[2017] ACAT 102
ACT Civil and Administrative Tribunal
2017-12-05
Member Daniel, Member Robinson, Member Orr
Original judgment source is linked above.
... engage a suitably(sic) contractor to complete the scope of work as noted above [the Lewis scope]. The Executive Committee will contribute an amount up to $6,785 incl. GST [BEC quotation] on receipt of a tax invoice from an appropriately qualified contractor and subject to inspection by Adrian Lewis that works have been completed to a satisfactory standard.[4]
3.4 We observe that the balcony has no visible upturns of membranes and/or skirting tiles present.
3.6 We noted a floor waste receptacle to be present at the southern end, adjacent to the air conditioner unit.
3.7 We confirmed the floor waste receptacle to be blocked with debris. No water was escaping.
3.8 The subject balcony has a large overflow relief outlet which was not found to be operational at the time of inspection as the water would need to pool extensively in order for this receptacle to come into play.
3.9 The removal of damaged skirting and subsequent electronic moisture encountered test revealed excessively high moisture levels within the masonry substrate behind the already damaged components.
3.10 The removed linings and skirting revealed the presence of mould which is consistent with long term water ingress.
3.12 The direct area of internal damage correlates exactly to the rendered wall which was found to be saturated as a result of pooling water on the subject balcony. It is reasonable to assume that this wall, being devoid of any visible upturn of balcony membrane or skirting tile, combined with the fact that the render was found to be slightly spalling with evidence of failed paintwork, would be allowing water to ingress and rise up the otherwise unprotected masonry where it then saturates the directly affixed plasterboard linings and skirting.
3.13 We immediately cleared the surface drainage receptacle of the subject balcony and shortly after this, all pooled water had evacuated from the subject balcony.
3.14 A close inspection of this drainage outlet receptacle revealed it to be blocked with debris which had caused the water to pool heavily on the balcony.
4.1 As the subject balcony was found to be excessively inundated with pooling water and the balcony has no visible upturn of balcony membrane or skirting tiles we conclude that the localized damage found to the interior of the subject unit is directly resultant of saturation of the masonry wall and directly affixed plaster linings and skirting trims.
4.2 A secondary conclusion (not yet proven due to total saturation of the subject masonry) is that the window and sliding door installation may not be properly flashed and as a result of inadequate anti capillary measures moisture which accumulates on the external frames and tracks may not be correctly draining away. The aluminium sub sill and sill flashing of the aluminium sliding door may not have the correct anti capillary breaks which are causing moisture ingress to the corner extremities where it will then be able to wick across the subject masonry wall.
4.3 Due to the overwhelming amount of water found on this balcony we cannot form any additional conclusions other than the water ingress at the perimeter of the balcony and masonry wall.
6.3Remove adjacent partitions so as to allow full membrane installation.
6.5 Revise the current waste receptacle and ensure that it has correct control leak flanges and is adequate for the catchment.
6.6 Install new graded bedding to provide adequate fall away from the building and to the installed waste receptacle.
6.7 Install approved waterproofing membrane ensuring all upturns are installed in accordance with relevant standards.
6.8 Ensure that the waterproofing membrane system has all necessary bond breaking measures and is designed to cater for the differential movement of adjacent elements.
6.9 Supply and install new floor and skirting tiles ensuring all upturns and corners are sealed in accordance with relevant standards.
6.10 During the course of the work it is suggested that the sub sill flashings and anti-capillary measures are in fact installed and functioning.
6.11 Following on from this scope of work it is suggested that monitoring be conducted to ensure rectification has been successful. If further water ingress occurs at the localized area adjacent to window and door frames these units may require removal with a view to a revision of flashings and anti-capillary measures, which may be required.
The report included 14 photographs of the balcony, the external wall and the interior of the unit.
to accept the (RBS) quote subject to ensuring the quote including refitting the air conditioning unit and can be done in a reasonable time frame. A quote to be sought from Reliance for the internals to unit 3 ... The report relevant to unit 3 can be released to the owner.
Please note that to avoid further inconvenience to the occupant we would suggest that the quote for internal repairs be held in abeyance until such time as the external balcony repairs commence in early November (Pending EC approval for external access to the balcony).
The internal repairs that I sighted are not major and are unable to be commenced until such time as the externals are completed anyway?
