[2019] VCAT 92
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2019-01-29
Mr P, Planning Design P
Original judgment source is linked above.
For the reasons given in our letters of 31 March, 6 April and 12 April, we advise that pursuant to the Notices of Termination served on your client on or about 10 March 2016, the Contracts are now terminated. Our clients revoke your clients license to be on the Properties, and all keys, remotes and access passes must be returned to our client immediately...
the Builder will within a reasonable time advise the Owner of the cause and the reasonable estimated length of the delay and the Builder will be entitled to a fair and reasonable extension of time for Completion of the Works;
the Builder may, within fourteen days (14) Days of becoming aware that Completion of the works will be delayed, notify the Owner in writing of the delay stating the cause and the reasonable estimated length of the delay
If the Owner does not notify the Builder in writing and reject or dispute the cause of the delay and/or the estimated length of the delay within fourteen (14) days after receipt of the Builder's notice under clause 15.1, the Completion Date under the Contract will be automatically extended by the delay period stated in the said notice...
If the Owner serves a written notice upon the Builder disputing or rejecting the estimated length of the delay stated in the Builder's notice, the Builder is still entitled to a fair and reasonable extension of time for Completion of the Works.
OWNERS ACTIONS AFTER THE TERMINATION OF THE CONTRACTS
Engineer certification of retaining wall footings
Windows rectification pursuant to RBS requirement
Installation of barbecue, sink and bulkhead in the alfresco area
(a) the builder warrants that the work will be carried out in a proper and workmanlike manner and in accordance with the plans and specifications set out in the contract;
(b) the builder warrants that all materials to be supplied by the builder for use in the work will be good and suitable for the purpose for which they are used and that, unless otherwise stated in the contract, those materials will be new;
(c) the builder warrants that the work will be carried out in accordance with, and will comply with, all laws and legal requirements including, without limiting the generality of this warranty, the Building Act 1993 and the regulations made under that Act4;
(d) the builder warrants that the work will be carried out with reasonable care and skill and will be completed by the date or within the period) specified by the contract;
- remove moisture from entrance gate intercom and ensure correct functioning, including the functioning of the connected front gate release;
- downpipes on first floor to be extended over flashing onto the metal roof with spreaders installed;
- southside air-conditioning condensation pipe to be extended into box gutter;
- adjustment of a misaligned master bedroom double doors, and any necessary touch-up repainting.
Conclusion - incomplete and defective works at 9 Page Street
18.1 Owner's entitlement to liquidated damages
If the Builder fails to bring the Works to Completion by the Completion Date, the Builder will pay or allow to the Owner by way of pre-estimated and Liquidated Damages, a sum calculated at the rate stated in Item 17 of the Appendix for the period from the Completion Date until the Works reach Completion or until the owner takes Possession, whichever is the earlier.
18.2 Liquidated damages may only be deducted from final payment
The amount of any Liquidated Damages may be deducted by the Owner from the Final Payment only and any deficiency may be recovered by the Owner as a debt due to the owner by the Builder.
Conclusion on the cost to complete works at 7 Page Street
- water and electricity $2107.61
- RBS additional inspection $ 165
- mirrors $3480
- letterbox $ 555
- internal doors $3040
- weather seal $ 55.90
- damaged benchtop $ 400
- drainage inspection $ 460
[1] Paragraph 36 (d) (iii) in the applicant's Second Further Amended Points of Claim dated 24 April 2018.
[4] RBS email to the builder 17 November 2015, Tribunal Book page 1188.
[5] witness statement of Mr Just, paragraphs 412 - 414.
[6] Regulation 12 of the Domestic Building Contracts Regulations 2007.
[7] The penal nature of sections 40(2) and (3) has been confirmed by Supreme Court in Imerva Corporation Pty Ltd v Kuna [2016] VSC 461.
[8]By order made 3 November 2016, the builder was required to file and serve a provisional sum adjustment schedule and a variation schedule.
[9] supplementary Tribunal Book pages 951 - 975.
[10] Supplementary Tribunal Book pages 498 to 513.
[11] The documents are identified in the PS spreadsheet under the heading 'Cornice'.
[12] 'Vandar Trading' invoice at page 470 3A and Page 594 of the Supplementary Tribunal Book.
[15] clause 7.2 in the contract provides the granting of the license.
[16] builder's closing written submissions, schedule paragraphs 33 - 49.
[19] Bellgrove v Eldridge [1954] HCA 36; (1954) 90 CLR 613.
[20] Tribunal Book p 251, windows marked W 23, W 26 in the drawing.
[21] invoice dated 7 September 2016 at Tribunal Book p 1654.
[22] Lord Diplock in Gilbert Ash (Northern) Ltd v Modern Engineering (Bristol) Ltd [1974] AC 689 at 717-718
[23] in closing oral submissions, the owners conceded they cannot claim both the interest burden and lost rental. It is one or the other.
[24] confirmed in paragraph 196 (b) of the owners Reply closing submissions.
[25] Alex witness statement paragraphs 123-124, Tribunal book pages 864 - 867
[27] Alex witness statement paragraph 124, at Tribunal book p 866
[28] the bank statements are said to be found at Tribunal book pages 2793 - 2820
[30] This approximate figure, $29,150, is extrapolated from the figures presented in Alex's witness statement at Tribunal book page 867
Oakmont Properties Pty Ltd
Zhang
(1954) 90 CLR 613