[2018] VCAT 679
Victorian Civil and Administrative Tribunal
2018-05-04
Original judgment source is linked above.
Domestic building contract. Architect appointed as administrator under the contract. Builder issued claim for final payment (save for 50% of retention sum) and subsequently stopped works and issued proceedings for recovery of the payment. Finding that builder not entitled to payment of the claim because the architect had not certified the payment claim and no occupancy permit was issued at that time. Finding that builder breached contract and wrongfully suspended the works, resulting in delay of 130 weeks to completion of the works. Builder returned to complete works after the delay period. Practical completion certified, Occupancy Permit issued and architect certified payment to builder. Owner's claim for delay damages arising from breach of contract unsuccessful on the Baltic Shipping principle. Nominal damages awarded. Owner ordered to pay final sum certified by architect.
January 29, 30, February 1,2, 5, 6, 7, 9, 12, March 16, 2018
Leeda Projects Pty Ltd v Zeng (Building and Property) [2018] VCAT 679
Mr D. Deller of Counsel for the first 9 days; Mr Fah, solicitor, for the final day, 16 March 2018
As per our phone call conversation on Tuesday, I was to suggest the client [the owner] to make the 5th claim [payment] without the 2.5% retention money. Unfortunately the suggestion was not taken by the client and they insist all major problem solved [sic] before the 5th claim paid.
I'm therefore not able to represent the client to solve this issue about the payment time of the 5th claim. The client will contact you directly shortly.
Wrongfully and in breach of the contract, and in breach of the implied term to complete the works within a reasonable time...Leeda [the builder] suspended the works from on or about 27 August 2014 until 9 December 2016 and did not achieve practical completion until 25 May 2017.[11]
THE CONTRACT AND THE DOMESTIC BUILDING CONTRACTS ACT 1995
1. The applicant must, by not later than 4:00 p.m. Monday 5 September 2016, deliver to the respondent's lawyers such access cards, keys, security codes and other information or devices required to allow the respondent access to the subject premises, Lot S28, Level 87 Eureka Towers, 7 Riverside Quay, Southbank, Vic ("the apartment") and the relevant car park for the apartment ("the car park").
2. Subject to orders 2(a) and (b) below, the respondent may, for the purpose of inspection only, attend the apartment with her representative and consultants:
3. The applicant may access the car park without any requirement to provide any notification to the respondent.
IMPLIED TERM THAT WORKS MUST BE COMPLETED WITHIN A REASONABLE TIME
this contract contains everything the owner or the architect has agreed to with the contractor [builder] in relation to the matters it deals with ...
I accept that in the position where the contract says TBA for the date for practical completion that it needs to be therefore implied that there will be completion within a reasonable time...[23]
Towards the middle of July 2014, the Project was, in my opinion, practically complete. By this, I mean that I considered the Project had reached a stage where a person could live at the Site. Of course, there was still some work to do, and I was still at the Site regularly, but that work was fairly minor, such as cleaning, minor touch-ups and things of that nature.[28]
In late October 2016, I was provided with a letter from [Mr Ng] setting out a list of work that needed to be completed in order to achieve Practical Completion (Remaining Work) and a separate list of work that needed to be completed at some stage, but did not need to be completed in order for Practical Completion to be certified...
The Remaining Work was commenced at the site on 9 December 2016...
By January 2017, the only issue that remained outstanding from the Remaining Work was the installation of the [laundry] floor waste.[30]
Breach of the implied term / suspension of works
...Our client notified the architect ... on 21 July 2014 that practical completion had been reached.
On 21 July 2014 our client rendered the following invoices [the two invoices issued 21 July 2014]
The invoices have been provided to SGA [the architect] for payment, however despite repeated demands for payment, the total amount of $218,791.52 remains outstanding.
SGA has made various allegations in support of a refusal to accommodate our client's requests for payment. In short compass the allegations are that our client is somehow responsible for the shedding of the carpet and the noise emitted by the air-conditioning unit. SGA also say that practical completion has not been reached. (Allegations).
