[2023] NSWCATCD 81
NCAT Consumer and Commercial
2023-06-22
Original judgment source is linked above.
d [1933] HCA 25; 48 CLR 475 Moratic Pty Limited v Gordon [2007] NSWSC 5 News v Cotes [2019] NSWCATAP 186 Oshlak v Richmond River Council [1998] HCA 11 Pongrass v Small [2021] NSWCATAP 314 Precision Plastics Pty Ltd v Demir [1975] HCA 27; 132 CLR 372 at 370-371 Taylor v Johnson [1983] HCA 5 TC Industrial Plant Pty Ltd v Robert's Queensland Pty Ltd [1963] HCA 57 Thompson v Chapman [2016] NSWCATAP 6 Waltons Stores (Interstate) Limited v Maher [1988] HCA 7; 164 CLR 387 Watson v Foxman (1995) 49 NSWLR 315 Texts Cited: None cited Category: Principal judgment Parties: Applicants - Jamie Mazurek and Donna Burgess
Respondent - Fisnik Fisniku and Saskia Fisniku, trading as Nobel Homes Central Coast Representation: Counsel: Applicants - E Glover
Solicitors: Applicants - Tonkin Drysdale Partners File Number(s): HB 22/03752
Outline
Hearing
Jurisdiction
Relevant law
Pleadings
Lay evidence
Expert evidence
Submissions for the owners
Submissions for the builder
Consideration
Issues
Chronology
Findings of fact
Did the costs plus contract come to an end? If so: how and when?
Is the fixed price contract binding?
How and when did that contract come to an end?
Have either of the estoppel defences been established?
Did the owners fail to mitigate their loss?
Can the owners recover the cost of completion?
Can the owners recover for overcharging?
Can the owners recover the storage costs incurred?
Claim for interest
Claim for costs
Summary
Orders
Appendix A Item No Description Scope of work 1 Remove the barge flashing 2 Inspect and ensure the necessary degree of fall in the gutter 3 Install weatherproofing, if required, to the roof sheets A Rear parapet 4 Rectify any water damage 5 Ensure roof sheets are turned up 6 Reinstall the barge capping 7 Clean up on completion 1 Jack up floor joists B Pier caps 2 Install ant caps under all brick piers 3 Lower floor joists onto ant caps 4 Clean up on completion 1 Remove single plasterboard screw C Tie down straps 2 Drill into the concrete footing at every pier a 10mm booker rod with epoxy to secure the rod. That is drill through the floor joists recessing the nut below the level of the joists for the new sheeting to be installed over 3 Clean up on completion 1 Set up A frames 2 Install the correct length lintel with a minimum of 100mm bearing each side D Window W09 3 Complete the brickwork to the head and sill with flashing 4 Install storm moulds to weatherproof the opening 5 Clean up on completion 1 Tooth the brickwork to the southern façade and complete the brickwork to watertight the building 2 Install window on northern façade including flashings to head and sill E Brickwork 3 Install lintel with a minimum 100mm bearing each side 4 Brickwork to window sill with weepholes 5 Install storm moulds to weatherproof the opening on the northern facade 6 Clean up on completion 1 Remove all existing sarking that has been exposed and deteriorated F Sarking wrap 2 Replace sarking that is removed with Ametalin wrap sarking 3 Clean up on completion 1 Remove LVL beam in master bedroom near the entrance to the ensuite which has been cut through G LVL beam 2 Install new VL beam 3 Clean up on completion
Appendix B Date Description Reference Feb 16 Owners purchased the subject property A27, [8] Sep 18 Owners contacted a mortgage broker, Jasmin Wilson A27, [10] Oct 18 Ms Wilson recommended the builder A27, [11] 30 Jan 19 Commonwealth Bank (CBA) approved $80,000 loan A27, [13] 07 Jun 19 Builder provided quote #1019 for $296,450 (4 stages) A272 16 Jun 19 Builder provided quote #1021 for $296,450 (more details) A44 01 Oct 19 Plans finalised, submitted to local council (1 page plan provided) A47-48 02 Oct 19 Builder provided quote #1042 for $147,347.20 A49 02 Oct 19 Owners advised builder their budget was $90,000 A50 04 Oct 19 Owners bought & stored second-hand kitchen & appliances A28, [23] 22 Oct 19 Development application approved (refers to 3 pages of plans) A54 24 Oct 19 Builder sent quote #1043* for $93,230.50 A60 24 Oct 19 Builder sent quote #1044* for $50,524.10 A62 31 Oct 19 Certificate for homeowners' warranty insurance provided A64 09 Nov 19 Builder's invoice #1053* for $17,796.04 A66 11 Nov 19 Costs plus contract signed A77 13 Nov 19 $17,796.04 was paid: $840.95, $14,621.45 and $2,333.64 A65, 109 18 Nov 19 Work commenced at the site A29, [35] 22 Nov 19 Builder's invoice #1056* for $5,084.06, paid the next day A111-117 02 Dec 19 Construction certificate issued by certifier A126 14 Dec 19 Builder issued invoice #1060* for $22,104.01, paid 2 days later A129-142 27 Dec 19 Builder issued invoice #1063* for $22,290.90, paid 2 days later A143-156 03 Jan 20 Owners texted Builder: "… We're out of money and confused on how to proceed…" A726 03 Jan 20 Ms Wilson advised Owners CBA (1) would only release further funding when she was working, (2) required fixed price contract A31, [46] 