[2025] VCAT 809
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2025-09-15
Original judgment source is linked above.
Construct a dwelling if there is at least one dwelling existing on the lot
Remove, destroy or lop any vegetation specified in a schedule to this overlay
(a) Constructed
(b) Surfaced with a durable all-weather seal.
(c) Drained to the nominated legal point of discharge.
(a) All drainage works associated with the development including any drainage works required outside the land.
(b) The nominated legal point of discharge.
(c) The conveyance of stormwater runoff by means of underground drains to the nominated legal point of discharge.
(d) The mechanisms used to prevent overland flows from having a detrimental effect on the land, the environment or adjoining properties;
(e) The mechanisms used to limit the Permissible Site Discharge (PSD) to the lesser of:
- the equivalent of a 35% impervious site coverage; or
- the pre-developed discharge rate.
(f) Stormwater detention storage that limits the maximum discharge rate to the PSD.
Tree Protection and Management Plan implemented
(a) The project arborist must advise the responsible authority in writing that the Tree Protection measures have been installed to their satisfaction.
(b) The TPP must be printed on A2 weatherproof paper.
(c) The TPP must be highly visible on the site and be displayed at the site entry.
(a) For each tree shown to be retained on the land or on neighbouring land, a Tree Protection Zone (TPZ) and Structural Root Zone (SRZ) calculated in accordance with the Australian Standard for Protection of Trees on Development Sites (AS4970-2025).
(b) A garden bed around the perimeter of the front carparking space for dwelling 1 with vehicle stops shown to prevent ingress into garden areas.
(c) Landscaping treatments within the front setback in a manner which complements the prevailing character of the surrounding area and includes additional plantings of screening shrubs.
(d) All canopy trees must be located to optimise their long-term growth and development. In this regard be shown in garden beds at least 1.5m wide (to provide at least a 1m radial area around the tree's stem which is mulched and free of lawn).
(e) All canopy trees must be located to optimise their long-term growth and development. In this regard, trees shall:
- be shown least 3.5m from the wall of any dwelling or building
- be shown at least 1m from any fence, pavement or retaining wall
- be shown beyond the canopy of any existing canopy tree
- be shown in a mulched area or garden bed at least 1.5m wide (to provide at least a 0.75m radial area around the tree's stem which is mulched and free of lawn).
(f) Substitution of Everlasting Daisy Helichrysum scorpioides with a more robust groundcover species.
(g) Rainwater tank consistent with Council engineering requirements. All rainwater tanks are to be shown as installed on a concrete slab.
(h) An amended planting schedule of all proposed trees, shrubs and ground covers, including botanical names, common names, pot sizes, sizes at maturity, and quantities of each plant. All species selected must be to the satisfaction of the responsible authority.
Completion and maintenance of landscaping works
Residential Reticulated Gas Service Connection
(a) the development is not started within two years of the date of this permit, or
(b) the development is not completed within four years of the date of this permit.
The responsible authority may extend the periods referred to above if a request is made in writing:
within 12 months afterwards if the development lawfully started before the permit expired.
[1] The submissions and evidence of the parties, any supporting exhibits given at the hearing and the statements of grounds filed have all been considered in the determination of the proceeding. In accordance with the practice of the Tribunal, not all of this material will be cited or referred to in these reasons.
[3] [2025] VCAT 502, as confirmed in Oakleigh Six Pty Ltd v Monash CC [2025] VCAT 648.
[4] Council indicated that the removal of these trees was unauthorised, and that it had taken enforcement action in response but that this was a separate matter.
[5] He opined that it was likely that it has at-grade construction or a shallow slab.
Morton
Maroondah CC [2025] VCAT 809