[2025] NSWCATAP 320
General information, not legal advice.
NCAT Appeal Panel
2025-12-22
S de Jersey, Principal MemberR C Titterton OAM, Senior Member
Original judgment source is linked above.
(1) a refund of the monies paid in the sum of $53,170;
(2) damages for an increase in building costs of $66,464;
(3) lost rent of $27,940;
(4) interest and costs.
(1) the Notice of Appeal lodged on 30 June 2025;
(2) the respondent's Reply lodged 20 August 2025;
(3) the appellant's submissions lodged 1 October 2025 with a bundle of documents;
(4) the respondent's submissions lodged 23 October 2025;
(5) the appellant's submissions in reply lodged 30 October 2025.
(a) the decision of the Tribunal under appeal was not fair and equitable; or
(b) the decision of the Tribunal under appeal was against the weight of evidence; or
(c) significant new evidence has arisen (being evidence that was not reasonably available at the time the proceedings under appeal The appellant has submitted that the appeal only raises questions of law.
(1) Ground 1 - whether the Tribunal erred in determining the matter on a basis not pleaded or argued by the respondent, namely repudiation;
(2) Ground 2 - whether the Tribunal applied the correct legal test of repudiation under contract law, including whether it properly considered the appellant's conduct objectively evinced an intention not to be bound by the Building Contract or to perform it in a manner substantially inconsistent with its obligations;
(3) Ground 3 - whether the Tribunal erred in law by concluding that the issuance of the Price Increase Notice constituted repudiation, without determining whether it was merely a contractual variation, request or negotiation;
(4) Ground 4 - whether the Tribunal failed to consider whether a party's insistence on an incorrect interpretation of the Building Contract, if made bona fide, could constitute repudiation, including whether the respondent was willing to perform the Building Contract according to its true construction once determined;
(5) Ground 5 - whether the Tribunal failed to consider whether the respondent was "in clean hands" before finding that that party was entitled to accept any alleged repudiation;
(6) Ground 6 - whether the Tribunal failed to provide adequate reasons, or failed to allow the appellant full opportunity to make submissions for its finding of repudiation contrary to its obligations under s 62(3) of the NCAT Act amounting to a failure to accord procedural fairness or natural justice;
(7) Ground 7 - whether the Tribunal erred in law by misconstruing the Building Contract, including when it found that clause 15 did not permit price variations arising from increased costs of trades and suppliers, thus impacting the conclusion of the repudiation.
(1) repudiation was not pleaded in the respondent's default or termination notice nor in the pleadings;
(2) the respondent's case was put on the basis of substantial breach/unilateral variation, not repudiation;
(3) section 38(2) of the NCAT Act provides that the Tribunal may inquire into and inform itself on any matter in such manner as it thinks fit, but subject to rules of natural justice;
(4) whilst the Tribunal was entitled in principle to raise the question of repudiation, it was required to ensure that the appellant had proper notice and a genuine opportunity to be heard;
(5) the appellant was not on notice that repudiation (as distinct from breach) would be determinative; the Tribunal did not exercise its discretion under s 51 of the NCAT Act to adjourn and allow submissions;
(6) the appellant was not given a full opportunity to consider and make submissions on this issue which meant it was unfairly prejudiced amounting to a failure to accord natural justice;
(7) a finding of repudiation is of particular gravity and went to the continuation of the contract and directly determined the Tribunal's conclusion on the refund under Special Condition 3.6;
(8) yet the finding of repudiation was:
(a) not pleaded by the respondent,
(b) introduced for the first time during the hearing,
(c) unexpected and prejudicial to the appellant; and
(d) central to and directly influenced the Tribunal's decision;
(9) the appellant was deprived of procedural fairness because it neither knew the case it was required to meet until raised at the hearing nor had a fair opportunity to respond; this amounted to an error on a question of law.
(1) one of the breaches notified in the Notice of Termination was the "unilateral increase in price" which stated:
The Builder attempted to unilaterally increase the Contract Price beyond the agreed terms, in contravention of the Contact, without the Client's agreement.
