[2025] NSWCATCD 176
General information, not legal advice.
NCAT Consumer and Commercial
2025-10-30
Original judgment source is linked above.
The applicants were the legal owners of more than 4 dwellings
(1) Their legal interest, as tenants in common, in the land known as Lot 2, 3 and 4 in DP 1156105, between 30 May 2014 and 20 April 2018;
(2) Their legal interest, as tenants in common, in the land known as Lot 101, 102, 103, 104, 105 and 106 in DP 1208824, between 20 April 2018 and 4 June 2018;
(3) Their legal interest in the 8 dwellings on 1 December 2017 when the OC was issued;
(4) Their legal interest in the 8 dwellings on 20 April 2018 when the subdivision was registered.
Does ownership as tenants in common yield to the intention of the parties?
"in order for the Owners Corporation to prove that GEO was a developer, it had to prove that, at the time of the construction of the townhouses, GEO was to be the owner of at least four of them."
"GEO owned the land on which the townhouses were built. It entered into contracts with Rubikcon to build the townhouses and entered into contracts for the sale of those townhouses. In the normal course of events, it is to be expected that GEO would own the townhouses up until the time of completion and that completion would not occur until the townhouses were ready for occupation. That is so whether GEO entered into contracts for the sale of the townhouses off the plan or not. In its submissions to the referee, GEO confused entry into a contract for sale and completion of that sale.
GEO did not seek to lead any evidence to suggest that some different arrangement applied in this case, although it was clearly in a position to do so if there was. Absent that evidence, the appropriate conclusion to draw is that, consistently with what is to be expected, GEO would retain ownership of the townhouses until completion and completion would occur after the townhouses were ready for occupation. It follows that the townhouses would, on their completion and until they were transferred to the buyers, be owned by GEO. For that reason, GEO was a developer within the meaning of s 3A." (emphasis added)
"It was never the intention that the respondent would own any of those strata home units after the strata plan had been registered. We are therefore of the opinion that the respondent was not a developer within the meaning of s3A of the Act." (emphasis added)
"That is, TCS was relevantly a legal and beneficial co-owner (as tenants in common) of the land on which the development occurred, and following completion of the build ... became the beneficial owner of only the commercial portion. In these circumstances the Appeal Panel held that TCS was never intended to be the owner of the residential lots for the purpose of section 3A."
(1) The application is to be filed and served, supported by evidence and submissions not exceeding 3 pages in length within 14 days of the date of these orders;
(2) Evidence and submissions in response to the costs application not exceeding 3 pages in length are to be filed and served within 28 days of the date of these orders;
(3) Any material in reply is to be filed and served within 35 days of the date of these orders;
(4) In their submissions the parties are to address whether a hearing on costs should be dispensed with, and costs determined on the papers.
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.
(1) The Owners - Strata Plan No 79707 v Trilogy Capital Services Pty Ltd [2015] NSWCATAP 171 ("Trilogy");
(2) The Owners - Strata Plan No 68372 v Allianz Australia Insurance Limited [2014] NSWSC 1807 ("Allianz");
(3) The Owners - Strata Plan 81837 v Multiplex Hurstville Pty Ltd [2018] NSWSC 1488 ("Multiplex").