[2025] VCAT 977
plaintiff. VCAT ordered the first respondent (4S Constructions Pty Ltd) to pay the first applicant (Owners Corporation PS628502Y) damages totalling $2,869,892.65; noted that because the first respondent is in...
VCAT found that the Owners Corporation could sue the builder for defects in the common property under the Domestic Building Contracts Act. On the evidence (building notices, expert reports, invoices), the Tribunal concluded the builder breached statutory warranties in multiple respects (fire resistance, balconies, essential safety measures, water ingress and other items). The Owners Corporation had already paid for and completed remedial works funded by loan; VCAT accepted the actual rectification costs, consultant fees and interest on the loan as recoverable and awarded $2,869,892.65. The builder entered liquidation after the hearing; the Tribunal published orders but noted that further steps against the liquidated company require leave of a competent court.
AI-generated legal information, not legal advice. Zoe can make mistakes. Check the cited source, and for advice about your situation consult a qualified Australian lawyer.
3 cited instruments linked from this judgment.
1,916 words · generated 06/07/2026
The Tribunal’s reasoning turned principally on three pillars:
Statutory framework and standing
Evidence of non-compliance and causation
Measure of loss and recoverability
Procedural point: despite the Builder’s liquidation and the automatic stay, the Tribunal proceeded to publish orders and reasons relying on earlier VCAT authority (Owners Corporation PS623721 v Shangri-La) permitting publication while noting that no further step against the liquidated company can be taken without judicial leave (PREAMBLE).
Before:
After:
This is an application of existing law rather than a departure from precedent.
Quotation (tribunal’s endorsement of actual cost approach): "It seems almost too simplistic to point out the actual cost was an impeccable alternative method of calculating cost." (quoted Meagher JA; Tribunal relied on this), translation: when the owner has paid to fix the problem, the invoice amounts are a straightforward and acceptable way to measure what the builder must reimburse.
Finding on standing: the Tribunal observed that the OC, as registered proprietor, 'falls within the expression "the owner for the time being" in s 54(3) of the DBC Act' (drawn from Body Corporate St James), translation: the owners corporation can sue for defects to common property just like any original contracting owner could.
Interest award summary: "In summary, the OC is entitled to damages in the nature of interest of ($889,228.74+$70,024.50) = $959,253.24. We will make an award accordingly.", translation: the Tribunal accepted the accounting and awarded nearly $960,000 of interest paid on the loan used to fix defects because the OC showed those interest costs were incurred to remedy the Builder’s breaches.
Procedural/risk note: because the builder is in liquidation 'a stay of the proceeding has come into effect' but 'this does not prevent us from publishing orders', translation: the Tribunal can give reasons and make orders publicly even though enforcement is restricted until the OC gets court permission to press on against the liquidated company.
This decision is most directly applicable where:
Where these facts are present, the Tribunal's approach, accepting actual rectification cost, consultant fees, and attributable interest, offers a practical path for recovery.
Enforcement reality given insolvency:
Apportionment and contribution issues:
The limits of actual-cost awards:
Attribution of finance costs:
Tribunal jurisdiction and procedural outcomes in insolvency:
Practitioners should analyse and document rectification choices, maintain clear invoices and accounting linking borrowings to remedial works, and where possible preserve expert evidence demonstrating necessity and reasonableness to support recovery under the DBC Act in similar factual scenarios.
Domestic Building Contracts Act 1995 (Vic): claim by owners corporation for damages made against builder for breach of warranties under s 8 of the Domestic Building Contracts Act 1995 (Vic); since date of hearing the first named respondent (builder) has gone into liquidation; Tribunal still may publish final orders: see Owners Corporation PS623721 v Shangri-La Construction Pty Ltd (Final Orders Defects) [2023] VCAT 501, [10];standing of the Owners Corporation as registered proprietor of the common property as proper party to bring claim for defects in the common property confirmed, following Body Corporate No 1/PS40911511E St James Apartments v Renaissance Assets Pty Ltd (2004) 11 VR 41; [2004] VSC 43; as the OC had undertaken all necessary rectification works, the observation of Meagher JA of the New South Wales Court of Appeal in Hyder Consulting(Australia) P/L v Wilh Wilhelmsen Agency P/L & Anor [2001] NSWCA 313, [86].that 'It seems almost too simplistic to point out the actual cost was an impeccable alternative method of calculating cost' applied.