(2) the term "repudiation" was not used in the Points of Claim, but the conduct pleaded and relied upon plainly constituted repudiation;
(3) the factual basis of repudiation was identified in the Notice of Termination;
(4) the appellant had ample opportunity to respond on the issue of repudiation both prior to and during the proceedings;
(5) repudiation was pleaded in substance or by implication in the Points of Claim as the conduct alleged clearly amounted to repudiation;
(6) repudiation was raised by the Senior Member at the hearing at Transcript (T) 24:25; at which time the appellant could have sought an adjournment or leave to file further submissions;
(7) the Tribunal was entitled to find repudiation regardless of whether the expression was used;
(8) the Tribunal was entitled to inform itself of any matter subject to natural justice;
(9) the issue was neither prejudicial nor unexpected and the appellant was afforded procedural fairness and had a fair opportunity to address the factual issue.
35 On 23 February 2024, the Builder served a Price Increase Notice. The Builder claimed a 5% plus GST increase in the Price pursuant to clause 3.2 of the Contract. It claimed in addition a 7% increase (GST inclusive) pursuant to clause 15 of the Contract.
...
40 The Builder stated in the Price Increase Notice that:
"As a building business that heavily relies upon and is therefore impacted by trades and materials, the trades and suppliers have significant powers to affect the building works (including their costs). Any increase in costs and charges introduced by our trades and suppliers will cause cost increases in the cost of the building works."
41 I do not accept that trades and suppliers come within the amended definition of statutory or other authority, because trades and suppliers do not have power to affect the works which are to be completed and handed over to the owner. I do not accept that the Builder is entitled to rely upon Clause 15 to adjust the price because of increases in its costs to complete the building works where those increased costs are not related to a statutory or other authority either introducing or increasing any tax, charge, levy or other regulation or introducing or increasing any requirement that affects the building works, causing the increase in the cost of the building works.
42 I therefore find that the Builder was not entitled to the price increase which it demanded in the Price Increase Notice. The service of that notice amounted to a repudiation of the Building Contract by the Builder.
43 The respondent submits that if the Tribunal finds that the attempt to increase the price was not in accordance with the contract, the attempt to increase the price was not a breach of a fundamental term of the contract. I do not accept this submission. I am satisfied that the price of the building works in a building contract is a fundamental term of that contract, and any attempt to increase the price beyond what is permitted in the contract is a breach of a fundamental term.
(emphasis added).
Unilateral Increase in Price
11 On 23 February 2024, I received an email from the Respondent, demanding that I either accept a price increase of 12.5%, or proceed with an alternative builder who requires a price increase of 10% ("Price Increase Email.
12 My own calculation based on the Building Contract shows that the price was subject to increases of 2.5% on 1 April 2023, 1 October 2023, and 1 April 2024, resulting in the Respondent being entitled to a cumulative price increase of 7.69% at most.
13 On or about 23 February 2024, I phoned Respondent's agent, Candy, from the Sales Agent's office. Candy said words to me to the effect:
Danni, leave it with me. The price increase is way too high. Let me talk to the builder about reducing it. I will come back to you.
14 I have received no further updates from the Respondent or their agent thereafter.
15 On 4 July 2024, I took the initiative to contact Hanging Liu (also known as "Clement"), who is the director of the Respondent company, via phone call. During our conversation, Clement said words to the effect:
We cannot carry out the building works anymore for the price stated in our contract. However, If you switch to a new builder, their price increase will be capped at 10%. They will also acknowledge the 10% Deposit you paid to us. The building work will be completed within 40 weeks after signing the contract. If it is not completed within that timeframe, compensation will be provided at a rate of $70 per day. Think about it. It's in your best interest to switch to the new builder.
16 On 5 July 2024, Clement emailed me and offered me a even more discounted contract price of $580,000 if I were to transfer to a new builder, and Clement asked me to choose a floor plan and confirm the price so the new builder could issue the new building contract.
17 On 7 July 2024, after careful consideration, I emailed Clement twice and requested a refund of the Deposit, instead of going with Clement's recommendations in entering into a new contract with another builder.
18 On 9 July 2024, Clement emailed me and refused to refund the deposit.
19 On 9 July 2024, I emailed Clement, requesting a full refund of $53,170.00 being the Deposit I paid.
20 On 11 July 2024, Clement replied and refused to refund the Deposit.
21 From July to August 2024, I engaged my former solicitor, Erica Yen-Hung Liu from GOH Lawyers (also known as "Erica"), to dispute the Price Increase Email. On 9 August 2024, Erica wrote to the Respondent, disputing the price increase and the Respondent's former solicitor replied.
