[2025] NSWCATAP 317
General information, not legal advice.
NCAT Appeal Panel
2026-01-20
Original judgment source is linked above.
(1) Item 2: Tiles floors of wet areas to have a minimum 1:80 fall to waste;
(2) Item 4: Bath and vanity bench tops not installed with care and skill;
(3) Item 5: Vanity wool linings main bathroom not straight; and
(4) Item 8: Water stops across wet areas not flush with floor level.
(1) a joint inspection to have the defects reassessed;
(2) reassessment by the NSW Building Commission;
(3) reimbursement of $2,200.00 for my expert report;
(4) reimbursement of $792.00 for attendance of my expert;
(5) toilet roll holder and two guest towel rails that the appellant says she paid for.
(1) A question of law should be articulated with precision;
(2) Absent leave to appeal, the question of law is the subject of the appeal;
(3) A question of law means a "pure question of law" which is not dependent on facts not found and is not dependent on the answer to the question;
(4) A party contending that a question of law was wrongly decided must identify the question in abstract terms;
(5) A mixed question of fact and law is not a question of law, and a question of law must not be hypothetical or arid;
(6) A question of law must be capable of affecting orders the subject of the appeal, not purely the reasons; and
(7) There may be disclosed an error of law but this of itself does not necessarily raise a question of law.
(1) 12(1)(a) - the decision of the Tribunal under appeal was not fair and equitable; or
(2) 12(1)(b) - the decision of the Tribunal under appeal was against the weight of evidence; or
(3) 12(1)(c) - significant new evidence has arisen (being evidence that was not reasonably available at the time the proceedings under appeal were being dealt with).
"... there was a "significant possibility" or a "chance which was fairly open" that a different and more favourable result would have been achieved for the appellant had the relevant circumstance in para (a) or (b) not occurred or if the fresh evidence under para (c) had been before the Tribunal at first instance."
(a) issues of principle;
(b) questions of public importance or matters of administration or policy which might have general application; or
(c) an injustice which is reasonably clear, in the sense of going beyond merely what is arguable, or an error that is plain and readily apparent which is central to the Tribunal's decision and not merely peripheral, so that it would be unjust to allow the finding to stand;
(d) a factual error that was unreasonably arrived at and clearly mistaken; or
(e) the Tribunal having gone about the fact-finding process in such an unorthodox manner or in such a way that it was likely to produce an unfair result so that it would be in the interests of justice for it to be reviewed.
(1) lodge with the Tribunal and give to the other party all the evidence that was provided to the Tribunal at first instance on which a party intends to rely; and,
(2) if what happened at the hearing at first instance is being relied on by a party in the appeal, a typed transcript of the relevant parts of the hearing, together with a sound recording of the entire hearing.
Item 2 Tiled floors of wet areas to have a minimum 1: 80 fall to waste & Item 8 Water stops across wet areas not sitting flush with floor level.
108 I find that the limited photos in the supplementary expert report were not conclusive evidence that water was pooling in the wet areas for 4 to 5 hours during normal use. In any event the pooling was created by the drain being blocked for test purposes. Further, if it had been pooled for such a long period it is not a surprise that areas had elevated moisture levels when tested, and it is not a reasonable conclusion to say this moisture arose due to the disputed waterstop levels in Items 7 and 8. There was no evidence of leak under tiles.
109 This is particularly cogent where Frontline's expert was not given any opportunity to reply to this material supplied very shortly before, or at the conclave. I give more weight to the oral evidence of Frontline's expert that there was no ponding in the bathroom, and he tested for this when he did his first report. I accept this evidence even though there is no written mention of that test in the report. I accept (sic) also accept Frontline's evidence that falls did meet the either 1:100 or 1:80 requirements when he did his inspection and the applicant's readings may have been subject to error for angle to millimetre conversion. I accept that on his inspection and testing the water onsite fell into the drain, not outside.
110 Further, if waterproofing and consequent ponding had been such an issue that ought to have been addressed in the applicant's first expert report. It is more probable than not that when the applicant's expert prepared the first report as he did not caried out any water testing at the first inspection because he had no instructions from the applicant that ponding of water was an issue.
111 In addition, the claims that the waterstops were not installed correctly and that wet area falls were incorrect are not observable defects but ones that may happen in the future. Frontline's expert also said that installation of aluminium angles being installed on the top of a membrane angle is standard. The defects claimed are bare assertions and presumptions, not observable defects. The statutory period for action on major defects is 6 years and the applicant would have the opportunity to make a claim if the defect was realised.
112 Ultimately, I give more weight to the overarching opinion of Frontline's expert that to strip down and redo the wet areas is disproportionate in the circumstances of the case and accounting for the quality of the work done. To execute extensive remedial action when there was no evidence of any defect proven is not accepted.
113 There was no breach of a warranty under s 18B for items 1, 2, 7 and 8
Item 4 - Bath and vanity benchtops not installed with care and skill.