Our client rejects the allegations as entirely baseless...
The ongoing refusal to pay our client by reason of the allegations is unacceptable, and we have now been retained to enforce our client's rights to receive payment.
Unless our client receives payment of $218,791.52 (Debt) within seven (7) days of the date of this letter we are instructed to issue proceedings in the County Court to seek recovery of the debt without further notice to you...
.1 If the works have not reached practical completion by the date for practical completion as adjusted, the architect must promptly notify the contractor [builder] and the owner in writing of the owner's entitlement to liquidated damages.
.2 Up to 20 working days after the date of issue of the notice of practical completion, the owner may notify the architect in writing whether it will enforce its entitlement to liquidated damages against the contactor.
.3 the contractor is liable to pay or allow to the owner liquidated damages at the rate shown in item 24 of schedule one
Owners Corporation fees, rates and utility charges
- 4 December 2014 to 31 January 2015 (pro rata basis,
- 1 February 2015 to 30 April 2017 - $228,628.22
- 1 May 2017 to 2 June 2017 (pro rata basis, 33 days) $5630.39
- 4 December 2014 to 30 June 2015 (pro rata basis 209 days) $7472.68
- 14 August 2015 $ 13,635.50
- 8 August 2016 $13,260.76
- 15 April 2015 to 12 May 2017 $3,311.11
- 10 May 2017 to 2 June 2017 (pro rata basis 24 days) $177.28
- invoices for the period 15 February 2015 (the first
invoice after 3 December 2014) to 14 February 2017 $1,737.40
- invoice dated 16 May 2017 (pro rata from 1 April 2017
So I turned to established, basic principles. I shall first set the scene by noting how the court approaches the question of financial recompense for interference with rights of property. As with breaches of contract, so with tort, the general principle regarding assessment of damages is that they are compensatory for loss or injury. The general rule is that, in the oft quoted words of Lord Blackburn, the measure of damages is to be, as far as possible, that amount of money which will put the injured party in the same position he would have been in had he not sustained the wrong... Damages are measured by the plaintiff's loss, not the defendant's gain. But the common law, pragmatic as ever, has long recognised that there are many commonplace situations where a strict application of this principle would not do justice between the parties. Then compensation for the wrong done to the plaintiff is measured by a different yardstick. A trespasser who enters another's land may cause the landowner no financial loss. In such a case damages are measured by the benefit received by the trespasser, namely, by his use of the land. The same principle is applied where the wrong consists of use of another's land for depositing waste, or by using a path across the land or using passages in an underground mine. In this type of case the damages recoverable will be, in short, the price a reasonable person would pay for the right of user...
The same principle is applied to the wrongful detention of goods... Earl of Halsbury L.C. famously asked in The Mediana [1900] A.C. 113,117, that if a person took away a chair from his room and kept it for 12 months, would anybody say you had a right to diminish the damages by showing that I did not usually sit in that chair, or that there were plenty of other chairs in the room? To the same effect was Lord Shaw's telling example in Watson, Laidlaw & Co v Pott, Cassels and Williamson [1914] UKHL 238; (1914) 31 RPC 104,119. It bears repetition:
" If A, being a liveryman, keeps his horse standing idle in the stable, and B, against his wishes or without his knowledge, rides or drives it out, it is no answer to A for B to say: 'Against what loss do you want to be restored? I restore the horse. There is no loss. The horse is none the worse; it is the better for the exercise.' "
Lord Shaw pre-faced this observation with a statement of general principle:
"wherever an abstraction or invasion of property has occurred, then, unless such abstraction or invasion were to be sanctioned by law, the law ought to yield a recompense under the category or principal... either of price or hirer."
That was a patent infringement case. The House of Lords held that damages should be assessed on the footing of a royalty for every infringing article.