4S Constructions Pty Ltd (ACN 083 248 122)(In liquidation)
Owners Corporation PS628502Y v 4S Constructions Pty Ltd (Building and Property) [2025] VCAT 977
Note: it is not necessary for the parties to attend at the Tribunal for the administrative mention.
(a) On 6 March 2023, the Honourable Justice Delany, Acting Member, handed down the ruling in Vaughan Constructions Pty Ltd v Melbourne Water Corporation (Building and Property) [2023] VCAT 233, determining that the VCAT had no jurisdiction determine contribution claims under the Wrongs Act 1958 (Vic) ('the Wrongs Act').
(b) Thereafter, the Builder accepted this Tribunal had no jurisdiction determine its proposed contribution claim. However, by paragraph 39 of its Points of Defence to the State's claim in this proceeding, the Builder alleged that the claim made by the State is an apportionable claim under the Wrongs Act and that the Building Surveyor and the Designer were concurrent wrongdoers.
(c) On 2 June 2023, the Builder and Mr Farag issued Supreme Court Proceeding S ECI 2023 02353 (the 'SCV Proceeding').
(d) In the SCV Proceeding, the Builder and Mr Farag (as the plaintiffs), sought various forms of relief against, inter alia, the RBS and the Designer, including a declaration concerning apportionment and a claim for contribution under the Wrongs Act.
(e) By application made 9 June 2023, the Designer sought orders that it be removed from this proceeding on the basis the claims made by Mr Farag were not apportionable claims and therefore paragraph 39 of the Defence ought to be struck out, and thereafter there would be no further reason for it to remain party to this proceeding in the Tribunal.
(f) The RBS supported the proposition that the claims made by Mr Farag in this proceeding were not apportionable claims.
The action continued without the joined parties
Defects identified in Building Order and Building Notices
(a) are of combustible construction contravening BCA Clause C1.9(b);
(b) are not enclosed contravening Clause 2.7 of BCA Specification C1.1;
(c) are not fire rated as required by Alternative Performance Solution; and
(d) do not achieve required FRLs specified in Table 3 of BCA Specification C1.1.
The damages claimed in relation to issues 1-9 are $888,822.
The damages claimed in relation to issues 10-12 are $729,590.
The damages claimed in relation to issues 13-15 are $86,864.
The damages claimed in relation to this issue are $29,800.
The damages claimed in relation to this issue are $32,764.
The damages claimed in relation to this issue are $14,633.
The damages claimed in relation to this issue are $16,148.
The damages claimed in relation to this issue are $7,040.
Implied warranties concerning all domestic building work
(a) the builder warrants that the work will be carried out in a proper and workmanlike manner and in accordance with the plans and specifications set out in the contract;
(b) the builder warrants that all materials to be supplied by the builder for use in the work will be good and suitable for the purpose for which they are used and that, unless otherwise stated in the contract, those materials will be new;
(c) the builder warrants that the work will be carried out in accordance with, and will comply with, all laws and legal requirements including, without limiting the generality of this warranty, the Building Act 1993 and the regulations made under that Act [4] ;
(d) the builder warrants that the work will be carried out with reasonable care and skill and will be completed by the date (or within the period) specified by the contract;
(e) the builder warrants that if the work consists of the erection or construction of a home, or is work intended to renovate, alter, extend, improve or repair a home to a stage suitable for occupation, the will be suitable for occupation at the time the work is completed;
In addition to the building owner who was a party to a domestic building contract, any person who is the owner for the time being of the building or land in respect of which the domestic building work was carried out under the contract may take proceedings for a breach of any of the warranties listed in section 8 as if that person was a party to the contract.
(a) inadequate or unreliable evidence of loss and damage incurred;
(b) insufficiently documented.