22 In or about August 2024, there were without prejudice correspondence between the parties.
23 On 19 August 2024 and 22 August 2024, Erica followed up with two more emails but no further responses were received from or on behalf of the Respondent.
24 On 8 October 2024, I requested my current solicitor to send a Notice of Default to the Respondent and their solicitors.
This Notice of Default is issued pursuant to Clause 23.7 of the Contract due to the Builder's substantial breach of the Contract.
Details of Breach
Failure to Deliver Preliminary works
...
2. Unilateral Increase in Price: The Builder has attempted to increase the project price beyond the agreed contractual terms in the Contract, without any agreement from the Client, further constituting a breach.
3. Invitation to Seek Alternative Builder The Builder's suggestion that the Client engage another builder is inconsistent with the obligations under the contract and evinces the Builder's unwillingness or inability to perform the work at the price as agreed.
Our client does not accept the repudiation by the applicant.
Senior Member: But if I find that the builder was not entitled to ask for the price rise and I find that that was a repudiation by the builder, the owner has accepted that, why would I not then apply cl 3.6.1 and .2 and find that your client did not incur any costs pursuant to the preliminary work agreement?
Mr Chan: If NCAT finds that the building contact has been terminated.
Fairness is not an abstract concept. It is essentially practical. Whether one talks in terms of procedural fairness or natural justice, the concern of the law is to avoid practical injustice.
[180]....The term "procedural fairness" is synonymous with natural justice (the latter term is used in s 38(2) of the NCAT Act, which expressly requires the Tribunal to observe the rules of natural justice). Reflected in s 38(5)(c) of the NCAT Act, those rules require NCAT to take such measures as are reasonably practicable to "ensure that the parties have a reasonable opportunity to be heard or otherwise have their submissions considered in the proceedings".
[181] ....It is well established that NCAT must conduct a hearing that gives procedural fairness to all parties, even taking into account the less formal nature of Tribunal proceedings (s 38(4) and (5) of the NCAT Act). What is necessary and appropriate to ensure a fair hearing depends on the particular facts and statutory context, rules of procedural fairness being flexible and adaptable so as to be appropriate in a given case so as to avoid practical injustice: see eg SZBEL v Minister for Immigration and Multicultural and Indigenous Affairs (2006) 228 CLR 152; [2006] HCA 63 at [26], [29]. How the requirement for procedural fairness is satisfied will depend on the circumstances of the particular case and the particular parties.
[182] Section 38(5)(c), and the principles of procedural fairness imported by s 38(2) of the NCAT Act, require NCAT to give a party a reasonable opportunity, not every requested opportunity, to be heard or otherwise to have the party's submissions considered.
[183] A failure to accord procedural fairness must be material and be capable of affecting the decision: see eg Kudrynski at [49]; Nathanson v Minister for Home Affairs (2022) 276 CLR 80; [2022] HCA 26 at [1], [33]. The question whether any such error was material to the Tribunal's decision also raises a question of law.
[184] Here, if the Tribunal breached the requirements of procedural fairness by denying the appellant the right to ask relevant questions or make relevant submissions in the manner contended by him, the question then would then arise whether the Tribunal's error was material to its decision, in the sense that there is a realistic possibility that the decision that was made in fact could have been different if the error had not occurred: LPDT v Minister for Immigration, Citizenship, Migrant Services and Multicultural Affairs (2024) 280 CLR 321; [2024] HCA 12 (LPDT) at [6]- [7]. The High Court said in that case that "realistic" is used to distinguish the assessment of the possibility of a different outcome from one where the possibility is fanciful or improbable. Meeting the threshold of materiality "is not demanding or onerous": LPDT at [14].
(emphasis added)
(1) The appeal is allowed.
(2) Order 1 made on 2 June 2025 in proceedings 2024/00336738 is set aside.
(3) Proceedings 2024/00336738 are remitted for redetermination by the Tribunal.
I hereby certify that this is a true and accurate record of the reasons for decision of the Civil and Administrative Tribunal of New South Wales.