We are still awaiting your further update from the EC on the quoted external scaffold access lift quote for this balcony repair.
I would reclassify the outdoor/indoor works with the indoor being the priority, given that I have a huge exposed mouldy rotten part of my wall that needs fixing straight away. ... As far as access goes for the outside we have made arrangements that suit all, however the inside is getting worse since the builder took the big scoop out of the wall, its all started to crumble and the cracks and mould are exposed up the wall.
...confirmed that no internal repairs were to be done until the external repairs were completed and the water ingress problem resolved.
Link is to write to the owner of unit 3 to clarify the EC position and to ensure that the owner is aware that under the Unit Titles (Management) Act 2011 that it is a requirement that the owner allow/arrange access so the external repairs can be completed in a timely manner.[13]
To expedite this matter the works, being the balcony repairs as quoted and agreed by the Executive Committee including the internal repairs be conducted shortly thereafter as instructed by the Executive Committee. We request that access be provided so the works can be completed.
To facilitate the works Reliance (cc'd) will liaise with you in writing i.e. via email keeping Link cc'd on all correspondence. Reliance have also suggested that works could be scheduled from mid-February.
Therefore we request that you contact Reliance to schedule the works keeping Link cc'd in on the correspondence.
Please Note: we advise if access is not provided at any time after an agreed date/time has been made any additional costs will be forwarded to you for reimbursement to the owners corporation as allowed under section 31 of the Unit Titles (Management) Act 2011.
We thank you in advance for your assistance and cooperation in this matter.
This should have been investigated in the first instance when it was reported to Links in Oct 13, it would have also avoided the extent of the repair works required given that the ongoing damage that is now critical.
...have severe reservations that the occupant will not be placated regardless of any future repairs or inspections that are completed. The relationship between the occupant and strata management is currently compromised and Reliance Building Services does not wish to be involved in such a hostile environment.[17]
At this stage we do not see any requirement to totally demolish the balcony tiles, or to remove and reset the windows. A simple and inexpensive sequence of repair should be tried in the first instant to see if the water entry can be blocked. We suggest the following:
It will be necessary for the owner/occupier to control internal moisture levels within the unit and a dehumidifier will be required to prevent the extent of condensation in the unit that we suspect has been occurring.
Whilst we have scoped the work to provide an edge seal to the balcony step up it is obvious that in the rain periods just experienced the balcony floods as the slope is inwards to the step up. It may be an appropriate time to consider retiling this balcony correctly. Let me know asp (sic) if you are in agreement and I will get this work requoted.
It was noted that the issues with the balcony works have been going on for some time. Two contractors as well as accompanying project managers/engineers have now declined to do the work due to access and other issues. The previous Executive Committee instructed Link Strata Management after discussion with the Office of Regulatory Services to notify the owner (email sent on 6 August 2014 of Unit 3) that it would now be up to them to organise a contractor and access to complete the works within the budget as quoted by the previous contractor. If the unit owner decides that they would like additional works completed that would go over this amount, these costs would be the responsibility of the unit owner.
Action: Unit 3 owner to organise a contractor and provide access to complete works within approved budget.
(1) Remove sufficient floor tiles to achieve adequate fall to the balcony drains, those tiles remaining will need to be cleaned and primed to insure good adhesion.
(2) Reset floor wastes with control leak flanges to correct levels.
(3) Provide new bedding with falls away from the building, suggest 1:60 fall.
(4) Install proprietary brand recognised waterproofing and flashings to best practice including upturns to neighbouring balcony partitions and bond breaks to building,
(5) Retile floor and provide skirting tiles as necessary sealing all change of tile planes with a waterproof flexible sealant to joints.
(6) Remove aluminium window trims and check for any moisture penetration at sides and sills, check also for any weep holes or bond breaks.
(7) Whilst the blockwork wall complies with the building code for such elements it is thought possible moisture may be migrating across the cavity via the blockwork internal webbing, with the plasterboard adhered directly to the blockwork any moisture migration will affect the plasterboard, to this end waterproofing and repainting of this external wall is recommended, this work will need to be carried out whilst the window trims are removed and prior to balcony returns being installed.
(8) Interior rectification work should be left until after several wet weather cycles and no further moisture readings can be obtained.
Supply labour and materials to prepare and paint external walls in Emiclad membrane.
Repaint areas to match existing external wall colour.
