[2022] QPEC 19
General information, not legal advice.
Planning and Environment Court of Queensland
2022-06-10
Original judgment source is linked above.
"The architecture of the building is characterised by visible expressed floor levels and an overhanging roof.
The northern and southern façades do not have columns supporting the roof so the expression of the roof on corners has a generous cantilever form which contributes to the subtropical design character of the building. The roof cantilever on the top-level assists in reducing the overall bulk and scale of the building, casting a changing shadow on the walls below as the suns [sic] moves through the sky during the day.
The roof and the building below it have a generous 9 m setback where the vehicle driveway is located. ... This recess in the building form achieves two key outcomes. The length and overall bulk of the front façade is reduced.
In addition, the recess reduces the length of wall on the western boundary and opens up the pedestrian pathway where it approaches the street - providing a wider view in and out and a better connection to the street.
The proposed development is a well-considered piece of architecture with a range of elements that demonstrate design finesse that is respectful of its location within the local area and the relationship to and impact on neighbouring development.
The proposed development is considered a contemporary response to the beachside environment (including form and materials) which shall contribute to the varied, ordered and interesting skyline and reinforce the local identity and sense of place.
The proposed development achieves a high-quality urban design outcome which is functional, accessible, attractive and memorable along with being responsive to the subtropical environment and adjoining public spaces..."[4]
"From an architectural perspective, the general surrounding context for the subject land can be considered to extend from Mermaid Park to the north to Seabeach Avenue to the south, and from the beach front east of Hedges Avenue to the Gold Coast Highway to the west."[10]
"The residential building heights within the general surrounding context range from single storey to seven-storeys in height. Many multiple dwellings three-storeys and higher have a single basement for car parking within the footprint of the floors above, with the basement extending above ground by a metre approximately. This achieves natural ventilation and the basement does not count as a storey in the Planning Scheme. The raised ground floor creates an elevated building scale and expression. There is no real pattern of the location for the taller development through the area."[12]
"(2) The Planning Act, section 45 applies for the P&E Court's decision on the appeal as if-
(a) the P&E Court were the assessment manager for the development application; and
(b) the reference in subsection (8) of that section to when the assessment manager decides the application were a reference to when the P&E Court makes the decision."
"(3) To the extent the application involves development that requires impact assessment, and subject to section 62, the assessment manager, after carrying out the assessment, must decide-
(a) to approve all or part of the application; or
(b) to approve all or part of the application, but impose development conditions on the approval; or
(c) to refuse the application."
"[42] ...The decision-maker under s 60(3) of the Act is still required to carry out the impact assessment against the assessment benchmarks in the relevant planning scheme and can take into account any other relevant matter under s 45(5)(b). The starting point must generally be that compliance with the planning scheme is accorded the weight that is appropriate in the particular circumstances by virtue of it being the reflection of the public interest (and the extent of any non-compliance is also weighted according to the circumstances), in order to be considered and balanced by the decision-maker with any other relevant factors.
[43] In view of the fact that s 60(3) of the Act reflects a deliberate departure on the part of the Legislature from the two part test under s 326(1)(b) of the SPA, it is no longer appropriate to refer in terms of one aspect of the public interest "overriding" another aspect of the public interest before a development application that is non-compliant with the assessment benchmarks can be approved. The decision-maker may be balancing a number of factors to which consideration is permitted under s 45(5) of the Act in making the decision under s 60(3) of the Act where the factors in favour of approval (or approval subject to development conditions) have to be balanced with the factors in favour of refusal of the application. The weight given to each of the factors is a matter for the decision-maker in the circumstances..."[33]
"[77] ...The change in the decision-making regime has not affected the fundamental nature of a planning scheme as the reflection of the public interest in the appropriate development of land."[34]
"This City Plan represents a major shift from development on the city's fringe to redevelopment of urban centres and key inner-city neighbourhoods ...
The City Plan supports greater development intensity and smaller lot sizes in the city's well-serviced and highly urbanised areas while requiring lower development intensities and larger lot sizes in areas where services and infrastructure are not as advanced ..."[38]
"... Growth and development will be concentrated in an integrated network of well-serviced urban places - places with good access to public transport, services and infrastructure assets, or places where improvements to public transport provide a catalyst for mixed use development and high density living ...
