JUDGMENT
1 HIS HONOUR: By amended summons filed on 7 May 2002 the plaintiff, McCallum Developments Pty Limited, has brought proceedings against the first defendant, The Owners Corporation SP 53908, and the second defendant, Fair Trading Administration Corporation, seeking the following relief:
"1. A Declaration that the First Defendant had and has no right to make insurance claim no. I 95/6945 ('the Claim') under the Comprehensive Insurance Scheme constituted under the Building Services Corporation Act 1989 and continued under the Building Services Corporation Legislation Amendment Act 1996 as the claim is out of time.
2. A Declaration that the Second Defendant has no power pursuant to the Building Services Corporation Legislation Amendment Act 1996 or otherwise to assess and determine the Claim as the claim is out of time.
3. A Declaration that the Second Defendant's approval in principle of the Claim, dated 12 November 2002, is void.
4. An Order that the Second Defendant be restrained, both pending suit and perpetually, from assessing and determining the Claim.
5. Such further or other order as the Court may deem fit."
2 Ultimately the plaintiff did not press for the relief sought in paras 2 and 4 but claims only the declarations in paras 1 and 3.
3 The plaintiff is a developer. The first defendant named in the summons, the Owners Corporation SP 53905, is, as its name suggests, the body corporate for residential home units. Those units were constructed at 117 John Whiteway Drive, Gosford. In all there are thirty-five residential units. Their construction was carried out in two stages, commencing somewhere between 23 July 1995 and 16 October 1995. The completion date appears to have been in October 1997. I shall return to the evidence as to the construction period presently.
4 The evidence received on the hearing of the summons consisted of the following: affidavits of Neill Douglas McCallum, a director of the plaintiff, sworn on 6 February 2002 and 2 May 2002, an affidavit sworn by Susan Edwards, the current chairperson and secretary of the first defendant, and an affidavit of Rodney Elliott, who is the general manager of the insurance service of the Department of Fair Trading. Each of those deponents was cross examined.
5 The Building Services Corporation Act, 1989 made provision for insurance schemes for residential building work and provided for the Corporation to be the insurer. It is common ground between the parties, however, that the relevant insurance scheme is administered by the second defendant. The evidence establishes that the first defendant pursued an insurance claim through the second defendant in respect of allegedly faulty work by the plaintiff. It is this claim and decisions made in relation to it which have prompted the present summons.
6 After the claim was first made, the second defendant wrote to the plaintiff on 10 August 2000 and the letter read in part as follows:
"I refer to the above complaint recently lodged by Strata Plan 53908 with the Department of Fair Trading regarding building/trade work carried at above address.
In view of the information contained in the file, this matter was referred to the A/Claims Manager of the Insurance Branch who is responsible for the insurance scheme administered by this Department.
Under the Building Services Corporation Act/Home Building Act, the contractor is responsible for defective work for a period of three years for what are considered general defects and seven years for major structural defects.
As the items in the complaint appear to be general defects and the above time limit has expired the Department will be taking no further action at this stage. The only other avenue which is available to the complainant would be to seek legal advice."
7 However, the second defendant wrote again to the plaintiff on 19 June 2001 concerning the first defendant's insurance claim, and it is apparent from the terms of this and later letters that the second defendant reconsidered its earlier decision:
"The Department of Fair Trading, Building Insurance Branch has received an insurance claim regarding building work at the above address which the Department has been advised was done or contracted to be done by your company This claim has resulted from the previously unresolved complaint under C 2000/1391 concerning defective and/or incomplete work.
Under the provisions of the Home Building Act 1989, if the Department approves and subsequently pays out a claim under the Comprehensive Insurance scheme, it is the Department's duty to seek recovery against the contractor who contracted to do or who did the work for the amount of the claim settlement. Should the contractor fail to reimburse the Department either in full or by a deed of arrangement, then recovery proceedings will be commenced.