This principle is established and not controversial. More difficult is the alignment of this measure of damages within the basic compensatory measure. Recently there has been a move towards applying the label of restitution towards of this character... However that may be, these awards cannot be regarded as conforming to the strictly compensatory measure of damage for the injured person's loss unless loss is given a strained and artificial meaning. The reality is that the injured person's rights were invaded but, in financial terms, he suffered no loss. Nevertheless the common law has found a means to award him a sensibly calculated amount of money. Such awards are probably best regarded as an exception to the general rule.
The general rule is that damages for anxiety, disappointment and distress are not recoverable in an action for breach of contract.[36] The principal exceptions to that rule are where the contract is one whose object is to provide enjoyment, relaxation or freedom from molestation,[37] and where the damages proceed from physical inconvenience caused by the breach.[38]...
The respondent pointed to several cases in which damages for anxiety, distress and disappointment have been awarded following breach of a building contract giving rise to physical discomfort or inconvenience... However, all these cases involved physical imposition upon the plaintiff, whether by virtue of having to live with offensive odours or a leaking roof, or in unsanitary or dirty conditions, or being obliged to vacate the defective premises... Nothing of this kind was alleged in the present case, where the respondent's premises were intended for the conduct of a business rather than her own occupation.
The respondent also relied on cases in which damages were awarded for inconvenience or discomfort as a distinct head of damage... All of the cases relied upon were claims in tort, rather than contract. However, damages may also be recovered for inconvenience flowing from a breach of contract...
... the issue arose for consideration by the Court of Appeal in Boncristiano v Lohmann.[39] In that case, general damages were awarded for 'inconvenience' occasioned by a builder's breach of contract. The Court took this to include damages for deleterious consequences to health flowing from the physical inconvenience.[40] Winneke P, with whom Charles and Batt JJA agreed, said:
It now appears to be accepted, both in England and Australia, that awards of general damages of the type to which I have referred can be made to building owners who have suffered physical inconvenience, anxiety and distress as a result of the builders' breach of contract, but only for the physical inconveniences and mental distress directly related to those inconveniences which have been caused by the breach of contract.[41]
The case illustrates the difficulty in separating a claim for inconvenience from one for distress and anxiety. But in any event, the respondent's case did not justify the above test. The 'inconveniences which have been caused by the breach of contract' for these purposes are not the time and trouble inevitably spent as a result of dealing with the consequences of any breach of contract... They are the actual disruption and physical imposition resulting from the building and construction works not having been performed as agreed.
"acoustic attenuation and mitigation work" relating to the air-conditioning units. As I understand it, that means works to lessen the intrusive noise of the air-conditioning system. As I understand it, the works included constructing bulkheads around the air-conditioning ducts in the area of the kitchen. 5. Mr Barnett says that during the course of the works he discovered that one of the fan speed controls was hardwired to be set at 'high' and could not be adjusted.[42] Mr Barnett does not have special expertise in air-conditioning, and it became apparent from Mr Barnett's evidence at the hearing that he 'discovered' the alleged incorrectly wired fan, not upon his own inspection of the air-conditioning units, but rather upon examining a report prepared by a sub-contractor engaged by Vault Corporate to carry out works to the air-conditioning units. 6. The subcontractor, Building Systems Asia Pacific Pty Ltd ("BSAP"), was engaged to carry out a proportional air and water balance on the air-conditioning units. As part of their works, BSAP produced a report on tests carried out by it. The report, dated 24 August 2017[43], notes in respect of each air-conditioning unit that the unit was "locked on high-speed" and that BSAP was "unable to reduce the fan speeds on any of the units, currently set on high. Wiring alterations may be required to adjust the fan speeds". The report includes a number of recommendations, one of which being: "Access control wiring for fans & reduce speed to low". 7. On 2 October 2017, Vault Corporate provided a quotation to the owner in a sum of $29,178 to carry out various works, described in the quotation as:
All works to complete that is listed & attached in both Defects list & the BSAP Report reduce unit speed & adjust Pac units.