The OC's agents refused to cooperate with the Builder and its subcontractors
(a) At the time of Mr Twiselton's appointment as administrator, the owner's corporation had been served with a building notice dated 8 January 2018 issued by the City of Dandenong. The building notice identified that the building was a danger to the life, safety or health of occupants and the public by reason of combustible cladding and a failure to have an active fire monitoring system.[14]
(b) Following his appointment, the administrator arranged for installation of a fire indicator panel and occupant warning system in compliance with the January 2018 building notice at a cost of $82,570. In March 2019 lot owners were levied $2,020 per lot to cover the cost of these works. However, five lot owners refused to pay the special levy, leaving a deficit of more than $30,000.[15]
(c) In March 2019, following installation of the fire indicator panel and occupant warning system, the owner's corporation was served with two further building orders and a building notice issued by the Victorian Building Authority. The building orders and notice required the owner's corporation to remove the flammable cladding and rectify other fire safety defects.[16]
(d) In June 2019, the administrator entered into a loan agreement with Lannock Capital for a loan of up to $2,500,000 to fund the rectification works. The purpose of the loan was initially to replace the flammable cladding. The administrator determined that the only viable method of funding the required building works was with a loan because it was clear that at least a lot owner related to the Builder would not pay any special levy raised to remedy the building defects.[17]
(e) On 28 May 2020, the owner's corporation was served with further building orders and a building notice as follows:
(i) building order to remove flammable cladding;
(ii) a building order relating to fire detectors, emergency lighting and other safety matters; and
(iii) a building notice in relation to 25 matters including leaking balconies, smoke alarms and other fire and safety matters.[18]
(f) The May 2020 building orders and notice substantially replaced and expanded the earlier orders and notice.
From 2019 to 2022, the administrator arranged for rectification works set out in building orders and building notice to be carried out. The cost of removal of the combustible cladding and its replacement was $1,344,034 and met by Cladding Safety Victoria. The costs to remediate the other works was $1,914,650.18 and was funded by the loan from Lannock Capital. The other works included installing a sprinkler system as an alternate solution to the numerous fire safety defects listed in the building notice and building order and replacement of the tiles and membranes of the balconies. Replacement of the balcony membranes was required to be carried out simultaneously with replacement of the cladding because removal of the cladding would compromise the waterproof membranes of the balconies. Cladding Safety Victoria would not cover the cost of the works to the balconies.
All works were completed by March 2022. It was undoubtedly a challenging task to arrange the substantial and complicated works whilst the building was still occupied and during Covid. The speed with which the administrator was able to complete the works and arrange Cladding Safety Victoria to pay for the cladding reinstatement is a testament to the administrator's diligence.
51 The OC claims the fees that the applicant incurred in engaging various experts for the inspection and assessment of defective works and the management of rectification works. The relevant consultant reports, and their costs, are set out in the Table 2 below, which drawn from the OC's Particulars of Loss and Damage[32].
52 We note that the total is $137,682.4. This does not align with the sum of $165,163 referred to in the OC's opening submissions, but no attempt was made in those submissions to explain the difference between the two figures.
53 We are satisfied that the OC incurred consultant's fees of at least $137,682.41 and will proceed on that basis.Discussion of the claim for consultants' fees
53 The OC borrowed money from Lannock Capital to fund its rectification works. The interest paid on the Lannock Capital loan to fund rectification work is sought. The relevant evidence is discussed below, at [126]-[132].
A comment about the Builder's defences concerning specific defects
Fire resistant construction related defects (Scott Schedule #1 to #9) - $888,822
18. The most significant departure from the requirements was that the PAR[37] and cl. 3.1 of BCA Specification C1.1 required all internal non-load bearing walls separating lots were to be of non-combustible construction and be built to the underside of the floor above. However, the [Builder] constructed those walls using timber, a combustible material.[38] Further, the [Builder] did not build those walls to the underside of the wall above and instead allowed a 300 mm 'crawl space' for each floor.[39] These matters were the subject of the Building Notice issued on 28 May 2020.[40]
Lack of fire separation in external walls and between lots
(a) the allegedly defective garbage chute system, alleging damage was the result of:
(i) misuse of the garbage chute by the occupants; and
(ii) the failure by the OC to properly maintain the property and its systems.
(b) the allegations contained in the Appendix to the Building Fire Integrity ESM Report.
(c) the allegations contained in the Building Notice Response Letter Report by Red Fire Engineers dated 8 March 2018.
(d) the allegations in relation to the claim for access to unit 31, the need for the lift isolation or other incidental works.
The Builder's submission in relation to the fire sprinklers.
