[2025] QCAT 191
General information, not legal advice.
Queensland Civil and Administrative Tribunal
2025-05-21
Original judgment source is linked above.
CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - REMUNERATION - EXTRAS AND ALTERATIONS - where a contractor performed work said not to be part of the contract - where the contractor did not put any variations as allegedly directed into writing nor have any written agreement with the owners to pay for such variations - where the contractor made a final claim under the contract and was paid in full under the contract, and only thereafter made a claim for payment of the alleged variations
Queensland Building and Construction Commission Regulations 2018 (Qld), s 54
Boys v Imperial Homes [2024] QCATA 35
Munro v Camdun Pty Ltd t/as Asset Carpentry & Building Supplies [2024] QCAT 452
MWB Everton Park Pty Ltd as trustee for MWB Everton Park Unit Trust v Devcon Building Co Pty Ltd [2024] QCA 94
Neil v Nott [1994] HCA 23; (1994) 68 ALJR 509
Peak Construction (Liverpool) Ltd v McKinney Foundation Ltd (1970) 1 BLR 114
Penfold v Firkn & Balvius [2023] QCATA 11
Thallon Mole Group Pty Ltd v Morton [2022] QDC 224
(a) A reduction of the claim for liquidated damages to $5,150.00 plus interest thereon;
(b) The claim for restitution of the 'credits' quantified at $3,771.95 but without any claim for interest thereon; and
(c) An abandonment of the claim for cost of rectification.
(e) "Completion Period" means the Completion Period stated in Schedule Item 6
(bb) "Starting Date" means whichever of the following dates occurs the latest:
(i) the Starting Date stated in Schedule Item 5; or
(ii) the day which is 10 business days after the issue of the plans duly approved by the Assessing Certifier; or
(iii) the day which is 10 business days after the Owner has satisfied its obligations under Condition 5.1.
(v) "Practical Completion" means the date upon which the Works are completed in accordance with the requirements of this Contract, including Condition 3 and Condition 28, apart from minor omissions or minor defects.
- Payment
19.1 The Owner must pay the Contractor the Contract Price for the Works calculated and adjusted as provided by this Contract in accordance with the following provisions:
...
(b) The Contractor is entitled to claim a Progress Payment when the Contract has achieved completion of each of the stages set out in Schedule Item 8A or 8B which claim shall consist of the percentage of the Contract Price applicable to that stage as set out in Schedule Item 8A or 8B, subject to the following adjustments:
(i) an adjustment for any Prime Cost Item ... such adjustment being an increase or decrease to the relevant stage payment ...
(ii) an adjustment for the value of any Provisional Sum item completion to that stage and not included in a previous Progress Payment, such adjustment being an increase or decrease to the relevant stage payment ...
(iii) an increase to the relevant stage payment in respect to an amount payable under a Variation Document where the work the subject of the variation and has been completed and for which payment has not previously been made; and
(iv) a decrease in the relevant stage payment in respect to a variation which reduces the Contract Price.
...
Variations
21.1 The work under this Contract may be varied by way of an increase, decrease, or substitution of work under this Contract agreed between the Contractor and the Owner provided that, before work commenced and before any additional payment is required, the details of the variation are put in writing in a Variation Document agreed in writing by both parties.
Time for Practical Completion
The Contractor must achieve Practical Completion of the Works by the Date for Practical Completion stated in or calculated in accordance with Schedule Item 7 or any extended date under Condition 23.
Extension of time
23.1 ... the Contractor may only claim and is entitled to a reasonable extension of the Date for Practical Completion if:
(a) ...
(b) the claim is made to the Owner in writing ... with the particulars, including the cause of the delay and the extension of the Date for Practical Completion claimed, completed; and
(c) the claim is given to the Owner within 10 business days of the earlier of the Contractor become aware of the cause and extent of the delay and when the Contractor reasonable ought to have become aware of the cause and extent of the delay; and
(d) ...