Remove and repair existing damaged plasterboard and skirtings.
Supply labour and materials to prepare external balcony.
Supply and install etched primer, waterproof membrane and retile total balcony area.
...have decided that due to the following reasons, they are willing to contribute $6,875.00 to the cost of repairs outlined in the quote by H & D Developments Pty Ltd:
...please forward this email on to the BC Committee as a last opportunity for the BC Committee to make things right and fund the total cost of repairs to Unit 3 based on the information provided by 3 independent building specialists. The amount that the BC Committee continue to base their argument on is for works that would have been non compliant, would not have fixed the issue and would have been carried out by the wrong specialist. The new quotation and building reports that the BC Committee requested have been provided by the correct specialist i.e. fully qualified building inspector, the works will be compliant and will fix and repair the damage sustained by water damage permanently. There is absolutely no truth in the reasons that the BC Committee have provided to not fully fund the works, nor is it reasonable or fair. We are all unit owners and we all pay a fee for this exact reason amongst other maintenance works. ...
As far as the reasoning provided by the BC Committee to not fund the total repair works required to Unit 3 are unfounded. The following email provides the specific reasons as to the non compliance of the report provided by the Engineer. It also confirms that condensation and the list of other unfounded comments are not consistent with any of the building reports provided by fully qualified Building Specialists...[27]
Engineer report from Adrian Lewis asked for the slab edge only to be waterproofed and No treatment to the walls. As determined by the two building inspector reports. The Water is entering the building from the external wall junction and the surface area of the external walls.
Because the construction is solid concrete block the moisture is travelling through the wall and effecting the plasterboard.
The water damage inside has not been caused by condensation on the windows.
...in relation to you being instructed by the BC Committee to cease all funding for works to be carried out on my unit, including those that were approved by the BC Committee last week. As I will need to advise the Contractors that works will be put on hold until further notice. As it is I have tried to resolve things and provided every opportunity for the BC Committee to abide by their obligations under the Act and allow these works to progress and to fund those works and the contractors that they authorise to provide information etc. ...[29]
We spoke yesterday regarding the repairs to your unit.
The Executive Committee at this time have decided that until the situation in regards to payment of the repairs and liability is sorted they will not give approval for the works to proceed.
We are instructed by this letter to provide you with a final opportunity to engage with the Owner in relation to this matter.
In our view it is plain from the various reports[32] that the water ingress affecting the Unit is caused by a failure to adequately waterproof that part of the external wall which forms common property (pursuant to section 15 of the Unit Titles Act 2001). It is uncontroversial that the Owners Corporation must maintain the common property and this statutory duty is well established.
(b) Whether the costs of the external works are to be apportioned between the parties, and if so, how?
From the balcony, you know, the water was pooling; and from the inside, it all started to rot and mould started to show and just - it was - it was full on, both sides.
...So you facilitated that access at those occasions? ---Yes. I've never prevented access.
...There was - with Peter Leary at that time, I just commented, as an option ... and asked if - there was any option that the works that they were going to do on the balcony, if they - if they were going to do those first. If that was the case, was - was there any option for the external works to be done other than coming through the front door, because I was expecting to go to hospital at any time, and I just wanted to see if there was - that's all.[44]
... I had just asked if there was an option for alternative works to be carried on the - externally, because if I was in hosp-, I couldn't give access. That was all. So - but it didn't matter in the - I mean, I still would have allowed access, it was just an option I was putting forward.[45]
A. No. It was more that I didn't know that if I was going to be there or not. And if I wasn't going to be there. Then yeah, obviously they're things that I would have to had done, you know, I've got a pet, I would have organised some things like that.
Q. Well, certainly Mr Dragovich hasn't said anything about hospital visits or potential hospital visits?
Q. Well, I don't know. Did you mention it to them?
Q. I thought you said you mentioned it to Mr Leary's tiler?
A. Look, I have mentioned it verbally, yes. Not - not in writing. Yeah. But you know, yeah, I - I was on call, I - that was the issue at the time - was just, okay, well, how do we coordinate this. You know, it was that if I had to go in (to hospital) at short notice, then I needed just to have some advice - some notice. That was all.