05 Jan 20 Owners advised Builder work to stop until loan situation resolved A374 06 Jan 20 Owners' email said: "Once again, we apologise for the inconvenience of not having the funds to get you working …" A726 06 Jan 20 Work at the premises stopped A31, [47] Jan 20 Builder alleges conversation with Owners in which it was said the Owners wish to stay on a costs plus basis and that the fixed price was "just for the bank" A671, [20] 08 Jan 20 Builder emailed quote #1048 for $88,000 A157-158 14 Jan 20 Owners asked for fixed price contract with staged payments A160 28 Jan 20 A fixed price contract was signed by the parties A161 24 Feb 20 Builder issued invoice #1067* for $1,973.70, paid 3 days later A194, 202 Late Feb Owners agreed to let Builder do "some small work" A260, [49] 26 Feb 20 Builder (1) advised doors would be installed later that week, and (2) sought a date for resumption of the building work A201 26 Feb 20 Owners replied, saying unable to indicate a resumption date A418 21 Mar 20 Owners advised what they bought to seal underside of floor A767 28 Mar 20 Builder issued invoice #1069* for $12,087.05 A203 30 Mar 20 Builder emailed Owners, saying: "… It's hard because we're doing costs plus" A769 30 Mar 20 Builder emailed owners, raising contract arrangements A215 01 Apr 20 Builder sought details from Owners A433 01 Apr 20 Owners supplied details of fixtures and inclusions A433-436 03 Apr 20 Builder sent overdue notice for invoice #1069* A216 03 Apr 20 Owners told Builder (1) they no longer have control of the money, (2) they will pay the labour component of invoice #1069, (3) "the balance will be received when the first progress payment is made" A261, [60] 04 Apr 20 Owners paid $5,605.25 in part payment of that invoice A218 18 Apr 20 Owners allege meeting at which commencement date for fixed price contract amended from 01 Feb 20 to 01 Apr 20 A33, [60] & A219 On or around Builder alleges meeting at which Ms Wilson suggested the parties start relying on the fixed price contract, Builder said a "proper quote" should be made, and Builder asked Owners to provide a list of product selections A673, [33] 19 Apr 20 20 Apr 20 Meeting: Owners suggest PC items & schedule discussed; A33, [61] Builder suggests amended contract date also discussed A673, [34] 20 Apr 20 Builder emailed Owners, saying $88,000 was "vague pricing" and asking about unpaid $6,481.80 invoice #1069 A220 20 Apr 20 Owners reply email, which referred to the unpaid amount of invoice #1069* being "included in the first lock-up stage costing" A221 24 Apr 20 Builder issued invoice #1070 for $35,000, seeking a progress payment described as "Lock up stage payment" A222 27 Apr 20 Owner sent email, indicating their product choices A777 04 May 20 Builder sent quote #1062 for $94,229.70 (cf $88,000) A223-225 04 May 20 Builder sent quote #1063 for $33,456.50 (additional work) A226-228 04 May 20 Owners replied "We aren't sure we are on the same page …" A229 05 May 20 Owners requested quotes for four specific trades A230 07 May 20 Builder alleges conversation re owners' additions A675, [44] 14 May 20 Variations for $8,259 and $6,573 were signed A231-232 14 May 20 Builder's email included reference to the unpaid $6,481.80 A233 14 May 20 Owners' reply referred to "what the $35,000 is meant to cover" A233 14 May 20 Builder's reply referred to the bank's payment schedule A233 18 May 20 On site conversation alleged by both parties A34 [72]; A263 [69]; A676 [47] 18 May 20 Text messages exchanged A785-786 18 May 20 Ms Wilson advised Owners CBA had paid Builder $35,000 A35, [73] 19 May 20 Owners requested no further payments be made "until we have resolved all issues and agree to what the next steps are" A234 19 May 20 Builder replied: "No problem." A234 20 May 20 Owners alleges conversation in which it was suggested the builder wished to continue and wanted to work with them A35, [75]; A263, [71] 24 May 20 Builder issued invoice #1073 for $26,110.10 which included $6,481.80, being the unpaid balance of invoice #1069*, under cover of an email which began: "Here is your final invoice" A235-237 24 May 20 Owners sent email to Builder which ended with: A456 "All keys are to be returned on this final day." 25 May 20 Certifier issued two inspection notices: both satisfactory A109,112 05 Jun 20 Builder emailed "Notice of Mutual Termination of Contract" A238 07 Jun 20 Builder paid owners $8,889.90, equal to the invoice #1070 total of $35,000 less the invoice #1073 total of $26,110.10 A35, [78] 15 Jun 20 Owners email suggested any termination was not mutual A239 16 Jun 20 Builder sent "Notice of Termination of Contract" A240-241 18 Aug 20 Owners' solicitor sent "Notice of Termination of Contract" A242 08 Apr 21 Owners obtained quote from Alpha Carpentry for $195,958.00 A244-253 22 Aug 22 Owners obtained quote from Alpha Carpentry for $242,386.00 A639-648
Mazurek
Fisniku
[1933] HCA 25
(1995) 49 NSWLR 315
[1998] HCA 11
[2003] HCA 22
[1990] HCA 59