DOMESTIC BUILDING DISPUTE - Liability of guarantors under contract of guarantee. Whether surety is discharged from its obligations under a guarantee when there has been an alteration to the primary contract which the surety guaranteed. Anker Pty Ltd v National Westminster Finance (Australia) Ltd [1987] HCA 15; (1987) 162 CLR 549; whether alternation or variation to primary contract caused by failure to re-issue architectural drawings or shop drawings; whether primary contract required shop drawings to be approved by architect or engineer.
7, 8 and 9 November 2012, 12 and 13 August 2013, 9 September 2013 and 21 November 2013.
Monty Manufacturing Pty Ltd v Platt (Domestic Building) [2013] VCAT 2137
According to Monty, those representations were false and untrue and therefore constitute false and misleading conduct in contravention of s 9 of the Fair Trading Act 1999 entitling it to relief under that Act.[3]
Note that due to steel shop drawings being unacceptable and unable to be satisfactorily revised within the available timeframe, the steel fabricator is now fabricating all steel work to measured site dimensions and in accordance with Connell Wagner's [the engineer] and NMBW's [the Architect] comments on the latest round of shop drawings received. Fabricator/ABMW [the Builder] to ensure that all details are in accordance with structural and architectural requirements as documented.[16] [square brackets added]
2.1 agree to be jointly and severally liable with the Contractor to the Owner for the performance of all the obligations of the Contractor.
2.2 jointly and severally guarantee to the Owner the payment of all money payable by the Contractor and the performance of the Contractor's obligations.
Then it has been said that any departure by the creditor from the suretyship contract "which is not obviously and without inquiry quite unsubstantial, will discharge the surety from liability, whether it injures him or not, for it constitutes an alteration in the surety's obligations" (Halsbury's Laws of England, 4th ed., vol. 20 par.259). The final clause in the passage quoted from Halsbury indicates that this proposition is founded not so much on cases dealing with a breach of a term in the suretyship contract, as on cases in which conduct on the part of the creditor materially altered the surety's obligations. Such an alteration takes place when the creditor agrees to a variation of the principal contract or to an extension of time within which the debtor may comply with that contract. The creditor's agreement with the debtor thereby alters the nature of the surety's obligations without the surety's consent.[17]
The rule does not permit the courts to enquire as to the effect of the operation. The consequence is that, to hold the surety to his bargain, the creditor must show that the nature of the alteration can be beneficial to the surety only or that by its nature it cannot in any circumstances increase the surety's risk e.g., a reduction in the debtor's debt or in the interest payable by the surety. The mere possibility of detriment is enough to bring about the discharge of the surety.[18]
In relation to a building contract, a change in the work or design from the original specifications, a variation in the terms of a trust of retention monies, the postponement of the date upon which the contractor was to take possession of the site in order to commence the building work, or payments made to the building contractor before the contractual date for payment stipulated in the principal contract all constitutes variations that will discharge guarantors of the builder's obligations.[19] [footnotes omitted]
First ground: Failure to address grid line discrepancy
(a) there was a gap in between the north-eastern boundary and the proposed location of the building; and
(b) the building significantly protruded into the property on the western title boundary. Effectively the building was not square to the Kerr street site and was askew to the south west.
(a) The set out on the Kerr Street frontage is parallel to the boundary as the lines of the boundary and grid do not diverge or converge. We note that the drawings do not specifically state the grid are parallel to the Kerr Street boundary or at 90° to that boundary but this might be reasonably assumed from the drawing unless otherwise noted. Simply put, lines appearing to be at right angles (90°) are assumed to be at right angles unless otherwise noted. If this was not the case typical rooms in houses, apartments and commercial buildings would have corners marked as 90°. If there is any confusion the architect can be asked during tender or construction. This requirement is normally mandatory under the specification.
(b) The set out on the western boundary has a grid numbered 4 which is not running true north-south. This is indicated by the drawing showing the grid and the boundary (10.82 m at 0° 0') not being parallel but the gridlines moving away from the boundary as the grid line goes south.
(c) The surveyor's initial set out (setout 1 drawing 092004) is based on a main grid access which is running true north-south (0° or 180°) as marked on gridlines 2 of setout 1. This set out is incorrect because the grids on the architectural drawing are shown as being slightly less than true north-south because they are at right angles to the northern boundary (Kerr Street) which is slightly less than east-west. The grid is based on the northern boundary rotated 0° 18' to the east of true north-south line. The surveyor is therefore incorrect in stating that the grid axis was north-south. The drawing A 02 clearly shows the gridlines moving away from that section of the west boundary running north-south in the north-east corner of the site.
A7.1 The architect may issue an instruction at any time during the performance of this contract provided that the instruction is given in writing.
B2.1 Unless otherwise shown in schedule 3, the order of precedence of the contract documents is as follows:
J1.1 The architect may give to the contractor a written instruction for a variation at any time before the date of practical completion
General: if required, submit dimensional drawings showing details of the fabrication and installation of services and equipment, including relationship to building structure and other services, cable type and size and marking details.
Diagrammatic layouts: Coordinate work shown diagrammatically in contract documents, and submit dimensioned set-out drawings.
