Condition N7 Noise survey requirements and condition N9 Operational Noise Management Plan
2 Noise surveys must be undertaken in accordance with a survey method approved in writing by the Director, as may be amended from time to time with written approval of the Director.
2 Noise surveys must be undertaken in accordance with the methodology stated in the Operational Noise Management Plan approved under Condition N9.
3 Without limitation, the Plan must include: > > 3.1 details of mitigation measures, including WTG sector management, to ensure compliance with these conditions; > > 3.2 a detailed community engagement plan including procedure for notifications of potential nuisance due to any equipment failure or fault and to receive and respond to complaints regarding noise disturbance.
3.1 details of mitigation measures, including WTG sector management, to ensure compliance with these conditions;
3.2 a detailed community engagement plan including procedure for notifications of potential nuisance due to any equipment failure or fault and to receive and respond to complaints regarding noise disturbance; and
3.3 details of background and operational noise monitoring procedures that will be implemented for noise surveys.
No Turbine Action Group Inc
Central Highlands Council [2025] TASCAT 162
Hobart City Council v Rich Tapestry Pty Ltd (ACN 667 999 055) [2024] TASSC 54;
Wilderness Society (Tasmania) Inc v Wild Drake Pty Ltd [2021] TASFC 12;
Raff Angus Pty Ltd v Resource Management and Planning Appeal [2018] TASSC 60;
M & J Purton v Waratah-Wynyard Council and D & V Turner [2022] TASCAT 92;
Elcham and Anor v Commissioner of Police and Ors [2001] NSWSC 614;
Hall v Hobart City Council [2024] TASCAT 155;
A & N McCullagh v Glamorgan Spring Bay Council & Ors [2019] TASRMPAT 30;
Mount Wellington Cableway Company Pty Ltd v Hobart City Council and Others [2022] TASCAT 128;
Tucker v State of Victoria [No 2] [2021] VSCA 182;
Minister for Immigration and Citizenship v Li [2013] HCA 18;
Allen Commercial Constructions Pty Ltd v North Sydney Municipal Council [1970] HCA 42;
Planning Commission (WA) v Temwood Holdings Pty Ltd [2004] HCA 63;
Ryan v Circular Head Council and Smith v Circular Head Council and Birdlife Tasmania v Circular Head Council and ACEN Robbins Island Pty Ltd v Circular Head Council and Bob Brown Foundation v Circular Head Council and Circular Head Coastal Awareness Network Inc v Circular Head Council (No.4) [2023] TASCAT 217;
Sunland Group Limited v Gold Coast City Council [2021] HCA 35;
Allandale Blue Metal Pty Ltd v Roads and Maritime Services [2013] NSWCA 103;
Olsson v Goulburn Mulwaree Council & the Minister Administering The Crown Land Act 1989, Olsson v The Minister Administering The Crown Land Act 1989 [2010] NSWLEC 169;
Sultan Holdings Pty Ltd v John Fuglsang Developments Pty Ltd [2017] TASFC 14;
Saltwater Lagoon Pty Ltd v Glamorgan Spring Bay Council [2022] TASFC 5;
AG and BJ Riley v Kentish Council [2024] TASCAT 105;
Meander Valley Council v Resource Management and Planning Appeal Tribunal [2013] TASSC 42
112 As a provision of a planning scheme, it should be interpreted in accordance with the ordinary rules of statutory interpretation: AAD Nominees Pty Ltd v Resource Management and Planning Appeal Tribunal [2011] TASFC 5 at [10]; Raff Angus Pty Ltd v Resource Management and Planning Appeal Tribunal [2018] TASSC 60, 28 Tas R 224 at [20].
113 That means starting with the ordinary and grammatical meaning of the text, with assistance to be gained from context; context includes surrounding provisions and the instrument as a whole, as well as purpose. The language actually employed is the surest guide: Alcan (NT) Alumina Pty Ltd v Commissioner of Territory Revenue (NT) [2009] HCA 41[2009] HCA 41; , 239 CLR 27 at [4] per French CJ, at [47] per Hayne, Heydon, Crennan and Kiefel JJ. Words that have an apparently clear, ordinary or grammatical meaning may be given a different legal meaning after the process of construction is complete: R v A2 [2019] HCA 35, 373 ALR 214 at [32].