And I'll say that we, as a building company actively sought for approval for a different method (external access) and from my understanding Link proposed that to the Owners Corporation. I did not get any feedback on that but I will give an opinion that accessing one single balcony by means of scaffold is not a cost-effective solution so I really did not expect to get approval for scaffold or boom lifts or the like.[49]
Janelle and Bridget that the preferred access method was definitely on the exterior. So that was second visit number one. Second visit number two was with my estimator, Mr Dragovich who is the drafter of the Reliance quotation where we once again tried to placate a method of internal access and to reassure the parties that - you know - we would execute as promptly as possible. We didn't receive any feedback following on from that second visit until such time as we learned that the work was not ultimately going to be awarded to us.
A. Link Strata Management said to close your file.
Q. Do you have evidence of the denial of access? Can you give me a document saying that we turned up on this date, and we had no access? From Reliance?
Q. I want to see specific evidence suggesting that we could not attend on this date, or we attended on this day and no-one let us in?
A. I do not have a document that says we attended on date X and they wouldn't let us in.
A. What I have instead is documentation of a persistent pattern of refusal of access on the part of the applicant.[51]
To expedite this matter, being the balcony repairs as quoted and agreed by the Executive Committee including the internal repairs be conducted shortly thereafter as instructed by the Executive Committee. We request that access be provided so the works can be completed. To facilitate the works Reliance (cc'd) will liaise with you in writing i.e. via email keeping Link cc'd on all correspondence. Reliance have also suggested that works could be schedule from mid-February.
Therefore we request that you contact Reliance to schedule the works keeping Link cc'd in on all the correspondence.
Please Note: we advise that if access is not provided at any time after an agreed date/time has been made any additional costs will be forwarded to you for reimbursement to the owners corporation as allowed under section 31 of the Unit Titles (Management) Act 2011.
...requires specialist testing to identify just how far gone it is, who's not to say that the wall will completely collapse with the jack hammering etc. It puts everyone at risk.
they have severe reservations that the occupant will not be placated regardless of any future repairs or inspections that are completed. The relationship between the occupant and the strata management is currently compromised and Reliance Building Services does not wish to be involved in such a hostile environment.
As a second contractor has now advised us they cannot complete the works due to access and other issues, the Executive Committee are not willing to engage any more contractors to complete this work on your behalf.
Q. Could I suggest to you that the contractor, Built Environment Construction, stood down from the job because they couldn't be guaranteed access?
I was concerned because it was right near the electricals, and the water was leaking under the carpet, on top of the carpet, there was mould everywhere. And it had developed into a big hole in the wall, exposed hole, and these things had rotted and come away. And Peter said "Look, you need to go back to Links," he said, "You need to ask them to get that diagnosed, find out where the water leak is coming from. Get it repaired. Once it is repaired" he said, "Contact me within a couple of weeks and I'll come out and do the balcony."[60]
I have been advised that the onus is on the body corporate to put me up in an alternative residence while the works are being undertaken.
... were trying to make arrangements to get other tradespeople there to pull the window out and things like that. Everyone there at the same time. And at the end of the day, they couldn't get everyone there at the same time. And yeah, they had their own conflicts, and they just picked up their things and off they went.[61]
The Tribunal is not satisfied that it was the applicant who required the work be conducted by marshalling all trades at the same time or sequentially.
have severe reservations that the occupant will not be placated regardless of any future repairs or inspections that ae completed. The relationship between the occupant and strata management is currently compromised and Reliance Building Services does not wish to be involved in such a hostile environment.[62]
At a meeting between the contractor, tradesperson and yourself on Friday 25 July 2014 the works were agreed upon and timelines were established. Since that date the contractors have not been able to resolve your concerns regarding tile selection and access.[63]
Given the need to have the works completed the Executive Committee has requested that you engage a suitably (sic) contractor to complete the scope of work noted above. The Executive Committee will contribute an amount up to $6,785 incl. GST on receipt of a tax invoice from an appropriately qualified contractor and subject to inspection by Adrian Lewis that the works have been completed to a satisfactory standard.[64]
... it may be an appropriate time to consider retiling this balcony correctly. Let me know asp if you are in agreement and I will get this work requoted.[67]
I want to understand why it is that the body corporate is insistent upon accepting a half baked scope of work to rectify this damage, when your expert, your very expert that you have called today, has said that anything less than his full scope of works, wouldn't work. Would not fix the job.[68]
(c) Whether the applicant is entitled to orders in relation to the internal works?
