For the reasons set out in this Report, the Panel concludes that the Amendment:
The issue is whether the financials of the exhibited DCP (project costs, demand unit calculation and apportionment) are sufficiently justified.
The exhibited DCP is proposed to increase the project costs and alters the demand unit calculation, compared with the existing DCP. Council's Day 1 DCP includes further cost increases. There is no change proposed to the apportionment of costs within the DCP.
Table 2 Costs comparison for different version of the DCP (June 2025 dollars)
The infrastructure project in this DCP has been costed to a sufficient level of detail; however, the Council may amend or modify some aspects of the project, so long as they are still generally in accordance with any direction regarding the scope outlined in this DCP.
Where the Council or another agency seeks to change the scope of a DCP infrastructure item to meet changing standards imposed by adopted policy or a public regulatory agency, such changes of standards and the resulting cost changes should normally be made through a change to the DCP at the time of a regular review of the DCP.
Where, after the DCP has been approved, a Council or other agency proposes changes to the scope of a DCP infrastructure item for reasons other than changes in standards imposed by policy or regulation the net cost increases resulting from the change should normally be met by the agency requesting the change.
Ms Fisher gave the following evidence on behalf of Council:
I note that Council could have pursued 100% apportionment however Council's acceptance of 30% effectively deals with any external benefit that would be associated with the proposed DCP project and therefore I consider this approach reasonable in the circumstances.
Mr Smith and Mr Dietzsch made the following submissions:
Mr Smith submitted that he was concerned about the change in the demand unit calculation.
Council has accepted that the cost increases included in the exhibited DCP and Day 1 DCP are 'not insignificant'. These costs increases are attributed to several factors, including:
The costs associated with financing and plan preparation costs are typically included in a DCP. The Panel accepts this approach given it is consistent with the Development Contribution Guidelines and was supported by Ms Fisher in her evidence_._
The costs associated with water mains and rising sewer mains are not typically included in DCPs. The Panel accepts the evidence of Ms Fisher that these items should not be included. This is particularly the case given these works were not included in the exhibited DCP and already the 'not insignificant' cost increase flagged by Council. While the Panel understands Council's dilemma in terms of recovering funds, it is not reasonable to add additional infrastructure that would not normally be expected to be covered in a DCP. Council needs to identify an alternative funding mechanism.
The Panel accepts Ms Fisher's evidence that the project costs should be calculated using the best available information, being the estimates prepared by Harlock in July 2025. However, Harlock's July 2025 estimates will need to be adjusted to reflect the DCP project scope changes recommended by the Panel.
Council should consider if further exhibition of the Amendment is needed on the basis noting that:
The Council has proposed to continue with a 30 percent contribution towards the project costs. This approach is consistent with the existing DCP and effectively deals with any external benefit that would be associated with the DCP project.
This is a reasonable approach in the circumstances and removes the need for a detailed (and costly) analysis of the split between the beneficiaries of the DCP project.
The use of lot area to calculate the demand unit is logical. This approach more accurately reflects the development capacity of land (and associated demand on the planned infrastructure), is consistent with the Development Contribution Guidelines and is a more equitable that an approach relying on the length of a lot's frontage.
The exhibited DCP expanded the extent of road infrastructure to be upgraded (as shown in Figure 1) that added 12 additional properties as shown in Figure 6 (New DCP land).
Figure 6 Residential properties proposed to be included in the New DCP area

Council's Day 1 Amendment reduced the scope of road works and properties proposed to be included in the DCP area (as described in section 1.3 of this Report). The extent of road works presented in Council's Day 1 Amendment are shown in Appendix B.
Ms Fisher gave the following evidence on behalf of Council:
I am concerned that the impact of the Day 1 DCP changes will result in an inconsistent road network that conflicts with the objective of the Exhibited DCP as it does not deliver a continuous local road network that is of shared benefit to the DCP area.
Council's Asset Plan requires Council to prioritise maintaining or renewing existing assets over new ones - this Development Plan [on the former industrial land] was privately led and will only benefit those properties clearly within Cresswell (sic) Street and should therefore be fully funded by those properties without subsidisation from adjoining existing properties already having the benefit from the other infrastructure proposed.
Submitters from properties in the New DCP land raised similar concerns to Mr Smith and Mr Dietzsch:
Most submissions were received from owners of established residential properties that are proposed to be included in the DCP area. The Council acknowledged that these properties (all zoned GRZ1) are already serviced by electricity, drainage, sewer and road access (though in some instances an unmade road).
The Panel agrees that these properties will receive some level of shared benefit, however the level of benefit will be generally equivalent to the benefit of other residential properties in the local area (i.e. other properties which are not liable for contributions under the exhibited DCP). The Council has acknowledged these broader local benefits by accepting that it will contribute 30 percent of the costs.
The additional properties would contribute disproportionately to the cost of the DCP project for the following reasons:
The Panel agrees with Ms Fisher that if Council supported the removal of the Cooma and Disney Street properties from the DCP, all 11 of the established residential properties in the GRZ1 should be removed from the DCP for consistency.
The exhibited Amendment included the introduction of a native vegetation exemption through a modification to the schedule at Clause 52.17 (Native vegetation). The exemption was proposed to facilitate the removal of native vegetation required for the DCP project.
The Panel accepts that Council introduced the native vegetation exemption as part of the Amendment with a view to streamlining the process for the delivery of the DCP project. The Panel accepts Council's revised position and notes there are some benefits in terms of enabling the consideration of all vegetation removal requirements (for example, for native and non-native vegetation).
This approach is more likely to enable further avoidance of impacts and secure native vegetation offsets through the permit application process.
The Panel canvassed the implications of delays in the permit process with the overall DCP project delivery timelines at the Hearing (completion by 2028). Council did not have a formal position on project delivery, but was open to the Panel considering an extension. To ensure the DCP does not need to be amended another time, it is recommended the project delivery time be extended to 2030 (noting this will not affect the project finance costs which are capped at a 5 year period).
Late submission from Caitlin and David Phillips (referred to the Panel)
Email to late submitter providing opportunity to complete a request to be heard form for the Hearing
Expert evidence statement of Jo Fisher of Mesh Planning Pty Ltd
Additional material referred to in Council's submissions:
Drainage comparison plans (as presented at the Hearing)
Appendix B Council's preferred extent of road works in Day 1 Amendment
Figure 7 Council's preferred extent of works in Cooma Street
Figure 8 Council's preferred extent of works in Creswell Street (West)

Figure 9 Council's preferred extent of infrastructure Glossop Street

[3] Revised date introduced through Amendment C305morn which came into effect on 18 July 2024
[4] Council's Part A submission, page 25
[5] At that time the late submission had not been received, this was referred to the Panel in July 2025.
[6] This is the revised cost estimate of the project as exhibited (e.g. including the Cooma Street infrastructure)
[7] This is revised cost estimate of the project based on Council's preferred position (e.g. not including a portion of Cooma Street infrastructure).
[8] Arden Precinct Development Contributions Plan (Amended December 2023)
[9] Refer to discussion in section 1.2.4 of this Report
[12] The Panel clarified that this issue was outside the remit of the Hearing.