Application for review under s 81(b) Planning And Environment Act 1987 against decision to refuse an extension of time of a permit requested under s 69(1), permit for subdivision, request for extension of time to certify plan, first extension requested, Mildura Planning Scheme, Farming Zone, whether sufficient grounds for extension, lack of funds due to drought, change of zone and planning policies, whether there are new circumstances to justify refusal of permit, consideration of tests under Kantor v Murrundindi Shire Council.
Mapkams Pty Ltd v Mildura RCC [2008] VCAT 2609
The decision of the responsible authority affirmed. No extension of permit no P05/519 issued 19 July 2006 is granted.
Request for extension of time under Section 81(b) Planning and Environment Act 1987 in which to certify the time to certify a plan of subdivision.
3 lot subdivision (re-subdivision to create 2 residential allotments).
The existing lots are Lot 1 (7.173 ha), Lot 2 (4.046 ha) and Lot 3 (4.046 ha) containing existing dwelling and shed.
The proposed lots are Lot 1(400 m²) vacant, Lot 2 (14.496 ha) containing existing dwelling and vines, and Lot 3 (4000m²) vacant.
Clauses 17.05, 21, 22.06, 35.05, 35.05-3, 35.07 Schedule, 35.07-3
The land is located on the south eastern side of Sandilong Avenue between Eleventh and fourteenth Streets, Irymple, comprising 3 titles with a total area of 14.265 ha. used for horticultural purposes (vineyard), associated dwellings and shed
12 Fitzroy Street St Kilda Pty Ltd v Port Phillip CC [1993] 3 VPR 103
Kantor v Murrindindi SC [1997] 18 AATR 285;
Freeman and Freeman Land Surveyors (for Pasquale & Sylvana Cufari) v Mildura RCC [2005] VCAT 1979 (22 September 2005);
Mifsud v Melton SC [2006] VCAT 1488 (26 July 1488);
Central Portland Hotel Pty Ltd v Glenelg SC [2006] VCAT 1205 (19 June 2006);
Roger C Jaques v East Gippsland SC [2007] VCAT 1466 (9 August 2007);
Roy Costa & Associates v Mildura RCC [2007] VCAT 2106 (23 October 2007);
Roy Costa & Associates v Mildura RCC [2008] VCAT 801 (12 May 2008);
Each lot must be at least the area specified for the land in a schedule to this zone. If no area is specified, each lot must be at least 40 hectares.
A permit may be granted to create smaller lots if any of the following apply:
It is a different situation altogether if a refusal would be the inevitable result of a new application. The purpose of limiting the life of permits is so that they will not survive unacted upon until they are revived after they become inappropriate due to changes in circumstances. Such changes might be changes in the nature of the land and locality so that the proposal is no longer appropriate. The other sorts of changes referred to in the authorities is where planning policies have changed, or planning scheme provisions have changed so that the proposal has become undesirable or contrary to current policies, or indeed prohibited.
The subdivision is the re-subdivision of existing lots. The number of lots must not be increased and all lots must be at least 0.4 hectares.
The subdivision is the re-subdivision of existing lots and the number of lots is not increased. An agreement under Section 173 of the Act must be entered into with the owner of each lot created which ensures that the land may not be further subdivided so as to increase the number of lots. The agreement must be registered on title.
"...I consider that the various changes to the planning framework since 2001 would raise such new considerations (notably the fact that the subject land now lies within the UGB rather than outside or it.)
A - Proposed trade-off prevents a loss of land to productive horticulture
New residential lots will result in the loss of 0.4ha of land from horticultural use and production, and would require the removal of vines.
B - Proposed trade-off avoids any new loss of land to productive horticulture
New residential lots will result in the loss of 0.4ha of land from horticultural use and production, and would require the removal of vines.
C - Proposed trade-off results in a lot suitable for productive horticulture without a dwelling or the possibility that a dwelling can be constructed
The larger horticultural allotment will contain the existing dwelling on the land.
All lots in the subdivision will have the potential to contain a dwelling.
D - Proposed trade-off results in a lot suitable for productive horticulture greater than 12 hectares in area
The proposed re-alignment will result in a productive horticultural lot of 14.465ha in area.
E - Proposed trade-off results in a lot suitable for productive horticulture greater in area than any existing lot
The proposed re-alignment will result in a productive horticultural lot to14.465ha (increased from 7.139ha).
F - Proposed trade-off avoids the use of land for purposes unrelated to productive horticulture
The proposal will result in the creation of two new rural residential lots, each with an area of 0.4ha, unrelated to use of the land for horticulture.
[1] Application for review under s 81(b) Planning and Environment Act 1987 (PE Act) against refusal extension of time under a permit.
[4] [2006] VCAT 1205 (19 June 2006)
[5] [2006] VCAT 1488 (26 July 1488)
[6] For a discussion of this type of application see Waraglen Developments Pty Ltd v Maroondah CC [2008] VCAT 1608 (31 July 2008)
[9] [2006] VCAT 1488 (26 July 1488) @ [39]
[10] [2005] VCAT 1979 (22 September 2005)