[1998] VSC 205
Supreme Court of Victoria
1998-12-23
Gillard J.
Original judgment source is linked above.
Novawest Contracting Pty Ltd v. Taras Nominees Pty Ltd
BUILDING CONTRACT - Standard form general conditions AS 2124-1992 - Interim Certificate - Payable without deduction - No entitlement to set-off claim for damages for delay - Parties exclude the right.
(i) the plaintiff contractor was entitled to payment of the amount certified by the superintendent without any deductions;
(ii) that even though the plaintiff is in breach of a term of contract which has caused damage to the defendant, the defendant is not entitled to exercise its common law right to raise the claim for damages as a set-off to the plaintiff's claim.
"Where a defendant has a claim against a plaintiff for the recovery of a debt or damages, the claim may be relied on as a defence to the whole or part of a claim made by the plaintiff for the recovery of a debt or damages and may be included in the defence and set-off against the plaintiff's claim, whether or not the defendant also counterclaims for that debt or damages."
"So when one is concerned with the building contract one starts with the presumption that each party is to be entitled to all those remedies for its breach as would arise by operation of law, including the remedy of setting up a breach of warranty in diminution or extinction of the price of material supplied or work executed under the contract. To rebut that presumption one must be able to find in the contract clear unequivocal words in which the parties have expressed their agreement that this remedy shall not be available in respect of breaches of that particular contract."
(Emphasis added)
"When parties enter into a detailed building contract there are, however, no overriding rules or principles covering their contractual relationship beyond those which generally apply to the construction of contracts. The particular wording of a particular contract may have to be considered in relation to particular facts. A decision in some one particular case as to the meaning and application of words in a contract will not have governing force as to the meaning of different words in a different contract. Nor, if a contract provides for the issuing of interim certificates, should it be supposed that debts of a special class will come into existence, i.e. debts in relation to which there cannot under any circumstances be any defence or set-off. Provisions governing such interim certificates will probably be found in the contract."
"A court may admit evidence of surrounding circumstances in the form of 'mutually known facts' to identify the meaning of a descriptive term and it may admit evidence of the 'genesis' and objectively the 'aim' of a transaction to show that the attribution of a strict legal meaning would 'make the transaction futile'".
"What a man intends is one thing - the expression of his intention is another".- see Simpson v. Foxon (1907) P. 54 at 57.
"Consequently when the issue is which of two or more possible meanings is to be given to a contractual provision, we look, not to the actual intentions, aspirations or expectations of the parties before or at the time of the contract, except insofar as they are expressed in the contract, but to the objective framework of facts within which the contract came into existence and to the parties' presumed intention in this setting. We do not take into account the actual intentions of the parties and for the very good reason that an investigation of those matters would not only be time consuming but it would also be unrewarding as it would tend to give too much weight to those factors at the expense of the actual language of the written contract."
(My emphasis)
" ... if detailed semantic and syntactical analysis of words in a commercial contract is going to lead to a conclusion that flouts business common sense, it must be made to yield to business common sense."
"My Lords, I cannot help thinking that building contractors and sub-contractors and architects advising building owners know far more about the building trade than I or, indeed any judges can hope to do. I am not prepared to approach any contract on the pre-supposition that the parties must have meant to exclude or
curtail the right of set-off. I am content to consider the
language of each contract and see whether it has done so."
(Emphasis added)
"Had the parties been asked at the time of the agreement whether it was necessary to put in a clause that the advances must be repaid, if it turned out that the commission in question was never earned, in my view both parties would have said: 'Yes, of course; as they are advances, they will have to be returned. It is quite unnecessary to put so obvious a matter into the agreement.'"
"It is of the utmost importance in commercial transactions that, if any particular event occurs which may affect the party's respective rights under a commercial contract, they should know where they stand. The court should so far as possible desist from placing obstacles in the way of either party ascertaining his legal position ... because it may be commercially desirable for action to be taken without delay ... it is for this reason, of course, that the English courts have time and time again asserted the need for certainty in commercial transactions - for the simple reason that parties to such transactions are entitled to know where they stand, and to act accordingly."
"However that may be, what is in question in all these cases is the interpretation of a particular contract. I deprecate in general the attempt to enunciate decisions on the construction of agreements as if they embodied rules of law. To some extent decisions on one contract may help by way of analogy and illustration in the decision of another contract. But however similar the contracts may appear, the decision as to each must depend on the consideration of the language of the particular contract, read in the light of the material circumstances of the parties in view of which the contract is made."
"This philosophy leads to the presumption that the parties to every building contract or sub-contract must have intended to exclude the general principle of law relating to the right of set-off save in respect of liquidated or ascertained sums which are established or admitted as being due. At any rate every such contract which has been recently considered in the Court of Appeal , including even the present, has been so construed."
"The general conditions of contract AS2124-1992 shall form part of the contract."
(i) On the last day of each month, the plaintiff shall deliver to the superintendent Fisher a claim for payment with supporting evidence.
(ii) Within 14 days of receipt of the claim, the superintendent shall issue to the parties a payment certificate which shall set out the superintendent's calculation as to amount, and if the amount certified is different to the claim, the reasons for the difference.
(iii) The superintendent shall allow in the certificate, inter alia, amounts due by the plaintiff to the defendant "arising out of or in
connection with the contract including but not limited to any
amount due or to be credited under any provision of the contract".
It is pertinent to observe that the provision gives the superintendent a very wide power to make adjustments.
(iv) 'Subject to the provisions of the contract' within 28 days of the
receipt by the superintendent of the claim or within 14 days of
the issue of the payment certificate, whichever is earlier, the
defendant 'shall pay to the plaintiff ... an amount not less than
the amount shown in the certificate as due to the contractor'.
(a) "A payment made pursuant to this clause shall not prejudice the right of either party to dispute under clause 47 whether the amount so paid is the amount properly due and payable" and goes on to provide that
after determination there will be an accounting between the parties.
It is appropriate at this stage to refer to clause 47 which is a dispute resolution clause. The important point to note is that notwithstanding the existence of any dispute the parties shall continue to perform the contract. More importantly the parties are obliged to continue to comply with clause 42.1.
(b) "Payment of money shall not be evidence of the value of work or an admission of liability or evidence that work has been executed satisfactorily but shall be a payment on account only, except as provided by clause 42.8."
"The principal may deduct from monies due to the contractor any money due from the contractor to the principal otherwise than under the contract and if those monies are insufficient the principal
may, subject to clause 5.5, have recourse to retention monies and,
if they are insufficient, then to security under the contract."
(Emphasis added)
"If the Contractor fails to reach Practical Completion by the Date for Practical Completion, the Contractor shall be indebted to the Principal for liquidated damages at the rate stated in the Annexure for every day after the Date for Practical Completion to and including the Date of Practical Completion or the date that the Contract is Terminated under Clause 44, whichever first occurs. If after the contractor has paid or the principal has deducted liquidated damages, the time for Practical Completion is extended, the Principal shall forthwith pay to the Contractor any liquidated damages paid or deducted in respect of the period up to and including the new Date for Practical Completion."
"It was for the architect to put that right if need be in a monthly certificate. I think therefore that the Master was right to give Sunley judgment for the full sum claimed ... "
"The power to order summary or final judgment is one that should be exercised with great care and should never be exercised unless it is clear that there is no real question to be tried."
(i) That the appeal brought by the defendant by notice dated 3 October 1998 against the order of Master Wheeler made 29 September 1998 is dismissed.
(ii) That the defendant pay the plaintiff's costs of the appeal.
Novawest Contracting Pty Ltd
Taras Nominees Pty Ltd [1998] VSC 205