[2017] NSWLEC 37
Land and Environment Court (NSW)
2016-12-20
Moore J, Mr J
Original judgment source is linked above.
Solicitors: O'Brien Legal Pty Limited (Louisiana Properties Pty Ltd) Watson Mangioni (Hakea Holdings Pty Ltd) Carneys Lawyers (Caverstock Group Pty Limited) File Number(s): 261922 and 322081 of 2016 Publication restriction: No
TABLE OF CONTENTS Introduction The two proceedings Louisiana's development consent The ownership history The Hakea development consent The Hakea development consent APZ condition The link road The subdivision consent easements The power to require the APZ easement The requirement to link the Hakea land The constructed road The Supreme Court proceedings The nature of the Supreme Court proceedings The issues requiring determination in the Supreme Court proceedings The tests in s 88K of the Conveyancing Act The terms of the easement The boundary and area of the easement Valuation of the necessary compensation for the easement Giving effect to the APZ Louisiana's cross-claim in the Supreme Court proceedings The nature of Louisiana's cross-claim The issues requiring determination in Louisiana's cross-claim Was there a trespass? Ordinary damages Exemplary damages Injunctive relief arising out of the cross-claim The Land and Environment Court proceedings The nature of the Land and Environment Court proceedings The status of Louisiana's development consent Louisiana's approved access to the Wyong Health Campus Hakea's approved access route Summary of outcomes Directions
Introduction
The two proceedings
Louisiana's development consent
The ownership history
The Hakea development consent
The Hakea development consent APZ condition
The link road
The subdivision consent easements
The power to require the APZ easement
The requirement to link the Hakea land
The constructed road
The nature of the Supreme Court proceedings
The issues requiring determination in the Supreme Court proceedings
The legislative provision
The 3 May 2013 letter to the Council
Hakea's submissions in support of an easement
Louisiana's objections to an easement
Louisiana's first s 88K objection
Louisiana's second s 88K objection
Louisiana's third s 88K objection
Louisiana's fourth s 88K objection
Louisiana's fifth s 88K objection
Louisiana's sixth s 88K objection
Louisiana's seventh s 88K objection
Conclusion on s 88K matters
The terms of the easement
The boundary and area of the easement
Valuation of the necessary compensation for the easement
Mr Ireland's position on value
A "per tree" valuation?
Mr Pugsley's oral evidence
Valuation methodology
Time period for the APZ easement
The area to be in perpetuity
Conclusion on compensation
Giving effect to the APZ
Louisiana's cross-claim in the Supreme Court proceedings
The nature of Louisiana's cross-claim
The issues requiring determination in Louisiana's cross-claim
Was there a trespass?
The Right of Access
Ordinary damages
Exemplary damages
Injunctive relief arising out of the cross-claim
The nature of the Land and Environment Court proceedings
The status of Louisiana's development consent
Louisiana's approved access to the Wyong Health Campus
Hakea's approved access route
Summary of outcomes
Directions
Amendments 26 April 2017 - The word "not" had been omitted. The clause now reads "does not do so" at [197]. 06 September 2017 - The year "2005" was omitted prior to 'subdivision consent" at line 6 of [142]. DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 06 September 2017
(2010) 171 LGERA 286
(1920) 29 CLR 71