[2000] VSC 26
Supreme Court of Victoria
2000-02-18
Byrne J
Original judgment source is linked above.
CONTRACT - building contract - construction - claim by construction manager for progress payments - whether proprietor may raise cross-claim for defective work.
"... those professional services to be performed by the FRP [flood response program] Construction Manager specifically described in Part 2 of Annexure 'A'."
Annexure A sets out the services to be provided, presumably by all of the consultants. Part 1 sets out the services to be provided by the other consultant or consultants as project manager for the flood response program. Part 2 sets out services which are generally called construction management services. It seems that the services to be provided by Leighton to the Authority pursuant to the agreement are those of the construction manager as detailed in Part 2.
In consideration of the promise by the Consultant to perform the Services the Authority promises to pay to the Consultant the Fee and the Reimbursable Expenses in accordance with Annexure 'C' at the times and in the manner set out in this Agreement.
At or about the end of each payment period specified in Item 7 of the Schedule the Consultant will give to the Authority an account for the Services performed, and for reimbursable expenses incurred, during the period. Subject to any limitations contained in Annexure C, the Authority shall pay the full amount owing in respect of each account within 30 days of issue of the account.
The Authority has the right of set off in respect to any moneys which become due by the Consultant to the Authority at any time.
The Authority agrees that in addition to all other rights and remedies of the Consultant if the Authority fails to pay all moneys as and when due, the Consultant shall be entitled to recover interest at the rate specified in Item 8 of the Schedule on all moneys which are not so paid. If no rate is stated in the Schedule, it shall be at the current rate payable by the Consultant for overdraft on its current account.
If the Authority disputes the whole or any portion of the amount claimed in an account submitted by the Consultant, the Authority shall pay to the Consultant that amount which it does not dispute. At the same time the Authority shall notify the Consultant in writing of the reasons for disputing the amount in the account remaining outstanding.
If the parties are unable to reach agreement within 7 days of the Authority's notice, the dispute may be determined in accordance with Part 6 of this Agreement. If it is resolved that some or all of the amount in dispute ought properly to have been paid at the time it was first claimed, then the Authority shall pay the amount finally resolved.
At no time shall the Authority be obliged to make any payments into any trust account in respect to any disputed amount."
(1) Leighton was engaged to provide consultancy and supervisory services; it is not to produce a physical thing or a structure. This is a significant feature because the sum withheld is calculated by reference to the cost of rectifying the work of the direct contractors, a fact which may bear upon the entitlement of the Authority to abate the amount payable for the provision of the services.[5]
(2) The payments to which Leighton is entitled are to be calculated, not by reference to the product of its work, but by reference to the time and expenditure which it incurred.
(3) There is no independent certifier of Leighton's progress claims. Depending on one's point of view, this means that the Authority was at the mercy of Leighton or that Leighton was at the mercy of the Authority.[6]
(4) There is no retention or other security to be given by Leighton to protect the interests of the Authority in the case that it may have a claim in the future.
(5) As is common in building contracts, progress claims and payments are provisional only. Clause 3.2 expressly acknowledges that payment does not constitute a waiver of any right of action of the Authority against Leighton. The presence of such a clause has been thought to suggest that a deduction should not be made from a progress certificate issued under standard form contract AS2545-1993.[7]
(6) The agreement makes provision in cl. 3.4.2 for the Authority to recover the "extra costs" incurred by reason of any error or deficiency in the services provided by Leighton.
(7) The agreement obliges Leighton to indemnify the Authority against any liability to an employee of Leighton, against any liability for loss or damage to property or personal injury caused by any action or omission or default of Leighton.[8]
(6) The Authority may terminate or suspend the services to be provided by Leighton for any reason[9] or for default.[10] There is no equivalent right in Leighton to suspend work or to terminate the contract for the default of the Authority. It would seem, therefore, that, in the case of the non-payment of a claim, Leighton must nonetheless continue working unless the non-payment amounts to a repudiation and the contract is terminated by it as a result.
(7) Part 6 provides for dispute resolution by an expert, if the parties agree, or by arbitration. Either process contains relatively short time frames. The identity of the expert must be agreed within seven days and that of the arbitrator within one month. It would seem, therefore, that this dispute resolution process is not intended to await the completion of the work
(8) The agreement is expressed in relatively simple and informal terms. It does not follow any of the standard forms in use in the construction industry. It does not deal with a number of matters which are customarily contained in agreements of this type. This said, it does not bear the hallmarks of an agreement prepared by non-lawyers or by persons unskilled in the ways of the industry. Nevertheless, I will not give undue significance to omissions.
(9) I will not construe this contract contra proferentem against the Authority who, I am told, was responsible for its drafting. The parties may be taken to have negotiated the contract at arms length.
(10) There is no express term in the agreement as to the finality of claims or limiting the right of set off or excluding the substantive or procedural rights of the authority to raise a claim such as the present.
[3] See Building Act 1993, s.131
[5] See Hermcrest plc v G Percy Trentham Ltd (1991) 53 BLR 104
[6] See Acsim (Southern) Ltd v Danish Contracting and Development Co Ltd (1989) 47 BLR 59 at 72-3, per Ralph Gibson LJ.
[7] Algons Engineering Pty Ltd v Abigroup Contractors Pty Ltd (1997) 14 BCL 215 at 227, per Rolfe J
[11] Gilbert-Ash (Northern) Ltd v Modern Engineering Bristol Ltd [1974] AC 689 at 717-8, per Lord Diplock; at 722-3, per Lord Salmon; LU Simon Builders Pty Ltd v H.D. Fowles [1992] VicRp 60; [1992] 2 VR 189 at 191, per Smith J; Melbourne Glass Pty Ltd v Coby Constructions Pty Ltd (1997) 14 BCL 409 at 414-5, per Gillard J.
[16] See Merritt Cairns Constructions Pty Ltd v Wulguru Heights Pty Ltd [1995] QCA 273; [1995] 2 QdR 521.
[17] Algons Engineering Pty Ltd v Abigroup Contractors Pty Ltd (1997) 14 BCL 215 at 230, per Rolfe J.
[18] [1974] AC 689 at 717-9, per Lord Diplock; at 772-3, per Lord Salmon, and the cases referred to in footnote 11 above.
[19] Riverside Motors Pty Ltd v Abrahams [1945] VicLawRp 5; [1945] VLR 45 at 53-4, per O'Bryan, Martin JJ.
Leighton Contractors Pty Ltd
East Gippsland Catchment Management Authority [2000] VSC 26