- Liquidated Damages
24.1 If the Contractor fails to achieve Practical Completion of the Works by the Date for Practical Completion, then the Contractor must pay to the Owner liquidated damages calculated at the rate provided in Schedule Item 10.
24.2 If Schedule Item 10 is left blank, a default amount of $50 per day shall be deemed to supply.
24.3 Liquidated damages may only be deducted by the Owner from the amount payable to the Contract in respect of the Practical Completion Stage. If the Owner's entitlement to liquidated damages exceeds the amount payable to the Contractor for the Practical Completion Stage, the excess may be recovered by the Owner as a debt due to the Owner by the Contractor.
Practical Completion
...
28.2 ... if the Contractor produces to the Owner satisfactory written evidence that all relevant inspections and approvals required under the Sustainable Planning Act 2009 and the Building Act 1975 ... the Contractor must:
...
(b) give the Owner a completed and signed QBCC Form 7 - Certificate of Practical Completion stating that as the Date of Practical Completion; and
(c) hand over the Works to the Owner.
Schedule
Item 6 Completion Period 105 days
Item 7 Date for Practical Completion[3] Date ___ / ___ / __
Completion Period of ____ days (see Schedule Item 6) from the Starting Date of the date on which the work under this Contract is commenced, whichever is the earlier.
Item 10 Liquidated Damages $ ____ per day for each calendar day if delay in achieving Practical Completion
(Note to Owner and Contractor) If this space is left blank, a default amount of $50/day shall apply
(a) List of asserted extras (separately detailed therein) $85,457.90
(b) Building & P.C. Credits
(c) Total $81,685.95
(a) $85,070.89 as "a debt due and owing" said to be for the "Outstanding Variations and Prime Cost Items";
(b) $81,685.95 as payment of "the Variation Invoice";
(c) Interest said to be "pursuant to clause 20.1 of the Contract" from 13 January 2021 to the date of payment, also quantified therein as being $13,517.35 from 13 January 2021 to 8 September 2022;
(d) Costs.
(a) payment of $7,050 as liquidated damages for late completion, as a stand-alone claim or alternatively a set-off against any amount this Tribunal may find is payable to Jokovich as part of its claim;
(b) restitution of what they say are 'credits' for prime cost materials not supplied under the contract, but without specifying a quantum of such, also as a stand-alone claim or alternatively a set-off;[9] and
(c) cost of rectification of defective work, once again without specifying a quantum of such, also as a stand-alone claim or alternatively a set-off.
(a) Is Jokovich entitled to its claim for payment of variations under the Contract in the absence of any written agreement for same?[10]
(b) Are the Garland's entitled to restitution for prime cost materials not supplied under the Contract?; and
(c) Is Jokovich liable to the Garlands for liquidated damages under the Contract?
... We don't do written variations with people we know, as we feel that clients feel that we don't trust them. ...
Relationship with the Garlands
I had known the Garlands as friends for a number of years prior to entering into the Contract. During the development of our friendship, and throughout the construction works, I believe that we had a great level of mutual trust between us. The factors surrounding the foundation of this relationship and mutual trust are as follows:
...
- Most (if not all) of the variations under the Contract were given and approved by Lucy to me verbally on site or over the phone, as I trusted the Garlands.
(c) In relation to the conversation that occurred when the Garlands were due to move in:
(i) the Garlands never indicated to me that they wanted to move into the property when they did;
(ii) I was not aware the Garlands had moved into the property until I returned to the site on Monday 29 October 2020 (sic). The Garlands moved in over the weekend when no one was around. This caused issues with contractors completed (sic) the remaining works and caused further delays; and
(iii) Any initial discussion between myself and Lucy was relating to the use of the house to store boxes in the garage only and not moving into the house while it was incomplete.
Mr Randall Lucy Garland asked you at various times to be given variations in writing.
Mr Jokovich Yes.
Mr Randall You did not provide them.
Mr Jokovich Yes.
Mr Randall You knew you were supposed to put them in writing.
Mr Jokovich Yes.
Mr Randall Under contract and the QBCC Act you need to have put them in writing.
