1. This approval is for the above uses in accordance with Schedule A - Level of Assessment Tables and Codes, and the Development Structure Plan (Plan of Development) as amended by the following:
a) The fisheries buffer in the southern and western edges of the development is to be increased in width to protect several regional ecosystems (8.2.2 and the mosaic 8.2.9/8.2.2) all listed as "of concern" under the Vegetation Management Act to include all the large patches of dry rainforest.
b) The proposed 5 storey development in the Tourist Hub to be not more than 3 storeys in height.
c) THAT the residential density is not to exceed 10 dwellings per hectare.
2. The currency period for the Preliminary Approval shall be ten (10) years starting the day the approval takes effect. The currency period is conditional upon completion of the Hotel in the Tourist Hub by the end of 2008. If the Hotel development is not completed by 2008, this preliminary approval shall lapse at that time.
3. Water Supply and Sewerage Headworks Contributions
Where an application for any development listed in the approved Plan of Development is made, the Applicant must pay all contributions required by:-
a) Council's Water and Sewerage Headworks Policies; or
b) Council's Infrastructure Charges Regime; or
c) Any infrastructure charges agreement between the Applicant and Council in existence at the time of lodgement of the relevant application.
4. Parkland
Parkland shall be provided generally in accordance with the Plan of Development and Council's Planning Instruments current at the time of an application for a Development Permit for any part of the proposal.
5. Electricity/Telephone Services
It shall be satisfactorily demonstrated that electricity and telephone services can be provided to the subject land.
6. Bikeways/Footpaths
Bikeways and Footpaths shall be provided generally in accordance with the Plan of Development, and Council's Planning instruments current at the time of application for a Development Permit for any part of the proposal.
7. Within six (6) months starting from the day of the approval takes effect and prior to any development commencing, submit for Council approval an Environmental Management Plan (EMP) for the whole of the subject land. Such EMP shall contain plans outlining strategies, actions, timelines, performance indicators, monitoring regimes, reporting mechanisms and remedial action procedures in the following areas:-
• Stormwater management and erosion and sediment control,
• Water quality and water quality monitoring,
• Vegetation management,
• Fauna management;
• Weed management; and
• Turtle management plan.
The assessment of the above EMP shall be undertaken by Council utilising independent professional advice, and any costs incurred by Council in relation to that advice shall be borne by the Applicant.
8. External Roadworks
a) Duplicate Ron Searle Drive between the roundabouts at Harbour Road and the Marina. The Marina roundabout is to be upgraded in accordance with the approval design.
b) Upgrade the roadway south of the Marina roundabout to a four lane road to the most southern entry to Mulherin Park/Surf Life Savers and then transitioned over a 50 metre distance to a two lane road.
c) Provision of a contribution and/or works towards the State Road Network as determined in consultation with the Council and Department of main Roads and recorded in an infrastructure agreement.
9. Provide an Evacuation Centre building to hold up to 3000 persons and which shall have a minimum floor level of Q500 immunity.
10. The ground level of the development area shall be raised to the Q100 level. A lesser ground level may be acceptable if a bund wall is provided within the development area to provide Q100 immunity. Filling is to be minimised in the development area.
11. Comply with the requirements of the Department of Natural Resources and Mines for Vegetation Management as detailed in their letter of the 27th May, 2003.
12. The minimum floor levels for the development shall be set at 300mm above Q100 level.