It is critical to the respondent's case that it make good its contention that it owed the appellant only a statutory duty under the SSM Act in relation to its management and repair of the common property. It is only if that premise is made good that the respondent can rely on the holding in Thoo that Ch 5 of the SSM Act provides exclusive remedies for breach of an owners corporation's statutory duty as an answer to the appellant's claim in nuisance, and can argue that s 226 is not engaged on the ground that the appellant cannot rely upon a duty arising apart from the SSM Act. For the reasons which follow I do not accept that premise. Rather, an owners corporation, as legal owner of the common property, may owe a general law duty of care or a general law duty not to create or to abate a nuisance, and not merely a statutory duty that can be enforced only through the mechanisms provided in Ch 5 of the SSM Act_. Contrary to the view of the primary judge, decisions of this Court do not support the view that such a general law duty is excluded. To the contrary, the decision in Ridis_ and in Owners - Strata Plan 21702 v Krimbogiannis [2014] NSWCA 411 proceed on the assumption that such general law duties can exist in addition to the statutory duty of repair. Thoo does not decide to the contrary. Neither the SSFD Act[74] nor the SSM Act negate the rights of a lot owner or occupier of a lot to enforce an owners corporation's duty in respect of the management or repair of the common property that is owed to an owner or occupier of a lot in that capacity. The appellant's right to sue at common law is preserved by s 226. In my view the appeal should be allowed.
The Court of Appeal found that there was nothing in the SSM Act which indicated a legislative intention to affect a lot owner's common law rights to sue the owners corporation in common law in relation to its management of the common property. A guiding factor in this reasoning was section 226 of the SSM Act (which is found in Chapter 7) which expressly preserved a lot owner's right to recover damages at common law for breach by an Owners Corporation of a common law duty.[75]
There is no provision in the UTMA that is the equivalent to section 226 of the SSM Act. This section states that there is nothing in the SSM Act that derogates from the rights or remedies that an owner or an owners corporation may have, in relation to any lot or common property, apart from the SSM Act. In McElwaine (at [71]), the Court of Appeal held that section 226 of the SSM Act makes it clear that unless there was something in the SSM Act or the Strata Titles (Freehold Development) Act 1973 (NSW) that excludes a lot owner's right to sue the owners corporation in nuisance, section 226 of the SSM Act expressly preserves that right. There is no such express preservation of the right to sue or seek a remedy at common law under the UTMA.
In the absence of such a provision, the question is whether the legislative intent in the UTMA is that a unit owner may or may not sue the Owners Corporation and seek a remedy external to the UTMA. If the legislative intent was such, a provision similar to section 226 of the SSM Act would have been enacted in the UTMA.[76]
... there is no apparent reason why an owners corporation could not be liable for damage caused to an owner's property under the usual principles of common law negligence.
[46] there is little doubt that an owners corporation has a sufficiently proximate relationship with unit holders that it owes a duty of care to take reasonable care to prevent reasonably foreseeable risk of damage, including damage to personal property.
45. In order to succeed in his claim for negligence, the applicant had to establish three things:
(a) that the owners corporation owed him a duty of care;
(b) that it breached that duty by failing to reach the standard of care required of a reasonable owners corporation; and
46. There could be little doubt that an owners corporation has a sufficiently proximate relationship with unit holders that it owes a duty to take reasonable care to prevent reasonably foreseeable risks of damage, including damage to personal property. Therefore, the owners corporation owed the applicant a duty of care.
47. The difficulty for the applicant is that he had little evidence upon which it could be concluded that the owners corporation breached that duty.
48. Section 42 of the Civil Law (Wrongs) Act 2002 sets out general principles relating to standard of care. It requires the applicant to show that a reasonable owners corporation, in the respondent's position, in possession of all the information that it either had, or ought reasonably to have had, at the time of the incident, would have done something more that what it did.
49. The 'time of the incident' would be the time when the cables were damaged. There is no evidence as to when this was, other than prior to the applicant engaging an electrician. Consequently, the applicant was required to establish either that the owners corporation should have known about the rodents, for example by conducting inspections, or that it should have taken precautions against rodents anyway.
50. In this regard, section 43 of the Civil Law (Wrongs) Act 2002 further provides that:
_A person is not negligent in failing to take precautions against a risk of harm unless - _
(a) the risk was foreseeable (that is, it is a risk of which the person knew or ought to have known); and
(c) in the circumstances, a reasonable person in the person's position would have taken those precautions.