Please note that some of the units are not assessable how [sic] this price allows for the works required to get access to the units. [44]
[1] Clause N in the contract deals with assessment and payment of progress claims. Clause A8 provides the procedure by which the parties may, by written notification, dispute a certificate, notice, written decision or assessment of the architect, or the architect's failure to issue something. The notice must be provided to the architect within 20 working days of the disputed certificate, notice, decision or assessment. In the case of alleged failure of the architect to issue something, the notice must be provided within 20 working days of the party becoming aware of the architects failure.
[2] Clause C in the contract in respect of the retention sum and its release; clause M for practical completion and defects liability period; clause N for final claim and final certificate
[3] This was Mr Guo's final communication on behalf of SGA in its capacity as architect appointed under the contract. SGA, through Mr Guo, had further brief communications with the builder's lawyers in September 2017 to arrange the transfer of the retention sum held in SGA's account to an independent account created by agreement between the parties' lawyers.
[5] paragraph 39 in the owner's amended witness statement
[7] The alternative method was to place the washing machine on a pedestal and to run a drain from the base of the washing machine to the existing sink drain outlet. This alternative method meant that the builder was not required to raise the entire laundry floor to create fall.
[8] See paragraphs15-20 of Mr Leonard's primary witness statement, page 875-876 in the Tribunal book.
[9] Clause N6 and item 10 in the schedule in the contract prescribe the period for payment of claims as certified by the architect to be seven calendar days after delivery of the architect's certification.
[11] paragraph 27 in the respondent's Amended Points of Defence and Second Further Amended Points of Counterclaim dated 2 February 2018
[12] Sections 34 and 31(n) of the DBC Act
[22] Paragraph 14 in the Further Amended Witness Statement of Andrew Privitelli.
[24] For examples: Justice David Byrne, 'Implied Terms in Building Contracts: Inference or Imputation?' (1998) 60 Australian construction Law newsletter 18, at 22.
Bailey and Bell, Construction Law in Australia, third edition, Thomson Reuters (2011) at 225.
[25] Clause A6.3 in the contract provides that the architect is the owner's agent for giving instructions to the builder, and by clause A7 the architect may issue an instruction in writing at any time.
[26] Under clauses M11 and M12, if the builder fails to rectify defective works or complete necessary works within 10 working days after receiving a written instruction from the architect, or otherwise fails to show reasonable cause for the failure to rectify/complete the works, the owner may use another person to correct the problem at the cost of the builder.
[28] Paragraph 23 of Mr Lazzaro's primary witness statement. Tribunal book page 842
[29] See transcript of evidence 2 February 2018, page 266, line 29.
[30] Further amended witness statement of Mr Privitelli, at paragraphs 25 to 28
[32] The owner's submission cites the statement of Lord Diplock in Gilbert Ash (Northern) Ltd v Modern Engineering (Bristol) Ltd [1974] AC 689 at 717-718
[33] Item 5 in the schedule to the contract describes the contract works as "Fit out of Private Art Gallery"
[34] paragraph 3 and paragraph 43 in Amended witness statement of the owner, Ms Zeng.
[35] The assumption is confirmed at paragraph 'g' on page 2 of Mr Tomaino's report dated 13 October 2017, at page 651 of the Tribunal book. Mr Tomaino also confirmed the assumption when giving evidence.
[36] McLeish JA references Baltic Shipping, 361-3 and 365 (MasonCJ), 380-1 and 383 (Dean and Dawson JJ), 387 (Gaudron J), 405 (McHugh J)
[38] Ibid 365 (Mason CJ), 383 (Dean and Dawson JJ), 387 (Gaudron J), 405 (McHugh J)
[42] paragraph 4 of Mr Barnett's witness statement, Tribunal book page 907
[44] the quotation at page 1113 of the Tribunal book
[46] paragraph 15(b) in the amended Points of Defence and Second Further Amended Points of Counterclaim dated 2 February 2018
Leeda Projects Pty Ltd
Zeng
(1993) 176 CLR 344