(2) This section does not apply to the carrying out of an activity specified in Part B of the following table:
(a) on land within the area of operations of the Sydney Water Board under the Sydney Water Act 1994 , or
(b) on land within the area of operations of the Hunter Water Board under the Hunter Water Act 1991 , or
(3) This section does not apply to the carrying out of an activity specified in item 1, 2, 3, 4, or 6 of Part B of the following Table on land within the area of operations of a water supply authority constituted under Water Management Act 2000.
Note. A person who fails to obtain an approval or who carries out an activity otherwise than in accordance an approval is guilty of an offence - see secs 626 and 627.
Table
Part B Water supply, sewerage and drainage work
1. Carry out water supply work
2. Draw water from a council water supply or a standpipe or sell water so drawn
3. Install, alter, disconnect or remove a meter connected to a service pipe
4. Carry out sewerage work
5. Carry out stormwater drainage work
6. Connect a private drain or sewer with a public drain or sewer under the control of a council or with a drain or sewer which connects with such a public drain or sewer
Part C Management of waste
1. For fee or reward, transport waste over or under a public place
2. Place waste in a public place
3. Place a waste storage container in a public place
4. Dispose of waste into a sewer of the council
5. Install, construct or alter a waste treatment device or a human waste storage facility or a drain connected to any such device or facility
6. Operate a system of sewage management (within the meaning of s 68A)
86. This matter was the subject of a joint conference between Mr Ellison, Dr Martens and Dr Paterson dealing with the sewerage infrastructure and S.T.P. They generally agree that the amended plans provided are satisfactory. Also that the draft plan of management is adequate.
87. The draft plan of management evolved during the hearing and contains detailed construction, procedural and maintenance matters.
88. Considering the nature of the detail, the respective parties responsibilities and the requirement for further refinement of this plan of management, based on the recommendations of the Court-appointed expert Dr Martens, I consider the final format should be provided for certification by either Council or Private Certifier.