[2008] VCAT 309
Victorian Civil and Administrative Tribunal
2008-02-19
Original judgment source is linked above.
I understand all of these works have been carried out apart from the new pergola, which is part-completed.
"Within three months of the date of this permit, [the Applicant must obtain] either:
A copy of the certificate of environmental audit and/or statement, and the complete audit report and audit area plan must be submitted to the Responsible Authority".
Can the applicant rely on any Clause 62.02 exemptions?
Is there a reasonable nexus between Condition 3 and the relevant works?
[1] The requirement for a permit condition to be reasonable is reinforced in Section 2.3 ("Validity of conditions") of Part 2 ("Preparing and organising conditions") of the "Writing Planning Permits" booklet published by the Dept of Sustainability and Environment (2nd Edition, February 2007).
Norman & Tinney
Yarra CC