15 An inspector from the NSW Building Commission attended on 16 May 2024. A rectification order was issued on 24 May. Frontline said that even during this inspection the applicant was verbally abusive. The rectification report and order made no findings that works done as of the date of the report were defective or that the builder had caused damage to the structure of works. The only order made was for Frontline to complete the contractual work. The applicant was ordered to allow reasonable access for this to occur. The order stated the rectification works to complete the contractual items ceased to have effect once this proceeding was lodged with the Tribunal.
50 In the joint conclave report the applicant's expert found that chips to the vanity benchtop and bath damaged both items. Rectification required replacing the bath ($1,792.00) and the vanity top ($650.00).
51 Frontline's expert said he could not identify any of the imperfections alleged. He opined that the bath surface is "absolute highest quality without defects or visual impairment". In relation to the vanity bench top, Frontline's expert said it was a "very high quality item and installation". It was alleged the applicant's expert focused on a tiny spot or indent, not considered a defect. Tiny and slight imperfections are expected with benchtops. Frontline's expert said that the applicant's expert referred to no manufacturer's standards in relation for supply of standard stone.
52 On 12 March 2024, Frontline sent an email to the applicant stating that the defect to the bathtub had been repaired. The marble vanity top which had some minor chipping would be replaced.
53 Applicant's expert relied on a zoomed photo of the vanity benchtop only (page 49 report). Frontline's expert relied on the photos for both bath and benchtop included in his report (pages 45-49). Even on the zoomed photo I could ascertain no defect beyond what normal imperfections might be. The only photos of the bath showed it to be in excellent order. Any damage caused to the bath by contractors had been repaired.
54 The claim is not allowed.
Item 5 - Vanity wall linings main bathroom not straight
55 The applicant's expert found deviation in the straightness of the existing bathroom wall along the vanity of approximately 7 millimetres over 2 metres contrary to the standard of 4 millimetres over 2 metres as required in the NSW 15 'Guide to Standards and Tolerances 2017, section 4.3 - straightness of steel and timber frame surfaces'.
56 Frontline's expert said the standard relied on was for framing, not the installation of tiles along the length of the wall. He said that 7 millimetres at a corner in a tile application is acceptable industry practice. He stated that the measurements of the applicant's expert were erroneous. The standard referral only applied for a timber or steel frame. The measure of the external tile surface is not related to the timber frame tolerance referred to. The tile application he observed was straight and acceptable when considering impacts associated with glue and applied liquid membrane would have at corner areas. This was also another alleged defect that only arose applicant's supplementary expert report without Frontline's expert having been present or being able to carry out any tests. It was asserted the applicant's expert observations were theoretical and the frame was not measured in the first report.
57 I accept that if this defect had been obvious, it would have been included in report of any defects of the Building Commission inspector when the inspection and rectification order was made. The first report and supplementary report contain no prior instruction of the alleged defect.
58 I accept the evidence of Frontline's expert that at the time of the first inspection "the wall, the tiles and installation of high quality and defect free".
59 The claim is not allowed. Leave to appeal in respect of Items 2 and 8 is therefore refused.
Reimbursement of $2,200.00 for expert report, $792.00 for attendance of expert.
114 Each party sought costs of their expert report and for their expert attending the final hearing to give evidence. The normal rule relating to costs in proceedings over $30,000.00 is that costs successful party in the proceeding are paid by the unsuccessful party.
115 The applicant has only been successful in this proceeding on two relatively minor issues and not the main substance of the claim. I am not satisfied she has been sufficiently successful to justify an order being made for her expert's costs.
116 Nor am I satisfied it would be just in the circumstances of the case to require the applicant to pay the costs of Frontline's expert. While not contested at hearing, Frontline did fail to comply with obligations under the HBA. For example, it provided no standard-form home building contract for the works. It did not provide the applicant with insurance as required under the Home Building Compensation Fund. It is these failures that caused the applicant to distrust Frontline from the beginning of the contract. By failing to comply with these requirements under the HBA, the respondent partly contributed to the possibility of the applicant proceeding with complaints about the issues that have been addressed in this determination. In the end, this required Frontline to obtain its own expert reports.
118 I make the following orders:
...
(2) Each party is to pay its own costs of the proceeding.
Claim for toilet roll holder and two guest towel rails!
(1) Neither the Notice of Appeal nor any of the appellant's submissions identify where this was claimed or otherwise considered and dealt with at the hearing;
(2) We have not been provided with a transcript of the hearing; and
(3) The decision does not identify a claim for a toilet roll holder and guest towel rails having been made as part of the application as filed or having been consider by the experts, even if just to assess the cost of them on an if found basis.
6 (2) If any party wishes to make an application for costs of the appeal, that party is to lodge with the Appeal registry and give to the other party any submissions on costs at the same time as their submissions in relation to the appeal.
(1) Leave to appeal refused.
(2) Appeal dismissed.
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.
Mavroudis
Frontline Building Group Pty Ltd [2025] NSWCATAP 317;