[2026] FCA 162
General information, not legal advice.
Federal Court of Australia
2026-02-26
Moshinsky J
Original judgment source is linked above.
Counsel for the Respondent, Time & Place Development Pty Ltd and Kapitol Group Pty Ltd:
Solicitor for the Respondent, Time & Place Development Pty Ltd and Kapitol Group Pty Ltd:
(a) the costs of Time & Place Development Pty Ltd (Time & Place Development) of the applicant's interlocutory application dated 27 October 2025 (including the informal application for joinder); and
(b) the costs of Kapitol Group Pty Ltd (Kapitol) of the applicant's interlocutory application dated 27 October 2025 (including the informal application for joinder),
(a) By 4.00 pm on 20 March 2026, each of Time & Place Development and Kapitol file and serve a Costs Summary in accordance with paragraphs 4.10 to 4.12 of the Court's Costs Practice Note (GPN-COSTS) (Practice Note).
(b) By 4.00 pm on 2 April 2026, the applicant file and serve a Costs Response in accordance with paragraphs 4.13 and 4.14 of the Practice Note.
(c) The amount of the lump sum of Time & Place Development's costs and Kapitol's costs be determined by a Registrar of the Court.
Note: Entry of orders is dealt with in Rule 39.32 of the Federal Court Rules 2011.
(a) Dr Lindrum contends that there should be no order as to costs in respect of the interlocutory applications.
(b) T&P contends that it should have its costs of the application for injunctive relief against it.
(c) The Non-Parties seek their costs of the interlocutory applications, to be determined on a lump sum basis.
(a) $1,469.50 (ex GST) for Time & Place Development; and
(b) $4,263.00 (ex GST) for Kapitol.
I certify that the preceding thirteen (13) numbered paragraphs are a true copy of the Reasons for Judgment of the Honourable Justice Moshinsky.
Lindrum
T&P Lindrum Pty Ltd