Should you wish to make a written submission or request any information in regard to the claim please forward your submission to the Manager, Building Insurance Branch, without delay. Please quote insurance claim file number I 95/6945 We will ensure that your submission is considered, provided it is received before a decision is made."
8 That letter prompted this response from the plaintiff on 26 June 2001:
"I refer to your letter of 19/6/01 & draw your attention to the letter sent to me dated 10/8/2000 (copy attached), & my subsequent phone conversation, where I was advised, considering the commencement dates, that all claims were outside the D.F.T. timeframe limits (i.e. 3 years general defects, 7 years structural defects from commencement i.e. 23-7-95) & that no further action would be taken. I rely on this advice which is consistent with my understanding of the situation."
9 The second defendant notified the first defendant by letter dated 12 November 2001 that "approval in principle" had been granted under cl 5(1)(d) of the comprehensive insurance scheme to settle the first defendant's claim and, consistently with that notification, the second defendant wrote to the plaintiff on the same date advising:
"On 19th June 2001 the Department of Fair Trading notified you that an insurance claim regarding work at the above address had been received by the Department's Building Insurance Branch. We invited you to submit any information you had regarding the claim.
This claim has now been approved under the Comprehensive Insurance Scheme for an amount to be determined upon the receipt from the Owners Corporation of a fair and reasonable quotation based upon the enclosed Schedule of Work.
Please note that the Owners Corporation could be eligible for a claim of up to $700,000. I will advise you once the Department has determined the amount of the claim.
In the meantime, should you wish to make enquiries concerning this matter, please contact Vince Kennedy at DFT Home Building Insurance on telephone number (02) 9377.9188."
10 I do not propose to record exhaustively all the communications between the plaintiff and the second defendant from the time that the plaintiff became aware of the second defendant's decision on the first defendant's insurance claim, but what I have set out suffices by way of background to a consideration of the plaintiff's claim for relief on the present summons.
11 Central to the plaintiff's claim is the contention that the insurance claim presented by the first defendant to the second defendant was out of time. Consideration of this contention necessitates an examination of the relevant insurance scheme which is provided for in Pt 6 of the Building Services Corporation Act, 1989 and by way of regulation under that Act. The name of the statute was subsequently changed to the Home Building Act and changes to the insurance regime were made by the Building Service Corporation Legislation Amendment Act, 1996. However, the operation of the 1989 Act and the insurance scheme to be found in Form 4 to Schedule 1 of the Building Services Corporation Regulation, 1990 remains applicable for the purposes of this case, involving as it does work insured before the commencement of the amending legislation on 1 May 1997.
12 Form 4 clause 4 defines "beneficiaries" for the purposes of the insurance scheme as including:
"(a) the owner of the land on which the residential building work was done or was contracted to be done, except where the work was authorised to be done under an owner-building permit; and
(b) the person, other than the owner, who contracted to have the residential building work done; and
(c) the successor in title to the owner of the land on which the residential building work was done."
13 The losses indemnified under the scheme are defined in clause 5 and relevantly include:
"(1) Subject to the maximum payment provisions (clause 6), the method of assessing claim benefits (clause 8) and the exclusions specified in this Scheme (clause 9), the Corporation will indemnify the following losses reasonably incurred by a beneficiary:
……………….
(d) losses in rectifying defects in insured building work or insured owner-builder work due to:
(i) bad workmanship; or
(ii) faulty or unsuitable materials…….
(e) losses in repairing:
(i) damage caused to the dwelling by a defect in the insured building work or insured owner-builder work…….."
14 Clause 6 makes provision for maximum payments and then clause 7 provides for time limitations. This provision assumes particular relevance in the present context and is as follows:
"(1) Subject to subclause (2), to qualify for the benefits under this Scheme, the beneficiaries must notify the Corporation in writing of the matters that could give rise to the losses referred to in clause 5 within the following times:
(a) ……..