Mixed use centres and specialist centres, urban neighbourhoods and the light rail urban renewal area ... will be targeted for renewal and transformation ..."[39]
"(8) The Building height overlay map shows the building height pattern and desired future appearance for local areas within urban neighbourhoods. This map also shows areas where building heights change abruptly to achieve a deliberate and distinct contrast in built form within and between low, medium or high rise areas.
(9) Increases in building height up to a maximum of 50% above the Building height overlay map may occur in limited circumstances in urban neighbourhoods where all the following outcomes are satisfied:
(a) a reinforced local identity and sense of place;
(b) a well managed interface with, relationship to and impact on nearby development, including the reasonable amenity expectations of nearby residents;
(c) a varied, ordered and interesting local skyline;
(d) an excellent standard of appearance of the built form and street edge;
(e) housing choice and affordability;
(f) protection for important elements of local character or scenic amenity, including views from popular public outlooks to the city's significant natural features;
(g) deliberate and distinct built form contrast in locations where building heights change abruptly on the Building height overlay map; and
(h) the safe, secure and efficient functioning of the Gold Coast Airport or other aeronautical facilities.
Note: Where the Building height overlay map shows both storeys and metres, the lesser of the two shall apply, and any fraction which results from the calculations shall be rounded down to the nearest floor or partial floor."[40]
(1) The purpose of the Medium density residential zone code is to provide for a range and mix of dwelling types including Dwelling houses and Multiple dwellings supported by Community uses and small-scale services and facilities that cater for local residents.
(2) The purpose of the code will be achieved through the following overall outcomes:
(b) Housing is provided at a form, scale and intensity that is appropriate for the zone and each particular locality it is in where the following outcomes are satisfied:
(iv) delivery of a generous mix of housing form, sizes and affordability outcomes that meet housing needs (including housing needs of the future) for the locality;
(v) whether intended outcomes for building form/city form and desirable building height patterns are negatively impacted, including the likelihood of undesirable local development patterns to arise if the cumulative effects of the development are considered;
(vi) retention of important elements of neighbourhood character and amenity, and cultural heritage;
(vii) whether adjoining residential amenity is unreasonably impacted;
(d) Built form (excluding Dwelling houses on small lots) -
(i) has a building height that does not exceed that indicated on the Building height overlay map;..."[41]
(a) in metres, the vertical distance between the ground level and the highest point of the building roof (apex) or parapet at any point, but not including load-bearing antenna, aerial, chimney, flagpole or the like; or
(b) in storeys, the number of storeys above ground level; or
(c) in both metres and storeys, both (a) and (b) apply."[44]
"As a starting point, the absence of the adjoining residential neighbours on three of the four boundaries, and having a driveway as the primary interface on the only neighbouring residential lot to the east, greatly assists to avoid or mitigate impacts on residential amenity and adds to the sense of building separations, and breathing space around the building, to assist the form in sitting comfortably in its setting."[53]
"The proposal achieves a 7.6m distance to the neighbouring duplex (located to the west of the public throughfare link) and 5.4m to the adjoining three (3) storey units. The separation distances are larger than the typical building separation present in William Street, ensuring that the extent of the reduced roof setbacks will not impact on the existing amenity afforded to the adjoining residential properties."[54]
"It is acknowledged that the eclectic nature of the existing residential buildings within the general surrounding context, including the diversity in age, style, built form and materiality establishes a local identity and sense of place with a varied, ordered and interesting skyline."[55]
"the proposal contributes to a varied local skyline by providing a flatter roof that varies from the adjoining skillion and gable forms, contributes to order by maintaining a perceivable roofline of approximately 600-750mm below the overlay of 15m, and contributes to an interesting local skyline by adopting a cut-out at the streetscape ... and a vegetated rooftop interfacing with the park ..."[56]
[1] Exhibit JNT.003.004, para 28; Exhibit JNT.003.001, para 24.
[14] Ibid; Exhibit JNT.003.003, Fig 14 and Fig 19.
[20] Exhibit JNT.003.004, para 39 and Fig 3.
[29] Ibid s 45(5)(a)(ii).
[30] Planning Regulation 2017 (Qld), Schedule 24.
[32] Planning Act 2016 (Qld) s 45(5)(b).
[35] [2014] QCA 147 at [52].
[37] Exhibit GCC.002.001, s 1.4(1)(b), p 4.
Matthew Lawrence
The City of Gold Coast & Anor [2022] QPEC 19