Issue (c): The threatened application of Reich
66 The third arm of the claimant's case contends that Reich was wrongly decided and that the Commission would commit a jurisdictional error if it were to find that conduct in breach of a contract is capable in itself of establishing that the contract is unfair in the sense defined in s105 of the Act. The point was not part of the claimant's written submissions, but emerged opaquely in the submissions of Mr Douglas QC.
67 The scope and correctness of Reich will be addressed by this Court (as presently constituted) in Sydney Water Corporation Ltd & Anor v Industrial Relations Commission of NSW & Ors (CA 40666/04). Judgment in that matter was reserved on 22 September 2004. This summons can be dealt with by assuming in the claimant's favour that it is not open to the Commission to hold that a contract has become unfair merely because of a party's conduct in breach (cf Solution 6 at [162]-[164] per Handley JA).
68 On this assumption, the claimant must still establish that the claim of unfairness made by the IRC applicants is based upon conduct in breach of the Contracts. This the claimant has substantially failed to do, for the reasons that follow.
69 The Reich point was not advanced in the claimant's written submissions and it was at most a subsidiary alternative in the oral submission of Mr Douglas QC. The nub of this submission was that some of the monetary claims in the IRC Summons were based on allegations of contravention of the Contracts by Mayne Nickless. The submission was advanced globally, directed at the entire IRC Summons, whereas close examination of that document indicates that the submission only engages claim 10 in that Summons. All other claims are based in terms upon specific allegations of unfairness in what the Contracts do not provide for.
70 Most of the allegations in the Commission are to the effect that the contractual arrangements are unfair in what they do not provide. The unfairness is said to be based in part on representations preceding entry into the Contracts, in part upon additional costs to Portpath stemming from changes in patient numbers and other matters occurring after the Contracts commenced. Issues of these types fall squarely within the Commission's jurisdiction under s106. it is no answer to suggest, as the claimant does in par 30 of its written submissions, that these claims would also lie in the Commercial Division or the Federal Court if framed by reference to the general law of misrepresentation or the Trade Practices Act 1974.
71 The major claim in the IRC Summons, monetarily speaking, concerns the unfair operation of the contractual mechanism for the review of the fees payable to Portpath. This is Claim No 1 and more than $3 million is at issue, excluding interest.
72 Claims 2, 3, 4, 5, 6, 7, 8, 10 and 12 in the IRC Summons are similar in form and substance to Claim 1. Claims 11 (Inconvenience, distress and vexation), 12 (loss of sale of business), 13 (professional costs) and 14 (interest) are not framed as claims for variation of the Contracts, but are obviously advanced as monetary claims consequential upon the other claims. They are capable of being addressed under s106(5) and do not necessarily involve the Reich issue. Indeed they appear highly unlikely to do so.
73 Only one of the claims in the IRC Summons appears to be based upon unfairness arising from conduct said to be in breach of the Contracts. Claim 9 alleges that nine patients have received tests that have not been billed by Portpath under the terms of the Deed. Since the sum claimed is $135, prohibition is a discretionary remedy, there has been considerable delay and since none of the submissions of either party squarely addressed the Reich issue in this context, this is a classical case for the application of the maxim de minimis non curat lex.
74 I have had the benefit of reading Hodgson JA's reasons. I agree with them.
75 The Summons should be dismissed with costs.
76 HODGSON JA: I agree with the orders proposed by Mason P, and subject to what I say below, substantially with his reasons.
77 In my opinion, the claimant has not shown entitlement to relief on the basis that there is no relevant contract or arrangement whereby a person performs work in an industry. The deed and associated contract and arrangements are capable of amounting to such a contract or arrangement, and whether or not they do may depend on the detailed facts ultimately found by the Commission. In approaching the matter, in my opinion the Commission will need to have regard to the principle referred to by Priestley and Handley JJA in Production Spray Painting & Panel Beating Pty. Ltd. v. Newnham (1991) 27 NSWLR 644 at 657, to the effect that it is not sufficient to establish jurisdiction that a contract involves the provision of goods and services, with a consequent performance of work in an industry. In cases such as the present, where it appears that the applicants do work for entities other than the claimant, this may be a real question. Although plainly a contract or arrangement whereby a person performs work part-time in an industry may be within the provision, the circumstance that the person performs work for other people or companies in the same industry pursuant to other contracts and arrangements will be a factor in determining whether the contract or arrangement in question is in truth one whereby the person performs work in an industry, or rather whereby the person provides goods and/or services with consequent performance of work in an industry.
78 McCOLL JA: I agree with Mason P.