onus is on the party making a Calderbank offer to satisfy the court that it should exercise the costs discretion in its favour, in particular that (a) the Calderbank offer embodies a genuine compromise and (b) it was unreasonable for the other party not to accept it, which is an evaluative judgment to be made by reference to the terms of the offer and all the relevant surrounding circumstances at the time that it was made, and not with the benefit of hindsight: Miwa Pty Ltd v Siantan Properties Pte Ltd (No 2) [2011] NSWCA 344 at [8], [11], [16]; Wheatley v Lakshmanan (No 2) [2022] NSWSC 851 at [97]; E Group Security at [57]-[58].
Relevant factors in determining whether the rejection of an offer was unreasonable include (a) the stage of the proceeding at which the offer was received; (b) the time allowed to the offeree to consider the offer; (c) the extent of the compromise offered; (d) the offeree's prospects of success, assessed at the date of the offer; (e) the clarity with which the terms of the offer were expressed; and (f) whether the offer foreshadowed an application for indemnity costs in the event of the offeree rejecting it: Hazeldene's Chicken Farm Pty Ltd v Victorian Workcover Authority (No 2) (2005) 13 VR 435; [2005] VSCA 298 at [25]; Miwa at [12]; Wheatley at [98]; E Group Security at [59]. A finding of unreasonableness should not be made other than on clear grounds: E Group Security at [58].
In relation to (d), what is required is an objective assessment of the offeree's prospects of success as at the date of the offer: Hazeldene's Chicken Farm at [30].
The practice of treating Calderbank offers in this way is informed by the public policy objective of providing an incentive to the parties to end their litigation as soon as possible and discouraging wasteful and unreasonable behaviour by litigants: Commonwealth Bank of Australia v Gretton [2008] NSWCA 117 at [41]. However, the mere fact that the offer is a reasonable one does not make it unreasonable for the offeree to have rejected it: Gretton at [74] and [120]."
(1) The builder was not clearly offering to perform any work to rectify defects. Rather, what the builder was offering to do was to "investigate" and then, only if the builder thought that there were major defects set out in the report of Mr Xue dated 16 April 2021, rectify those defects. The offer empowered the builder to "determine the cause and extent" of any defects. It follows that if the builder did not believe it caused any major defects, it did not have to rectify. That offer was vague, uncertain and entirely dependent upon the opinion of the builder.
(2) The offer was contingent upon the parties entering into a Deed at some future time. However, no terms of the Deed were identified. Again, the terms of the offer were vague and uncertain.
(3) It cannot be said that had the offer been accepted, the owners would have been in a better position (or no worse position) than the work orders ultimately made by the Tribunal. By the time the Tribunal determined the matter at a contested hearing, the owners had obtained a second and more comprehensive report of Mr Xue, and the builder had obtained an expert report by Mr Roberts. The Tribunal found in favour of the owners on most of the defect issues and accepted the proposed method of rectification by Mr Xue on most of the defect issues. That was clearly a much better outcome for the owners than accepting an offer that the builder "investigate" and only repair the defects set out in Mr Xue's first report that the builder thought were major defects, as well as enter into a Deed with unspecified terms.
Any Other Reason to Depart from the Principle that the Builder Pay the Owners Costs?
(1) A hearing on the issue of costs is dispensed with under s 50(2) of the Civil and Administrative Tribunal Act 2013 (NSW).
(2) Order 3 of the Tribunal dated 28 May 2025 is varied to read: "The respondent is to pay the applicants' costs of the proceedings on the ordinary basis as agreed or assessed, other than in respect of the costs order made by the Tribunal on 9 February 2024.
(3) The Tribunal affirms the costs order made on 9 February 2024.
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.
Pan
St George Design & Construction Pty Ltd