[2025] QCAT 279
General information, not legal advice.
Queensland Civil and Administrative Tribunal
2025-07-15
Mr J
Original judgment source is linked above.
PROFESSIONS AND TRADES - BUILDERS - STATUTORY POWER TO REQUIRE RECTIFICATION OF DEFECTIVE OR INCOMPLETE BUILDING WORK - where the Queensland Building and Construction Commission determined to give a direction to rectify in respect of a complaint about building work - correct interpretation of time frame given to builder to comply - whether the builder was given reasonable opportunity to comply with direction to rectify - the manner in which the builder ought to have applied for an extension of time to comply with direction to rectify
Acts Interpretation Act 1954 (Qld), s 4, s 38
Mr N Congram of Counsel with him Alicia Collett and Alena Taylor in house lawyers
23 December 2020 Larissa and John Tyas as homeowners enter into a Master Builders Queensland Residential Renovation Contract.
12 October 2021 work ceased but not complete.
16 December 2021 homeowners provided with Form 21 final inspection certificate.
24 December 2021 homeowners make a final payment.
Prior history of complaints, compliance, and reconsideration in the period 1 November 2021 culminating in the issue of the direction to rectify of 16 January 2023 and issues around compliance the subject of this application.
Friday 10 February 2023 Mr Rae's supervisor attended site to measure up for a custom-made sill tray flashing. Some tiles were removed.
Monday 13 February 2023 Mr and Mrs Tyas advise 48 hours' notice of access would be required. The same day Mr Rae requested access for Wednesday 15 February, Thursday 16 February, Friday 17 February, and Monday 20 February 2023. The same day Mr and Mrs Tyas confirmed access on those four dates. In a later email the same day Mr and Mrs Tyas required 48 hours' notice of arrival and leave times to correlate with their availability.
Tuesday 14 February 2023 Mr and Mrs Tyas stated in an email that failure to provide times may affect access. The same day Mr Rae urgently emailed Mr O'Shannessy "seeking QBCC backing to complete this rectification" and asking to discuss Mr and Mrs Tyas' imposition of 48 hours access notice including specific timing for access. Mr Rae expressed concern about having enough time to complete rectification with such access notice. The same day Mr Rae emailed Mr and Mrs Tyas varying contractor attendance on Friday morning 17 February and requiring access on Saturday 18 February. He also indicated his intention to install a strip drain as part of a performance solution.
On 15 February 2023 Mr Rae ordered and paid for additional tiles to be utilised in the rectification work.
On 16 February 2023 Mr Rae sought access for his supervisor to do a final check measure for a steel insert tray (part of the performance solution). Access was granted and the same day the measurements were furnished to the fabricator.
No person for or on behalf of Nailed It attended site on either Friday 17 February or Saturday 18 February 2023. On Saturday 18 February 2023 Mr and Mrs Tyas enquired, in view of non-attendance on Friday and Saturday, as to whether access would still be required on Monday 20 February.
Monday 20 February 2023 at 8.02 am Mr and Mrs Tyas emailed Mr Rae and Mr O'Shannessy stating that they had been waiting for the arrival of Nailed It, but no one had come. At that point they had to leave. If access was required that day Mr Rae would have to contact them. The same day at 8.17am Mr Rae emailed Mr and Mrs Tyas and Mr O'Shannessy apologising for the delay in responding and indicating that the necessary flashings would be ready that morning. When confirmation was received from the supplier, he would have his supervisor Brendon call to organise access. The same day at 1.20pm Mr and Mrs Tyas emailed Mr O'Shannessy stating minimal work completed and requesting advice as to next steps to be taken. Mr O'Shannessy answered at 1.45pm indicating that he would be sending an email the next day requesting a response to assess if works had or had not been successfully rectified.
On Tuesday 21 February 2023 at 7.02 am Mr Rae emailed Mr and Mrs Tyas and Mr O'Shannessy stating he advised yesterday (20 February) that materials were not ready. He had just collected them, (the tax invoice from Rollsec the fabricator of the stainless welded tray is dated 21 February 2023 and delivery date recited thereon is also 21 February 2023) and Brendon and his team would be on site at 7.30am. Mr and Mrs Tyas replied at 7.12 am stating they were unable to provide access that morning at such late notice. They required 48 hours' notice. In addition, they said yesterday (20 February) was the due date for completion of works as stated in the direction to rectify and for Mr Rae to feel free to discuss with the Commission. Mr Rae replied at 7.20 am to both Mr and Mrs Tyas and Mr O'Shannessy requesting access and stating 48 hours' notice was not required; that works had commenced and that "we (presumably all parties) need to provide an adequate time for access to do the work"; that stopping performance of work was contrary to Commission directions. He also stated he had discussed matters with the Commission. Mr and Mrs Tyas responded at 7.24 am to both Mr Rae and Mr O'Shannessy that it was not possible to wait for Mr Rae; that Mr Rae was not respecting the due date for works and his requirements for giving them fair notice for access. A further follow up email was sent at 7.27 am stating that they Mr and Mrs Tyas had also had discussions with the Commission and were awaiting instructions about further access.
On Tuesday 21 February 2023 at 3.32 pm Mr O'Shannessy emailed both Mr and Mrs Tyas and Mr Rae indicating that where rectification works were incomplete or disputed the Commission would undertake a reinspection and pointing out that where the direction to rectify had expired the Commission no longer had legislative powers to enforce access to rectify defective building work. Any further access to rectify defective work was at the discretion of the homeowners. Any incomplete defective work identified would be referred to the Home Warranty Scheme for assessment of a possible claim.
In an email sent at 7.31 pm on 21 February 2023 to Mr O'Shannessy Mr and Mrs Tyas indicated that due to past experiences with Mr Rae they did not wish to provide Nailed It with any further site access. They wished to proceed with the Commission's process.
Nailed It Creations Pty Ltd
Queensland Building and Construction Commission [2025] QCAT 279