General: Submit shop drawings showing the following information:
Before submitting these documents to the Superintendent, ensure that the work covered by these documents complies with the requirements of the Specification and Drawings including all details of connections, welds and paint finishes.
Do not manufacture, stockpile, supply or assemble steelwork affected by these documents until the documents are received back from the Principal, endorsed as examined by the Principal and Structural Engineer.
Endorsement of these documents by the Managing Contractor, Architect and Structural Engineer will indicate if the Contractor's interpretation of the contract requirements is generally satisfactory. Such examinations do not relieve the Contractor of his contractual obligations nor of his responsibility of ensuring that the works are complete, accurate and correct.
Fabrication: Do not commence fabrication until permission to use the relevant shop drawings has been obtained.
Submit the name of the proposed Shop Drawing Company to the Managing Contractor for approval prior to work commencing.
Submit to the Managing Contractor, for examination, comprehensive shop and construction drawings with notes and/or specification, called "the documents", which are necessary for the proper carrying out of the works. Ensure the documents are in accordance with AS1100. Prepare and submit the documents in a logical order to allow a full examination to be carried out.
The drawings shall show the relevant details of each assembly, component and connection, together with information relative to fabrication, surface treatment and erection. (emphasis added)
1. The action of endorsing; concr. a signature, memorandum, or remark endorsed on the document. 2. fig. Confirmation, ratification, approving testimony.[23]
[1] Mr Robins SC appeared on behalf of the First and Second Respondents on 7, 8 and 9 November 2012 and behalf of the First Respondent only on 12 August 2013.
The First Respondent appeared in person on 13 August and 9 September 2013.
Mr Foster, solicitor, appeared on behalf of the First Respondent only on 21 November 2013.
[2] Mr Robins SC appeared on behalf of the Second Respondent on 7, 8 and 9 November 2012 only.
[3] As the Fair Trading Act 1999 existed at the time.
[4] In paragraphs 5 and 14 of the First and Second Respondent's Fifth Further Amended Points of Defence and Counterclaim dated 19 November 2012 and paragraphs 5 and 14 of the First Respondent's Sixth Further Amended Points of Defence dated 22 November 2013, the First and Second Respondents admit the Guarantee and the quantum of the Applicant's claim as set out in Paragraph B of Applicant's Amended Further and Better Particulars of Loss and Damages dated 24 October 2012.
[7] Minutes: Site meeting no 3 dated 1 November 2007.
[8] Minutes: Site meeting no 4 dated 13 November 2007.
[9] Minutes: Site meeting no 5 dated 20 November 2007.
[10] Minutes: Site meeting no 14 dated 26 February 2008.
[11] _Minutes: Site meeting no 1_5 dated 5 March 2008.
[12] Minutes: Site meeting no 16 dated 11 March 2008.
[13] Minutes: Site meeting no 17 dated 8 April 2008.
[14] Minutes: Site meeting no 18 dated 23 April 2008.
[15] Minutes: Site meeting no 19 dated 7 May 2008.
[16] Minutes: Site meeting no 20 dated 14 May 2008.
[18] [1987] HCA 15; (1987) 162 CLR 549 at 559-560.
[19] Modern Contract of Guarantee Dr James O'Donovan & Dr John Phillips (Thomson Lawbook Company) Looseleaf service at paragraph 7.200.
[20] Johnson Bros (Dyers) Ltd v Davison (1935) 79 SJ 306.
[21] Wren v Emmett Contractors Pty Ltd (1969) 43 ALJR 213 at 220.
[23] The Shorter Oxford English Dictionary Third Edition (Oxford University Press) 1973.
[25] Fifth Amended Points of Defence and Points of Counterclaim of the First and Second Respondents dated 19 November 2012 and Sixth Amended Points of Defence of the First Respondents dated 22 November 2013.
[26] On 21 November 2013, leave was given to the First Respondent to file and serve Sixth Amended Points of Defence. Paragraphs 15 and 25.2 of the First Respondent's Sixth Amended Points of Defence denies the Applicant's claim based on a breach of the Fair Trading Act 1999, on the ground that the representations did not cause loss or damage to Monty. This was expanded upon during closing submissions on 21 November 2013 where the First Respondent argued that if the Anker principle applied and the Guarantee became unenforceable, it was because of the conduct of Monty, through the actions of the Architect and its dealings with the Builder, and not because of any conduct of the First Respondent. Therefore, the First Respondent contended that if its defence based on the Anker principle succeeded, Monty's alternative claim based on the Fair Trading Act 1999 also failed.
[27] Paragraph 14 of the Sixth Amended Points of Defence of the First Respondent dated 22 November 2013 and paragraph 14 of the Fifth Amended Points of Defence of the First and Second Respondents dated 19 November 2012.
[28] Paragraphs 129-141 of the Amended Witness Statement of: Montaldo dated 9 November 2010.
[29] Paragraphs 142-150 of the Amended Witness Statement of: Montaldo dated 9 November 2010.
[30] Paragraphs 142-150 of the Amended Witness Statement of: Montaldo dated 9 November 2010.
[31] Paragraph B(v) of Monty's Amended Further and Better Particulars of Loss and Damage dated 24 October 2012.
Monty Manufacturing Pty Ltd
Platt
(1987) 162 CLR 549
(1969) 43 ALJR 213