(b) for loss relating to heads of claim in clause 5(1)(d) or (e) incurred in rectifying major structural defects or in repairing damage to the dwelling that has occurred in consequence of major structural defects - within 6 months after the beneficiary first becomes aware of the defect, but not later than 7 years from:
(i) the commencement of insured building work which is not also insured owner-building work; or
(ii) the date of issue of the owner-builder permit for insured owner-builder work;
(c) for loss relating to heads of claim in clause 5(1)(d) or (e) other than those referred to in paragraph (b) - within 6 months after the beneficiary first becomes aware of the defect, but not later than 3 years from:
(i) the commencement of insured building work which is not also insured owner-builder work; or
(ii) the date of issue of the owner-builder permit for insured owner-builder work."
15 The time restraints provided for under clause 7(1) may be extended pursuant to sub-clause (2) which is expressed as follows:
"(2) The Corporation may extend the times specified in subclause (1) if it is satisfied that the delay in notification was due to circumstances outside the control of the beneficiary."
16 It is the plaintiff's contention that in the present case the second defendant in administering the insurance scheme has accepted the claim advanced by the first defendant as being within time because the claim was lodged not later than three years from the commencement of the insured building work. The contention is that in accepting the claim there was a failure to consider the requirement imposed by sub-clause (1) that notice was required to be given in writing of matters that could give rise to the losses referred to in clause 5 "within six months after the beneficiary first becomes aware of the defect". It is submitted on behalf of the plaintiff that the evidence establishes that no attention was given to the six month requirement at all and that this failure made the decision of "approval in principle" as conveyed on 12 November 2001 a void determination. Mr Thompson referred to Hale v Parramatta City Council (1981-82) 47 LGRA 269 and Minister for Aboriginal Affairs v Peko-Wallsend Limited (1985-86) 162 CLR 24 in support of this submission.
17 In resisting the plaintiff's claims for declaratory relief, both defendants have submitted that whether or not the second defendant determines it should make a payment pursuant to the claim of the first defendant under the statutory insurance scheme is a matter between the defendants, and the plaintiff has no standing to seek the relief expressed in the summons. The defendants rely on the unreported decision of Newman J in P. & V. Sammut Homes Pty Limited v Building Services Corporation (24 April 1997).
18 In Sammut Homes the court was concerned with the same statutory scheme as in the present case. There the builder was in dispute with the owners and arbitration proceedings were pending. The owners also made a claim under the statutory insurance scheme and the corporation informed the builder it intended to determine the claim. This prompted the builder to seek declaratory relief and an order in the nature of prohibition to restrain the corporation from exercising its powers under Pt 6 of the Building Services Corporation Act, 1989 pending conclusion of the arbitration. Newman J dismissed the builder's summons.
19 In the present case, the builder is concerned that if the second defendant proceeds to meet the first defendant's claim the second defendant will pursue it to recover what has been paid out.
20 Section 98 of the Building Services Corporation Act provides:
"(1) Any amount paid by the Corporation under BSC Insurance may be recovered by the Corporation in a court of competent jurisdiction as a debt from the person by whom the residential building work concerned was done or contracted to be done.
………………..
(4) After considering the circumstances of the case, the Corporation may decide:
(a) not to attempt to recover an amount under this section; or
(b) to accept any amount in satisfaction of its right to take recovery action under this section."
21 This very same provision influenced the decision in Sammut Homes. Newman J reasoned that in order to succeed in an action for debt under s 98 the Corporation would have to prove "all the elements of its claim" (see p 13 of the judgment). Later (at p 14) his Honour said:
"It follows that any payment due by the defendant to the [owners] does not involve an interference with the private right of the plaintiff in defending a claim made on the scheme. This is particularly so because it is also the law that the plaintiff's rights in respect of any liability under s 98 of the Act are the same as any other person suing for debt. That is, as I have said, that [if] the present defendant were to bring such a claim [it] must prove all elements of its claim and if it has paid too much to the [owners] as a consequence of an administrative error any excess payment would not be recoverable."
