[2014] VCAT 1417
General information, not legal advice.
Victorian Civil and Administrative Tribunal
2014-11-18
Original judgment source is linked above.
Section 77 of the Planning & Environment Act 1987; Mornington Peninsula Planning Scheme; Green Wedge Zone Schedule 2; Environmental Significance Overlay Schedule 1; Contractor's depot & Solid fuel depot; Policy; Link to rural activity; Alienating land for green wedge purposes; Preferred location; Orderly planning
McMillin v Mornington Peninsula SC [2014] VCAT 1417
Mr Gary Testro, Lawyer. He called the following witness -
Mr Henry Wood, senior planner, The Planning Group Pty Ltd
Application under Section 77 of the Planning and Environment Act 1987 to review the refusal to grant a permit
Environmental Significance Overlay Schedule 1 (ESO1) (Moorooduc Plain and Balcombe Valley)
Clause 35.04-1 (use of land in GWZ2 for Contractor's depot and for Solid fuel depot)
Clause 35.04-5 (building and works in GWZ2 for a Solid fuel depot)
Clause 42.01-2 (buildings and works in ESO1 for a Solid fuel depot)
Clause 52.06-6 (reduction in parking requirement for a Solid fuel depot)
Clauses 10, 11, 14, 21.03, 21.04, 21.09, 22.07, 35.04, 42.01, 52.06, 57 & 65
The land is on the east side of Stumpy Gully Road, between Eramosa Road West to the north and Bungower Road to the south. It is rectangular with a frontage of 165 m, a depth of 243 m and an area of about 4 ha. The land is developed with a dwelling, a large shed (former poultry shed) and several outbuildings. Parts of the land are fenced for grazing. The land has two vehicle access points, at the north and south ends of the frontage.
Use for a Contractor's depot and for a Solid fuel depot in the Green Wedge Zone
Buildings and works for a Solid fuel depot in the Green Wedge Zone and the Environmental Significance Overlay
Reduction of parking requirement for a Solid fuel depot
(a) No more than 17 vehicles (including seven water carts) associated with the Contractor's depot must be present on the land at any time.
(b) No more than three vehicles associated with the Solid fuel depot must be present on the land at any time.
(a) Vehicles associated with the Contractor's depot must only enter or leave the land between the hours of 6 am and 6 pm on weekdays, and between 6 am and 3 pm Saturdays, and must not enter or leave the land on Sundays, Good Friday or Christmas Day.
(b) The Solid fuel depot must only operate between the hours of 7 am and 5 pm on each day of the week. The use must not operate on Good Friday or Christmas Day.
In accordance with Section 69 of the Planning and Environment Act 1987, an application may be submitted to the Responsible Authority for an extension of the periods referred to in this condition.
[1] I have considered the submissions of all the parties that appeared, all the written and oral evidence, all the exhibits tendered by the parties, and all the statements of grounds filed. I do not recite or refer to all of the contents of those documents in these reasons.
[2] Mr John Glossop, statement of evidence, p 27.
[3] Mr John Glossop, statement of evidence, p 28.
[4] Mornington Peninsula Planning Scheme cl 21.09 & cl 22.07.
[5] Mornington Peninsula Planning Scheme cl 10.04.
[6] Mornington Peninsula Planning Scheme, Amendment VC103, Explanatory Report, p 2.
[7] Mornington Peninsula Planning Scheme cl 21.03 & cl 21.09.
[8] Mornington Peninsula Planning Scheme cl 22.01.
[9] See eg Andsand Pty Ltd v Kingston CC No 2 [2009] VCAT 2506 at [57].
[10] Landforming to Perfection Pty Ltd v Wyndham CC [2013] VCAT 1703 at [44].
[11] Mornington Peninsula Planning Scheme cl 22.07.
[12] Foster v Port Phillip CC [2004] VCAT 1912 at [26].
[13] Mornington Peninsula Planning Scheme cl 52.06-5.
McMillin
Mornington Peninsula SC [2014] VCAT 1417