Mr Jokovich Yes.
Mr Randall You say in your statement that you were not required to put in writing - you accept that this is incorrect.
Mr Jokovich Yes - it is incorrect.
Mr Randall In entering into the contract you knew the Garlands had to pay as per this clause.
Mr Jokovich Yes.
Mr Randall It sets out the process.
Mr Jokovich Yes.
Mr Randall This is the only clause in the contract that gives your company a right to payment.
Mr Jokovich Yes.
Mr Randall You put the amounts of each payment in Item 8A of the Schedule.
Mr Jokovich Yes.
Mr Randall You knew that there were six payments only including the deposit.
Mr Jokovich Yes.
Mr Randall You knew that under Clause 19.1 you were allowed to adjust the amounts claimed.
Mr Jokovich We leave it until the end to make the adjustments.
Me When is the end?
Mr Jokovich We wait until all the invoices from the suppliers and subcontractors have been received.
Me This could be after practical completion and the owner has moved in.
Mr Jokovich Yes.
Mr Randall The end is the practical completion stage.
Mr Jokovich Yes.
Mr Randall After the practical completion stage your company had no contractual right to claim further payment.
Mr Jokovich Yes.
Variations to the Contract
As noted above, barring one exception, at no stage did the Applicant provide us with, or did we agree to, written variation documents setting out the nature of the variations alleged by the Applicant ....
If the Applicant had provided us with written variation documents setting out the nature and additional cost of the variations alleged, we would have carefully considered those variations and the additional expense to which the variations would put us and would not have proceeded with the variations ... .
Liquidated Damages
We have not received nor withheld any sum associated with the liquidated damages payment by the Applicant under the Contract.
Lucy Garland got us to price the retaining wall, plus other works for her when completing her pool.
Once we showed her the pricing to sign a variation to the works, she said it was too expensive and she was going to get it done herself.
Mrs Jokovich You agree with the content of that e-mail.
Ms Garland Yes.
Mrs Jokovich Did you ask Mark to construct the rear retaining wall ?
Ms Garland Yes.
Mrs Jokovich You said it had to be done quickly because the pool was to be installed next week.
Ms Garland No - I do not believe there was the need for a rush.
Mrs Jokovich You agree this was not part of the contract.
Ms Garland Yes.
Mrs Jokovich You agreed to have the work done on a cost plus 10% arrangement.
Ms Garland I don't remember that.
Mrs Jokovich How do you think it would be costed?
Ms Garland We had discussions as to options discussing materials and suppliers. He gave me an estimate of $7,000 to $9,000 for fencing and retaining walls on the block. Ultimately I said go ahead.
A frequent consequence of self‑representation is that the Court must assume the burden of endeavouring to ascertain the rights of the parties which are obfuscated by their own advocacy.
From on or about 6 January 2020, the Respondents requested for variation additional items to be added to the contract (the "Variations") referred to in paragraphs 3, 4, and 5 herein.
Rule 1. An item specifically provided for in the contract is not an "extra."
Rule 2. When the [contractor] supplied material of a better quality than the minimum quality necessary for the fulfilment of the contract, without any instructions, express or implied, from the [owner] to do so, he is not entitled to charge the extra cost as an "extra."
Rule 3. When the [contractor] did work or supplied materials not called for by the contract ... without instructions, express or implied, from the [owner] or the consent of the [owner], he is not entitled to charge this additional work or materials as an "extra." ...
Rule 4. When the [contractor] did work or supplied materials not called for by the contract on the instructions, express or implied, of the [owner], he is entitled to charge for additional work or materials as an "extra."
(a) the back retaining wall was not part of the Contract;
(b) she requested Mr Mark Jokovich to construct it;
(c) she was given an estimate by him for the work at between $7,000 and $9,000; and
(d) she directed Mr Jokovich to go ahead.
The Respondents are also entitled to credits of $3,771.95 which were agreed by the Applicant.[38]
(a) Jokovich sought an order for payment of interest under the Contract;[39]
(b) the Garlands did not seek any relief in terms of interest.