(2) In deciding whether a reasonable person would have taken precautions against a risk of harm, the court must consider the following (among other relevant things):
(a) the probability that the harm would happen if precautions were not taken;
(c) the burden of taking precautions to avoid the risk of harm;
(d) the social utility of the activity creating the risk of harm.
53. This does not mean that the owners corporation has no obligations in relation to rodents. Even in the absence of evidence of an actual rodent infestation, had the owners corporation been aware, or should it have been aware, of a foreseeable and not insignificant risk of harm if there were rodents, then it likely would have been required to take some mitigating action. ...
It is possible that [a claim in negligence] could be made against the owners corporation.
This suggests that section 129(1)(d) may not be a limitation on money claims...
This issue has been raised so many times over the years. ... This was inspected some 15 months to 2 years ago and I continue to verbally ask for the repair of these issues which are now getting beyond compliance and yet no action has been taken.
What does it take to get the basic maintenance rectified in this development? The type of maintenance that is going to cause the wall to collapse and electrical compliance issues to occur without notice.
3.9 The removal of damaged skirting and subsequent electronic moisture encounter tests revealed excessively high moisture levels within the masonry substrate behind the already damaged components.
3.10 The removed linings and skirting revealed the presence of mould which is consistent with long term water ingress.
3.12 The direct area of internal damage correlates exactly to the rendered wall which was found to be saturated as a result of pooling water on the subject balcony. It is reasonable to assume that this wall, being devoid of any visible upturn of balcony membrane or skirting tile, combined with the fact that the render was found to be slightly spalling with evidence of failed paintwork, would be allowing water to ingress and rise up into the otherwise unprotected masonry where it then saturates the directly affixed plasterboard linings and skirting.
(d) Whether the applicant is entitled to associated costs claimed for obtaining reports and quotations, namely Lawrie Paul - $450.00, HD - $550.00 and GIO Assessment - $300.00?
(e) Whether the applicant is entitled to orders for the respondent to pay her legal fees and disbursements?
(1) The parties to an application must bear their own costs unless this Act otherwise provides or the tribunal otherwise orders.
(a) if the tribunal decides an application in favour of the applicant, the tribunal may order the other party to pay the applicant--
(ii) any other fee incurred by the applicant that the tribunal considers necessary for the application; or
Note An example is part of the Act, is not exhaustive and may extend, but does not limit, the meaning of the provision in which it appears (see Legislation Act , s 126 and s 132).
(f) Whether consequential orders should be made that the applicant facilitate access to her unit for the purpose of the external works being carried out?
[14] Transcript of proceedings page 41, lines 19, 20
[32] The Leary Report, the Lewis Report and the Paul Report, Ibid page 327-328
[33] Respondent's Submissions at [13]
[43] Transcript of proceedings page 15 lines 5-7
[51] Ibid 103 lines 34-35, lines 41-44, page 104 lines 1-2
[54] ACT Civil and Administrative Tribunal Act 2008 section 8, which provides that the Tribunal need not comply with the rules of evidence
[59] Transcript of proceedings page 46 lines 10 - 16
[68] Transcript of proceedings page 103 lines 7 - 10
[74] Strata Titles (Freehold Development) Act 1973 (NSW)
[75] Respondent's supplementary submissions lodged 6 October 2017 at [8]
[77] Castro v Owners Unit Plan No 246 [2016] ACAT 111
[78] Garcia v The Owners - Units Plan 10 [2017] ACAT 91
KIRK
THE OWNERS - UNITS PLAN NO 2992
Legislation cited: ACT Civil and Administrative Tribunal Act 2008 ss 18, 48
Strata Scheme Management Act 1996 (NSW) ss 62
Unit Titles (Management) Act 2011 ss 9, 16, 24, 31, 102 125, 129
Cases cited: Bennett v Owners Units Plan 932 (Unit Titles) [2016] ACAT 57
Castro v Owners Unit Plan No 246 [2016] ACAT 111
Garcia v The Owners - Units Plan 10 [2017] ACAT 91
McElwaine v The Owners Strata Plan Number 75975 [2017] NSWCA 239
Ridis v Strata Plan 10308 [2005] NSWCA 2
The Owners Strata Plan 50276 v Thoo [2013] NSWCA 270