22 In Sammut Homes and in the present case reference was made to the decision in Builders' Licensing Board v Inglis & Anor (1985) 1 NSWLR 592. That case involved consideration of the Builders Licensing Act of 1971, later replaced by the Building Services Corporation Act. Under s 36 of the 1971 Act, there was a recovery provision similar to s 98 of the 1989 Act. Section 34(3) of the Builders Licensing Act provided:
"Any amount paid by the Board under a house purchasers' agreement in respect of any building work may be recovered by the Board in a court of competent jurisdiction as a debt from the person by whom the building work was carried out or undertaken to be carried out or out of the estate of that person from his personal representation."
23 In Inglis the Court of Appeal considered the nature of the recovery proceedings under s 34(3) and Kirby P said (at 596-597):
"It cannot be said that any amount paid by the Board is recoverable. For example, an amount paid as a result of an administrative error or for a reason wholly extraneous to the purposes of the Act, would clearly not be recoverable. The terms of s 34(3) of the Act limit the amount recoverable to amounts paid 'under a house purchaser's agreement' and 'in respect of any building work'. So that connection, at least with the builders conduct, must be shown. Indeed this much was conceded by counsel for the Board.
But the result of the Board's contention would still be surprising if it meant that an amount paid under such an agreement and in respect of building work could be recovered as a debt without the builder having any entitlement to scrutinise, and have the court scrutinise, the basis of the debt. Such a result would deprive the builder of the opportunity to challenge the claim, to subject it to scrutiny and to rebut it if such scrutiny disclosed defects in it.
It is possible that the legislature intended to take away this normal entitlement of our system. However, it would be unusual for it to do so. And clear statutory language or other indicia of the Parliament's intent would be needed to drive the court to such a result. For the consequences would be that a person might complain to the Board, the Board might pay a very large amount and the builder might be fixed with an obligation to reimburse the Board, although the builder never had knowledge, even after the payment, of the precise way in which this substantial debt was said to be incurred. Such a legislative scheme could be devised, relying on the integrity and good sense of the officers of the Board, to protect builders. It would certainly save the costs of litigation, typically high in building cases, and often in such cases disproportionate to the matter in dispute. But it would be an unusual provision. It would, in my view, require the clearest possible legislative language to produce such a result."
24 And, later (at 598) the President said:
"But where, as here, there is a contest, the entitlement to recover as a debt should not, in my view, bypass the normal requirement that, when a claim is disputed, he who alleges must particularise and prove."
25 What was said in Inglis is equally apposite to s 98 of the Building Services Corporation Act, and I respectfully agree with Newman J's analysis of s 98 of the Building Services Corporation Act. It follows that should the second defendant make a payment to the first defendant on its claim and later take recovery proceedings against the plaintiff, the second defendant would in such proceedings be required to prove all the elements of its claim, and it would be required to prove, if called upon by the plaintiff to do so, that the first defendant's claim was made within time for the purposes of Form 4 clause 7(1), or, alternatively, that time had been extended in accordance with clause 7(2), upon the corporation being satisfied "that the delay in notification was due to circumstances outside the control of" the first defendant.
26 Since the processing by the second defendant of the claim made by the first defendant would not interfere with any private right of the plaintiff, the plaintiff is required "to show a special interest over and above that enjoyed by the public generally": see Australian Conservation Foundation Inc. v The Commonwealth (1980) 164 CLR 493 at 526 and 547, and Day v Pinglen Pty Limited (1981) 148 CLR 289. In Day, the court said (at 300):
"The existence of an impending detriment threatened by an unlawful act is sufficient to confer standing to seek an injunction to restrain that act, without regard to theoretical possibilities in other circumstances: cf Campbell v Paddington Corporation (1911) 1 KB 869 at 879."
27 A special interest may be shown other than that expressed in Day. As Gibbs CJ observed in Onus v Alcoa of Australia Limited (1981) 149 CLR 27 at 36:
"The [special interest] rule is obviously a flexible one since, as was pointed out in [Day], the question what is a sufficient interest will vary according to the nature of the subject matter of the litigation."