(a) As for the counterapplication filed, it being the claim which Jokovich came to the hearing to meet, there was no claim for interest expressed. For this sole reason she should now not be permitted to raise such a claim by way of closing argument; and
(b) Moreover, under the Contract the Garlands had the entitlement to deduct liquidated damages from the practical completion payment,[41] yet they did not do so. This was either a conscious decision made at that time thus leaving it to be dealt with by way of recovery action at a later time should they choose to pursue same, or because they did not know that they could do so. Either way, given the entitlement that they were seized of then, it is entirely at odds with that entitlement and the reason for not exercising it then to now seek a payment of interest within this proceeding from the date Ms Garland says the liquidated damages was first payable.
(c) For these reasons, my finding was that there was no interest payable by Jokovich to the Garlands.
(a) from the day which was 5 business days after the Garlands presented their defence in this proceeding,[42] such being 3 November 2022 which in turn made the due date for payment 10 November 2022; such being because the Garlands should have realised at that point in time the concession / admission that was necessary and so then promptly made payment to Jokovich;
(b) up until the first day of the hearing, namely 13 November 2025, being when at the latest the Garlands should have paid it as a result of this proceeding.[43]
As a general proposition, I observe that the two sets of documents (one sent 30 June 2023 and the other sent 17 July 2023), show a confusion on the part of the builder between the concept of a payment claim under the BIFA and a progress claim under the contract. As the case law referred to at [7] shows, if a builder wishes to take advantage of the provisions for statutory payment claims under the BIFA, it is incumbent on the builder to set up an accounting system which conforms to that Act, with professional advice if necessary.
(a) The Garlands should pay to Jokovich $ 9,408.83, being the aggregate of:
(i) $833.30 as conceded in terms of allowance for insurance and a front entry door adjustment;
(ii) $7,000.00 for construction of the Back Retaining Wall; and
(iii) $1,575.53 as interest on the aggregate of these two amounts.
(b) Jokovich should pay to the Garlands $8,871.95, being the aggregate of:
(i) $5,100.00 as liquidated damages for late completion; and
(ii) $3,771.95 as the restitution credit.
[1] This information is drawn from the documentary evidence as it was before this Tribunal. The relevant Exhibit received during the hearing is footnoted.
[3] This is at appears in the Contract document - the date and completion period being left blank.
[5] There is inconsistency within the Jokovich's filed statement as to the date of completion. In Mr Mark Jokovich's first statement, he gives the date of 27 November 2020 - Ex 6 para 13. In his second statement he gives the date of 6 November 2020 subject only to minor works remaining - Ex 7 para 13(d). In Mrs Sheree Jokovich's statement, his wife and co-director, she asserts that the 'Final Building Certificate' was received and e-mail to the Garlands on 18 November 2020 - Ex 1 para 19. Ms Garland gives the date of 27 November 2020 - Ex 10 para 18. In Ms Garland's second statement she says she received an e-mail from the Jokovich's on 30 November 2020 with a 'Form 21 Final Inspection Certificate', a copy of which is annexed thereto as LG-2 - Ex 11 para 7. That certificate is dated 27 Novembe 2020. Given the certificate was in evidence and unchallenged I proceeded on the basis that this was the date of the Final Certificate.
[8] The statements given by Mr and Mrs Jokovich are silent on the issuing of any written agreement recording the variations. In her evidence Ms Garland states that "barring one exception, at no stage did the Applicant provide us with, or did we agree to, written variation documents" - Ex 10 para 31. She does not however identify that one exception. In his second statement, given in response to Ms Garland's statement, he did not deny this as a fact - Ex 7 para 20, nor did he identify that exception.
[9] During the hearing Ms Garland's Counsel informed me that the 'credits' to which this part of the counterclaim referred was that which were stated in the invoice Jokovich sent to the Garlands when it first claimed payment for variations. That credit is shown thereon as $3,771.95.
