[2019] NSWLEC 1366
Land and Environment Court (NSW)
2019-07-29
Original judgment source is linked above.
Judgment
Jurisdiction
Height of building contravention
Floor space ratio contravention
Other matters
Amendments 22 August 2019 - Pursuant to UCPR r 36.16(3B), by the Court's own motion, amend the reference number to the Development Application in Order (6), by:
As a consequence, the final orders made on 6 August 2019, as amended on 22 August 2019, are: (1) The Applicant is granted leave to rely upon the amended material, copies of which are behind Annexure 'A': (2) The Applicant is to pay the Respondent's costs thrown away in accordance with section 8.15(3) of the Environmental Planning and Assessment Act 1979 as agreed in the amount of $70,000.00 within twenty eight (28) days. (3) The written request to depart from the height of buildings standard on the site set out in "Amended Clause 4.6 Variation - HOB" variation request prepared by Planning Ingenuity dated 5 July 2019 pursuant to the LEP is upheld. (4) The written request to depart from the floor space ratio standard on the site set out in "Precautionary Clause 4.6 Variation - Floor Space Ratio" variation request prepared by Planning Ingenuity dated 24 June 2019 pursuant to the LEP is upheld. (5) The appeal is upheld. (6) Development Application No. DA/2018/0139, as amended in accordance with the above plans and documents, for the demolition of existing structures and construction of a thirteen (13) storey mixed use development comprising a residential flat building with sixty-one (61) apartments over 1,110m² of retail and commercial space on the ground and first floor at 32-38 Montgomery Street, Kogarah (Lot B in DP332533 and Lot 47 Section E in DP1397) is approved subject to the conditions in Annexure 'B'. DISCLAIMER - Every effort has been made to comply with suppression orders or statutory provisions prohibiting publication that may apply to this judgment or decision. The onus remains on any person using material in the judgment or decision to ensure that the intended use of that material does not breach any such order or provision. Further enquiries may be directed to the Registry of the Court or Tribunal in which it was generated. Decision last updated: 22 August 2019
Lateral Estate Pty Ltd
Georges River Council