At the time of the issuing of the Building Permit for the Building, there was no lawful requirement for the Builder to ensure the premises were sprinkler protected.[48]
Defective work in relation to the balconies (Scott Schedule #10, 11 and 12) - $729,590
The Builder's challenge to the OC's standing to bring a claim in respect of the balcony
(a) the Plan of Subdivision defines the common property to be all the Property except the lots (and including the structure of all walls, floors and ceilings which define boundaries);
(b) the Plan of Subdivision states that boundaries shown by "thick continuous lines" are defined by buildings and that the location of those boundaries is at the interior face of walls, floors and ceilings;
(c) the Plan of Subdivision has been drawn unambiguously to provide that the walls separating each lot from its balcony forms part of common property as illustrated in the below extract ...[55]

Figure 1: Extract of Plan of Subdivision[56]
23. The [Contract] required the construction of balconies and the plans specified that those balconies were to be built with a "...minimum 100 mm step down to balcony level..." and using a 'Flexitray' or similar waterproof system.[59] None of the balconies were built according to the plans in that none of them were built with the required step down nor did they have any waterproofing system installed.[60] Further, a substantial number of the balconies were constructed either without any drainage or with adequate drainage.[61]
The balconies are generally in poor condition with the tile grout breaking down, non-complaint falls to drainage outfalls and generally insufficient or missing drain overflow provision. Elimination of water ingress into many of the Units and associated damage is a high priority with all Units requiring substantial repairs.
Generally, the balcony panels are allowing moisture ingress within the units and typically there are generally no hobs beneath the window/door elements to facilitate proper water proofing.[62]
the 'lack of hobs' allegation is more accurately described as the alleged failure of the builder to include a 100 mm step down to the balcony level in relation to all balconies throughout the property;
this does not constitute a building defect for which the Builder is responsible for as the requirements of AS4654.2 cited in the Roscon Report dated 24 November 2016, upon which the OC relies, was released in 2009 and prior to the date on which the Building Permit was issued.
Failure to properly install balcony waterproofing systems
Failure to construct balconies with adequate drainage
The defence that problems were caused by a lack of maintenance
Defective work in relation to Essential Safety Measures (Scott Schedule #13 to #15) - $86,864
103An audit of the fire detection and essential safety measures was undertaken by Mr Duler. This audit was commissioned following the GDC Building Notice of 8 January 2018.[68] Mr Duler completed his audit and provided a report on 12 April 2018. In his report, Mr Duler considered that:
The ESM defects are so numerous and serious in nature that we believe this building is unsafe and cannot be made safe without major and costly works.[69]
Water ingress into the Property's basement (Scott Schedule #16) - $29,800
Lot 9 fire escape stairs (Scott Schedule #17) - $32,764
Fire sealing of the basement carpark service/ ceiling penetrations (Scott Schedule #19) - $16,148
The fire rated internal doors to fire-isolated internal stairwell and stair balustrade spacings (Scott Schedule #18 and #20) - $14,633 + $7,040
(i) misuse of the doors by the occupants; and
(ii) the failure by the OC to properly maintain the property and its systems.
[1] [2023] VCAT 501, [5]-[9].
[2] Supplementary Tribunal Book ('STB') 93.
Owners Corporation PS628502Y
4S Constructions Pty Ltd
(2004) 11 VR 41
VCAT ordered the first respondent (4S Constructions Pty Ltd) to pay the first applicant (Owners Corporation PS628502Y) damages totalling $2,869,892.65; noted that because the first respondent is in liquidation no further step may be taken against it without leave of a court of competent jurisdiction and made directions for an administrative mention on 28 November 2025 for the applicant to advise whether it seeks leave to proceed (Orders).
(g) The RBS and the Designer and the Builder and Mr Farag on 6 July 2023 consented to orders removing the RBS and the Designer as joined parties on terms concerning costs, on the basis that the allegations made by the Builder and Mr Farag against the RBS and the Designer could be agitated in the SCV Proceeding.
(f) if the contract states the particular purpose for which the work is required, or the result which the building owner wishes the work to achieve, so as to show that the building owner relies on the builder's skill and judgement, the builder warrants that the work and any material used in carrying out the work will be reasonably fit for that purpose or will be of such a nature and quality that they might reasonably be expected to achieve that result.
(g) All works were completed by March 2022.[20]