[10] I pause here to observe that the manner in which Jokovich presented its claim was one as being entirely as 'variations' to the Contract, notwithstanding that on one reading some of it was detailed as being the difference between a prime cost / provisional sum allowance and that ultimately expended. But, to the extent any part of it might have been the latter, Jokovich did not present its evidence in a manner which supported the claim as merely the adjustment, instead presenting its evidence as being one seemingly in support of a variation claim.
[12] Even though this Tribunal is not bound by the rules of evidence, and so it is permissible for hearsay evidence to be presented, its probative value is limited at best. In the present circumstances the nature of the evidence was such that I formed the view it had no probative value and thus was appropriate for it to be struck out. These parts were para's 8, 10 to 18, 21, 22, and 24. The paragraphs were not numbered in the written document, these paragraph numbers being as counted with paragraph 1 being the first paragraph in the document after the words 'STATEMENT OF SHEREE JOKOVICH'.
[14] Ex 5. The struck out paragraphs are - that on page 2 starting with the words "Lucy Garland would often attend site ..." up to and ending with the words " nature of these meetings", leaving the last part of the last line starting with the words "however conversations with Nicholas ..." remaining; and on page 3 being the entirety of the second last paragraph thereon starting with the words "It is very important to note ...." ending with the words " ... dishonourable and disgusting".
[17] Ex 7 para 24. The underlining emphasis is as it appears in the original. There is an error in this statement as to the date, the Monday in October 2020 to which he refers being 26 October.
[18] During the hearing, this document was marked for identification and recorded as 'MFI - I'.
[19] The words stated here as attributed to individual persons is not taken from a transcript and so is not to be read as being verbatim. It is as per the notes I took during the hearing. Wherever similar references are made in these reasons the same applies.
[28] MFI 'E' para's 64 to 66, supplemented with oral submissions.
[30] Penfold v Firkn & Balvius [2023] QCATA 11 at [37] per Judicial Member Forrest SC.
[31] [1994] HCA 23; (1994) 68 ALJR 509, 510.
[32] Annexure A to the Application for domestic building dispute' - para 7. See Document MFI 'A'. The reference to 'paragraphs 3, 4, and 5' therein is to the earlier paragraphs which described the Contract.
[33] Chittick v Taylor (1954) 12 WWR (NS) 653 per Egbert J at [6]-[9], as recorded in The Laws of Australia - Thomson Reuters Westlaw at TLA [8.3.300].
[35] This is so even though I found Jokovich had an entitlement to be paid for the Back Retaining Wall.
[36] Such as an application of the 'prevention principle' which has its foundations in the English decision of Peak Construction (Liverpool) Ltd v McKinney Foundation Ltd (1970) 1 BLR 114. This conclusion and the reasoning that led to it is a manifestation of that burden cast upon this Tribunal by way of that laid down by the High Court in Neill v Nott to which I referred earlier herein.
[37] I pause here to note that this is almost the same amount Mr Randall submitted I should find as being payable, however his method of calculation to get to that date was different to mine which I calculated on the basis of what I read as being in the Contract terms.
[38] Document MFI 'D' Annexure A para 11.
[39] See document MFI 'A' Annexure A para 137.C.
[40] See document MFI 'E' para's 65 and 66.
[42] I allow that 5 business days for payment being such consistent with the period for payment under Clause 19.1(g) of the Contract terms. The period for payment arising because of this period satisfies the requirement of s 54(2) of the Queensland Building and Construction Commission Regulation 2018 (Qld).
[43] Such an approach to calculating interest is consistent with that submitted by Mr Randall for Ms Garland in his written closing submissions - see document MFI 'E' para 65.
[44] The rate is consistent with s 54(1)(c) of the Queensland Building and Construction Commission Regulation 2018 (Qld).
[45] MWB Everton Park Pty Ltd as trustee for MWB Everton Park Unit Trust v Devcon Building Co Pty Ltd [2024] QCA 94;[21].
MA & SK Jokovich Pty Ltd
Garland [2025] QCAT 191
(1994) 68 ALJR 509