[2025] QCAT 227
General information, not legal advice.
Queensland Civil and Administrative Tribunal
2025-06-06
Original judgment source is linked above.
CONTRACTS - BUILDING, ENGINEERING AND RELATED CONTRACTS - THE CONTRACT - CONSTRUCTION OF PARTICULAR CONTRACTS AND IMPLIED CONDITIONS - OTHER MATTERS - where the parties entered into a domestic building contract - where the builder mistakenly supplied the wrong turf for landscaping - where the builder was advised too late to be able to readily remove the turf and use it elsewhere - where the owners brought an action to claim the cost of removal of the turf and supply and relaying of the correct species of grass - whether the remedy sought was reasonable - where the owners claimed liquidated damages for delay - where the refusal of extension of time sought preceded the receipt of the written request - where no reasons for refusal of the extension of time were given - where subsequent correspondence suggested the extended time for completion was accepted - where the owners limited their claim for liquidated damages to a specific period and therefore there was no award made for delay beyond the specific period
Karacominakis v Big Country Developments Pty Ltd [2000] NSWCA 313
Lazicic v Rossi [2024] NSWSC 777
Tabcorp Holdings Ltd v Bowen Investments Pty Ltd [2009] HCA 8
Walker Group Constructions Pty Ltd v Tzaneros Investments Pty Ltd [2017] NSWCA 27
Neither excessive diligence nor perfection is required of a claimant: note eg Karacominakis v Big Country Developments Pty Ltd [2000] NSWCA 313; (2000) 10 BPR 18,235 at [187]. As was said in Lodge Holes Colliery Company Ltd v Wednesbury Corporation [1908] UKLawRpAC 40; [1908] AC 323 at 325 by Lord Loreburn LC:
Now I think a Court of justice ought to be very slow in countenancing any attempt by a wrong-doer to make captious objections to the methods by which those whom he has injured have sought to repair the injury. ... Errors of judgment may be committed in this as in other affairs of life. It would be intolerable if persons so situated could be called to account by the wrong-doer in a minute scrutiny of the expense, as though they were his agents, for any mistake or miscalculation, provided they act honestly and reasonably.
187. A plaintiff who acts unreasonably in failing to minimise his loss from the defendant's breach of contract will have his damages reduced to the extent to which, had he acted reasonably, his loss would have been less. This is often misleadingly referred to as a duty to mitigate, although the plaintiff is not under a positive duty. The plaintiff does not have to show that he has fulfilled his so-called duty, and the onus is on the defendant to show that he has not and the extent to which he has not (TCN Channel 9 Pty Ltd v Hayden Enterprises Pty Ltd (1989) 16 NSWLR 130). Since the defendant is a wrongdoer, in determining whether the plaintiff has acted unreasonably a high standard of conduct will not be required, and the plaintiff will not be held to have acted unreasonably simply because the defendant can suggest other and more beneficial conduct if it was reasonable for the plaintiff to do what he did (Banco de Portugal v Waterlow and Sons Ltd [1932] UKHL 1; (1932) AC 452; Pilkington v Wood (1953) Ch 770; Sacher Investments Pty Ltd v Forma Stereo Consultants Pty Ltd (1976) 1 NSWLR 5).
186. The general principle on which damages are recoverable by a building owner for breach of a building contract is the cost of making the work or building conform to the contract, subject to the qualification that not only must the work be necessary to produce conformity, but it must also be a reasonable course to adopt: Bellgrove at 617-618; Tabcorp Holdings Ltd v Bowen Investments Pty Ltd (2009) 236 CLR 272; [2009] HCA 8 at [15]. In the latter case, the court indicated that the test of unreasonableness is only to be satisfied by fairly exceptional circumstances: at [17].
17. ...(I)n Bellgrove v Eldridge this Court pointed out that there was a qualification to the rule it stated in regard to damages recoverable by a building owner for the breach of a building contract. "The qualification ... is that, not only must the work undertaken be necessary to produce conformity, but that also, it must be a reasonable course to adopt."[25] The example which the Court gave of unreasonableness was the following[26]:
"No one would doubt that where pursuant to a building contract calling for the erection of a house with cement rendered external walls of second-hand bricks, the builder has constructed the walls of new bricks of first quality the owner would not be entitled to the cost of demolishing the walls and re-erecting them in second-hand bricks."
That tends to indicate that the test of "unreasonableness" is only to be satisfied by fairly exceptional circumstances. The example given by the Court aligns closely with what Oliver J said in Radford v De Froberville, that is, that the diminution in value measure of damages will only apply where the innocent party is "merely using a technical breach to secure an uncovenanted profit." It is also important to note that the "reasonableness" exception was not found to exist in Bellgrove v Eldridge. Nothing in the reasoning in that case suggested that where the reasoning is applied to the present circumstances, the course which the Landlord proposed is unnecessary or unreasonable.
... was the wrong species for the type of ground that we had, so it (the weeds) was growing out of control.[1]
My concern moving forward, if we were to accept that two and a-half thousand dollars, would be that we would still be dealing with the weeds that came with the provided Couch.[2]
[4] The communication is dated 23 January 2022 and the author is Ms Langham but there is no recipient noted - there is an email address apart and above the message which perhaps also suggests the message was sent (for the first time) or resent to the builder on 28 October 2022.
Langham & Anor
Verticorp Pty Ltd [2025] QCAT 227
(1989) 16 NSWLR 130
(1976) 1 NSWLR 5
(2009) 236 CLR 272